Jackson Bond Projects
Page Navigation
Aug. 19, 2019
-
The dropoff areas and parking lot have been paved and striped.
Photo 1: the striping shows dropoff and through lanes for buses (nearest the school) and a separate exit to the west, and two lanes for parent vehicles (dropoff lane and through lane).
Photo 2: an additional parking lot to the right of the entrance provides spaces for staff and visitors.
Aug. 12, 2019
-
Photo 1: as asphalt is poured into the paver, it is deposited and leveled to a specific depth; crew members ensure a smooth installation. The roller will compact the asphalt even more.
Photo 2: the dropoffs/parking lots prior to paving; the gravel and soil have been compacted to prepare for the paving.
July 29, 2019
-
Aerial views show how the dropoffs and parking lot areas are beginning to be outlined with concrete curbs.
July 19, 2019
-
Photos 1 and 2: aerial views of the grading and compaction of the bus and parent dropoff area and the new staff/visitor parking lot.
Photo 3: crew members prepare a hole to place the concrete base for a parking lot light pole.
July 8, 2019
-
Photos 1 and 2: The front sidewalk is being excavated.
Photo 3: Stormwater pipe will be installed in trenches below the parking lot.
July 1, 2019
-
Photos 1 and 2: excavation and grading of the dropoffs/parking lot for parents (1) and for buses and staff (2) are underway.
Photo 3: the reconstruction of Jacob's Field is nearly complete. The infield area has been graded and graveled; it is now awaiting the turf installation.
June 18, 2019
-
The southeast ball field is being excavated to prepare for construction of the new parking lot area. A replacement field is currently being built in the northeast corner of the campus.
July 19, 2018
-
Due to delays in the permitting process, the parent/bus dropoff project has been postponed to summer 2019. The relocation of Jacob's Field is also being rescheduled.
June 26, 2018
-
A backhoe and excavator have been mobilized and stand ready to begin the remodel of Jackson's parent/bus dropoff area, which is expected to be completed by the end of August.
Milestones
-
Aug. 16, 2019 - paving and striping of the dropoff/parking area have begun.
-
June 18, 2019 - excavation of the site of the new dropoffs has begun.