• Bond construction timeline - Facilities

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Total cost: $3.2M.

    COMPLETED

    • Safety Upgrades

    The Facilities Department building underwent installation of safety and security measures that include security camera upgrades, card key access, perimeter fencing, and an automated entry gate that limits off-hours access to the site.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Luke Harkness

    General Contractor

    • Automated gate: Dick's Evergreen Fence & Deck
    • Security: Reece