• Bond construction timeline - Tobias

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $3.0 million

    Summer 2021

    • Improvements

    Tobias' entry vestibule will be renovated to improve monitoring and limit entry into the building. Other safety and security upgrades include security cameras, interior door locks, and alert/warning systems.

    Summer 2022

    • Parent/Bus Dropoff Areas

    Parking lots and parent/bus dropoff areas will be remodeled in summer 2022. The traffic pattern of the new dropoff areas will separate personal vehicles from the buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

    COMPLETED

    • Roofing, Flexible Furniture

    The Tobias building's roof was renovated in summer 2018. New flexible furniture (FFE) was delivered to classrooms; this will help stimulate student engagement and learning.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Roofing: Rick Cunningham
    • FFE: Karyn Rainone
    • Entry vestibule: John Abel

    Architect/Engineer

    • Roofing: WTI General Contracting
    • Entry vestibule: Axis Architects

    General Contractor

    • Roofing: Anderson Roofing
    • FFE
      • McDowell-Craig (desks)
      • School Specialty (seating)
    • Entry vestibule: tbd - bid date Feb. 23, 2021*

     

    *grouped with W.L. Henry, Minter Bridge, and Tobias entry vestibule projects