• Bond construction timeline - satellite transportation facility

     


Scope of Work

  • Please note that the preliminary site plan/design, project costs, and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $17.8 million

    2019-2020

    The Transportation Department will get a second hub on the north side of the District to house buses as well as mechanics and other staff. Also included is space for our new diesel mechanic career-technical education program. Construction is expected to begin in June 2019 and conclude by Sept. 2020.

  • Project Manager

    Cornerstone Management Group

    • Rick Cunningham

    Architect

    • BBL Architects

    Contractor

     

Last Modified on November 20, 2019