Roofing work is wrapping up. HVAC units have been installed on the roof.
Sept. 14, 2019
Roofing work is nearly complete (west/left side of building).
Sept. 3, 2019
The first day of school shows the finished pipes and conduits amid freshly-painted hallways. Inspirational phrases have been repainted on the ceiling beams and color stripes designate hallway locations to facilitate emergency response.
Aug. 5, 2019
Photo 1: HVAC ductwork is being installed in the gym to add air conditioning.
Photo 2: insulation is being wrapped around hot water pipes.
Photo 3: domestic water pipe is being replaced in the bathrooms.
Photo 4: the woodshop area is undergoing seismic and roofing upgrades.
July 12, 2019
Photos 1-3: Crews work on renovating the roof.
Photos 4-6: inside the school, work continues with HVAC and domestic water pipe upgrades.
June 28, 2019
Photo 1: Roofing preparations.
Photos 2 and 3: Old HVAC ducts wait to be recycled, while new ducts are going to be installed.
Photo 4: HVAC ductwork in the gym has been marked for replacement
Photo 5: A crew member is installing a large HVAC duct.