Aug. 9, 2022

  • Photos 1 and 2: painting has been completed in the entry vestibule and frames for the doors stand ready for installation in the new doorway.

    doorways ready for installation in painted entry vestibule

    painted vestibule under construction

    Photo 3: the frames will be installed against the area cut into the tile artwork, under the constructed header. The cutting was necessary in order to preserve the rest of the artwork.

    vestibule showing cut area in tile artwork

    Comments (-1)

Aug. 4, 2022

  • Photos 1 and 2: painting has started in the renovated vestibule.

    crew member painting vestibule

    painting of renovated vestibule

July 26, 2022

  • Photos 1 and 2: sheetrock has been added to the new vestibule framing and is being taped up to prepare for painting.

    sheetrocked vestibule

    crew member taping sheetrock in vestibule

July 19, 2022

  • Photos 1-3: work continues on security pathways and cabling for the vestibule.

    security pathways work at entrance ceiling

    view of vestibule construction toward front of building

    open framing for vestibule remodeling

July 12, 2022

  • Photos 1-2: the frame has been constructed above the vestibule for the new set of doors. The doorway is being constructed to minimize impact on the tile artwork.

    view of vestibule construction toward front entry

    view of vestibule construction toward back of building

    Photo 3: the front of the office has been re-framed to adjust window and door spaces for the new configuration.

    office framing reconfiguration

June 28, 2022

  • Photos 1-3: some demolition work is taking place as part of the remodeling of the front entry vestibule to upgrade security.

    demolition work begins at entry vestibule

    drywall removed at entry vestibule

    entry vestibule remodeling underway