• Bond construction timeline - Poynter

     


Scope of Work

  • Please note that the preliminary site plan/design, project costs, and schedules may fluctuate due to cost of materials and labor, unforeseen and/or revised scope, conditions at the site, and other factors. Projected budget: $17.2 million

    March 2019-February 2020

    • Improvements

    Poynter will receive seismic, electrical service, roofing, and HVAC upgrades, including added air conditioning. Domestic water piping will be replaced. Project crews will be mobilizing in early spring 2019, with construction expected to start in March 2019. Substantial completion is expected by mid-February 2020.

    With this early start, construction will be a continuous process through the school year. A phasing plan will be in place to cycle construction in specific zones and keep students safely out of those zones. Alternate classrooms in temporary portable buildings will be made available so education is uninterrupted by the work taking place on the campus. As one zone is under construction, students in the affected classrooms will be placed in the portables. When that zone is completed, students will be returned to that area. Then, the next phase of construction begins in another zone, with those classes moved to the portables; this phasing continues until all improvements are completed.

    Summer 2020

    • New Furniture

    In summer 2020, new furniture (FFE) will be delivered that is known to enhance the learning environment and increase student engagement.

    Completed Projects

    • Security Cameras

    Installation of security cameras enhances safety and security in the building. This project was completed in summer 2018.

     

  • Project Manager

    Cornerstone Management Group

    • Renovations: Mathieu Jacobs

    Architect

    • Renovations: Soderstrom Architects

    Contractor

    • Renovations: P&C Construction