Transportation & Support Services Bond Project
Scope of Work
-
Please note that the preliminary site plan/design, project costs, and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $19.3 million
COMPLETED
- New Transportation and Support Services Building
The Transportation Department now has a second hub on the north side of the District to house buses as well as mechanics and other staff. The building will be shared with the Facilities Department and its groundskeeping and trades shops. Also included is space for our new diesel mechanic and trades career-technical education program.
Construction began in July 2019 and was substantially completed in August 2020.
-
Project Manager
Cornerstone Management Group
- Rick Cunningham
Architect
- BBL Architects
Contractor
- Robinson Construction
Last Modified on November 20, 2020