Scope of Work
-
Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $8.5 million
May 2020 - January 2021
- New Gym
A new gymnasium will be built on the campus, enabling dedicated use for PE and activities, separate from the cafeteria. The gym will be constructed to "immediate occupancy" seismic standards, enabling it to serve, as needed, as an emergency shelter resource for the community in case of a major earthquake. Construction is expected to begin in May 2020 and conclude in January 2021.
- Parent/Bus Dropoff Area Upgrades
Improvements will be made to the parent and bus dropoff areas, including an extension of the existing lot. The new design will separate buses from regular vehicular traffic to improve traffic flow, pedestrian and driver safety, and efficiency of dropoffs.
- Safety/Security Upgrades
Minter Bridge's existing security systems will be upgraded and enhanced after all other renovations are completed. These improvements include security cameras, interior door locks, alert/warning systems, and other safety measures. Work is expected to be completed by early 2021.
Summer 2021
- Upgrade Canopy Roofs
The existing canopy roofs will be upgraded in summer 2021 along with new aluminum coatings.
- Upgrade Entry Vestibule
The vestibule will be renovated to upgrade the capability to monitor and limit entry into the building.
Completed Projects
- New Modular Building
The existing portables were replaced with a new, permanent modular building that includes two classrooms and a restroom. This work was completed in summer 2020.
- Improvements
In summer 2020, renovations were made to the existing building that included seismic upgrades and new roofing, as well as the addition of heating to the existing HVAC system.
- Classroom Walls and Doors
Walls and doors were constructed around classrooms to improve the teaching environments, and reduce noise and distractions. This project was completed in August 2019.
- Flexible Furniture
New flexible furniture (FFE) was delivered to Minter Bridge classrooms in summer 2019. Research has shown that this type of furniture helps stimulate student engagement and learning.
Current Contractors
-
Project Manager
Cornerstone Management Group
- Gym, modular, dropoffs: Casey Cunningham
- Canopy roofs: tbd
- Entry vestibule: John Abel
Architects/Engineers
- Gym: Mahlum Architects
- Canopy roofs: Tremco Roofing
- Entry vestibule: Process-PDX
General Contractor
- Gym: Five Star Builders
- Canopy roofs: tbd - bid day Jan. 19, 2021
- Entry vestibule: tbd