Aug. 18, 2020

  • Photo 1: the main domestic water inflow pipes (white) have been replaced (the red-and green-colored pipes are part of the fire suppression system).

    main domestic water inflow pipes

    Photo 2: a new drinking fountain and bottle filler have been installed near the school's entryway.

    new drinking fountain and bottle filler

    Photo 3: ceiling tiles have been reinstalled to cover up the replaced domestic water pipes above.

    reinstalled ceiling tiles in hallway

    Comments (-1)

Aug. 3, 2020

  • Photos 1-3: patching and painting are taking place in areas where the domestic water pipe replacement has been completed.

    patching of front entry fountain pipe replacement

    patching of sink pipe replacement

    patched kitchen pipe replacement

    Photos 4-5: ceiling grid has been re-installed over the entry and the north-south hallway where pipe has been replaced.

    entryway

    north-south hallway

July 14, 2020

  • Photo 1: plumbing pipes of various sizes and materials await installation to replace old domestic water lines.

    plumbing pipe

    Photos 2-4: the new pipe is being installed to replace old plumbing behind sinks and toilets, and in the overhead areas of the building.

    new plumbing behind bathroom sinks

    exposed bathroom ceiling

    plumbing pipes running above ceiling

June 16, 2020

  • Ceilings and walls have been exposed as part of the domestic water pipe replacement at the school.

    exposed hallway ceiling

    exposed wall underneath bathroom sinks

    exposed bathroom ceiling

Aug. 31, 2018

  • The play area has been completed and ready for the start of school. A school alumnus tested it out and declared it "very nice" - the swings were his favorite.

    new playground at Butternut Creek

Aug. 21, 2018

  • August 21, 2018

    Rubberized tile installation

    Stretching synthetic turf

    Photo 2: The synthetic turf is being stretched across the play area, which creates a mud-free space for students.

Aug. 14, 2018

  • August 14, 2018

    Butternut Creek play structure

    Installation of the play structure is complete. Next steps are placement of rubberized tiles around the structure and installation of the synthetic turf play area.

Aug. 7, 2018

  • August 7, 2018

    Play structure installation Installation of the play structure has begun, including digging holes for the posts.

July 31, 2018

  • July 31, 2018

    Butternut Creek playground construction Parts for the play structure are about to be assembled.

July 24, 2018

  • July 24, 2018

    Butternut Creek playground construction The concrete base for the playground is finished and ready for installation of the play structure's posts.

July 16, 2018

  • July 16, 2018

    Gravel poured into play area

    Flexible furniture in Butternut Creek classroom

    Photo 1: The gravel base is poured as part of the foundation for the new play structure.

    Photo 2: Flexible furniture in one of the classrooms.

July 10, 2018

  • July 10, 2018

    Butternut play area construction Work continues on constructing forms for concrete curbs around the border of the play area.

July 3, 2018

  • July 3, 2018

    Butternut Creek playground construction Forms for curbs are being set around the playground area, in preparation for concrete to be poured.

June 26, 2018

  • June 26, 2018

    Photo of cleared play area

    Contractors have cleared the area for the school's new playground, which will have a new play structure and a rubberized tile surface for added safety.

June 19, 2018

  • June 19, 2018

    Moving out furniture at Butternut Creek Movers start removing old furniture, which will be replaced with new flexible furniture.

Last Modified on August 18, 2020