• aerial photo of Lenox campus

     

    construction timeline for Lenox

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Total costs: $6.2 million

    COMPLETED

    • Perimeter Fencing/Gates

    Scope was added to install fencing and gates in summer 2022 to complete the perimeter around the building to enhance security and separate the play field and students from vehicular traffic in the parking lot.

    • Security Upgrades

    In addition to entry security, Lenox's existing security systems were enhanced and upgraded in the 2020-21 school year, including: security cameras, card key access, strobes, and visual warning inside and outside the building.

    • Building Renovations

    During summer 2019, Lenox received seismic, roofing and HVAC upgrades. Heat, air conditioning and direct digital controls (DDC) will be added to the upgraded HVAC system.

    • Parent/Bus Dropoff

    New parent/bus dropoff areas, completed in August 2019, will ease traffic backup along Rock Creek Blvd., with the goals of increasing the safety of pedestrians and drivers as well as the efficiency and flow of traffic.

    • Flexible Furniture

    New flexible furniture (FFE) was delivered to the school in summer 2019. Research has shown that this type of furniture helps stimulate student engagement and learning.

     

Contractors

  • Project Manager

    Cornerstone Management Group

    • Renovations/Dropoff: Rick Cunningham

    Architect

    • Renovations: Mahlum Architects

    Contractor

    • Renovations/Dropoff: Par-Tech Construction
    • HVAC/Mechanical: Sure-Flow HVAC
    • Roofing: Tremco
    • FFE
      • McDowell-Craig (desks)
      • School Specialty (seating)