• aerial of WL Henry campus

  • construction timeline for WL Henry

     


Scope of Work

  • Please note that project renderings, costs and schedules may change due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $11.6 million

    Spring 2021

    • Security Upgrades

    After completion of the gym, W.L. Henry's existing security systems will be upgraded with such measures as security cameras, interior door locks, and alert/warning systems; this work is expected to be completed in spring 2021.

    • Replace Covered Play Posts

    Construction will take place in the spring to replace a few of the posts in the covered play structure. These were found to be weakened.

    Summer 2021

    • Upgraded Entry Vestibule, Add AC

    Better monitoring and limited entry into the building will result after upgrades to the entry vestibule. Also, HVAC upgrades continue with the addition of air conditioning in the cafeteria and library.

    COMPLETED

    • New Gym

    An exciting addition to the campus is a new gymnasium that enables dedicated use for PE and activities, separate from the cafeteria, and which can serve as an emergency shelter for the community in case of a major earthquake. Construction was completed in March 2021; watch the virtual tour.

    • Building Improvements

    During the summer of 2020, the existing building underwent renovations that included seismic, HVAC and roofing upgrades.

    • Parent/Bus Dropoff Areas

    From June to August 2020, the parent/bus dropoff areas was modified to separate personal vehicles from buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

    • Flexible Furniture

    New flexible furniture (FFE) was delivered to W.L. Henry classrooms in summer 2019. Research has shown the furniture to promote engagement and learning.

    • Playground

    W.L. Henry's playground was installed on a safer, rubberized tile surface in summer 2018, and students can now play rain or shine on a new, synthetic turf area.

    • Modular Building

    Due to permitting delays, W.L. Henry's new modular building, originally scheduled for summer 2018, was installed in November 2018. The permanent building houses three classrooms and includes a bathroom facility. The modular replaces the temporary, two-classroom, no-bathroom portable, which was demolished on March 23, 2018.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Modular building, playground: Rick Cunningham
    • Gym/renovations: Rick Cunningham
    • Entry vestibule*: John Abel

    Architects/Engineers

    • Modular building, playground: 3J Consulting, Inc.
    • Gym: Mahlum Architects
    • Entry vestibule*: Process-PDX

    Contractors

    • Modular building: Five Star Builders
    • Playground
      • Site work: Five Star Builders, Inc.
      • Structure: Cascade Recreation
      • Rubber tile: NW Playground Equipment
    • Gym/renovations: Emerick Construction
    • Entry vestibule*: Inline Construction

     

    *grouped with Indian Hills, Minter Bridge, and Tobias entry vestibule projects