Dec. 2, 2019

  • Photo 1: crew members hang wiring on the ceiling of the new weight room addition.

    weight room under construction

    Photo 2: work continues in the team room installing ducts and conduit.

    team room construction

    Photo 3: metal framing is cut to size and installed in the cafeteria addition.

    cafeteria addition construction

    Photos 4-6: rooftop HVAC units have been placed on top of the media center addition as framing and sheathing continue on the first and second floors.

    aerial view of rooftop HVAC units on media center construction

    first floor of media center construction

    second floor of media center construction

    Comments (-1)

Nov. 25, 2019

  • Photo 1: the cafeteria addition is taking on more definition with wall and roof framing. The arrow indicates the location of the steel beam signed by community members on Sept. 26.

    cafeteria addition under construction (view to north)

    Photo 2: a view of the addition toward the adjacent, existing cafeteria.

    cafeteria addition under construction (view to east)

    Photos 3, 4 and 5: sheathing is enclosing the exterior of the media center addition while, inside, work continues on the steel framing of the first and second floors.

    exterior view of media center construction

    media center first floor construction

    media center second floor construction

    Photos 6 and 7: HVAC ductwork is being installed in the team room as work continues on the exterior.

    ductwork installation in team room

    framing work on team room window

    Photo 8: in the weight room, HVAC ductwork is also being installed.

    ductwork installation in weight room

Nov. 12, 2019

  • Photo 1: an aerial view of the cafeteria addition after installation of steel beams for the roof.

    aerial view of cafeteria addition

    Photo 2: the steel beam, signed by community members, sits in the middle of the structure.

    signed steel beam

    Photo 3: HVAC ductwork is being installed in the team room.

    HVAC ductwork in team room

    Photo 4: sheathing now encloses the walls of the weight room.

    sheathing encloses weight room walls

    Photo 5: framing of the exterior border of the roof.

    roof border framing

Nov. 4, 2019

  • Photos 1 and 2: the concrete masonry walls for the cafeteria addition have been erected.

    cafeteria addition walls

    cafeteria addition hallway

    Photos 3 and 4: walls are being framed in the team room addition.

    team room addition wall framing

    team room construction

    Photos 5 and 6: weight room framing is being installed.

    weight room addition framing

    weight room construction

    Photo 7: welding of steel beams in media center addition.

    welding steel beam

    Photo 8: building of stairs to the second floor of the media center addition.

    building stairs

    Photo 9: a view of the second floor of the media center addition.

    second floor construction in media center addition

Oct. 28, 2019

  • Photos 1 and 2: now that the roof deck panels are in place on the media center addition, the second floor base panels are being installed.

    welder working on the second floor of the media center addition

    aerial view of media center construction

    Photo 3: the cafeteria addition masonry work continues.

    aerial view of cafeteria addition construction

Oct. 22, 2019

  • Photos 1-4: the metal roof panels have been installed as crew members continue welding on the steel structure.

    aerial view of construction of media center addition

    crew members working on the structure rooftop

    crew member welds rooftop steel

    crew member welds steel on the first floor

    Photo 5: work on the team room continues after the roof beams have been fireproofed

    team room under construction

    Photo 6: the weight room is being prepared for fireproofing.

    weight room under construction

    Photo 7-8: reinforced concrete masonry blocks are being installed on the perimeter and entry area of the cafeteria addition

    concrete masonry block installation

    crew installs concrete masonry blocks

Oct. 14, 2019

  • Photos 1 and 2: concrete masonry has been set to outline the walls for the cafeteria addition.

    aerial view of construction of cafeteria addition

    concrete masonry outlines the cafeteria wall construction

    Photos 3-5: crew members check connections and weld the steel beams for the media center addition.

    crew member checking steel beams

    crew members welding steel beams

    aerial view of construction of media center addition

    Photos 6-7: work continues on the roofing and sides of the weight room and team rooms.

    aerial view of construction of weight room addition

    aerial view of construction of team room addition

Oct. 1-2, 2019

  • Photos 1-3: a crane lifts steel beams to frame the new media center addition.

    aerial view of media center addition construction

    aerial view of media center addition construction

    aerial view of media center addition construction

    Photos 4-5: construction continues on the weight and team rooms.

    aerial view of weight room construction

    aerial view of team room construction

    Photo 6: the cafeteria addition is taking shape with the foundation laid.

    aerial view of cafeteria addition construction

Sept. 25-26, 2019

  • OUTSIDE

    Steel beams are being arranged around the media center site in preparation for the framing of the structure.

    aerial view of media center construction site

    The frame has been installed for the weight room roof.

    aerial view of weight room construction

    Decking has been installed on the team room roof.

    aerial view of team room roof decking

    INSIDE

    Completed renovations in the student services office, main office, band storage/concessions, and the student store.

    student services office

    main office

    band storage/concessions area

    student store

Sept. 16, 2019

  • Photo 1: the foundation has been poured for the new weight room, and workers start preparing for structural framing.

    aerial view of weight room construction

    Photo 2: the foundation in the second section of the media center addition has been poured.

    aerial view of media center construction

Sept. 9, 2019

  • The second section of the media center/classroom addition has been framed in preparation for the next concrete pour.

    aerial view of construction site for addition

Sept. 4, 2019

  • An aerial view of the south side of campus at the start of the school year.

    aerial view of the south campus

Aug. 26, 2019

  • Paving, striping and landscaping have been completed for the new parking lot on the south side of campus. Note the canopy at the side of the building over the sidewalk - this will help shelter students as they wait for the bus. Light poles are still pending installation.

    aerial view of south parking lot

Aug. 14, 2019

July 2, 2019

  • Video: Project update by Glencoe senior Andrew Goodwin

    Photo 1: "Mount Glencoe" is filled with concrete excavated from various areas of the site. It will be ground up and repurposed to form part of the base in the south parking lot.

    Mound of excavated concrete, aka Mt. Glencoe

    Photo 2: Crew members work on strapping the new ventilation ducts in the school office.

    Crews strapping HVAC ducts

    Photo 3: The main entryway is being excavated and graded to prepare for the new addition. The crane lifts gravel to the rooftop.

    Main entryway excavation

    Photo 4: The student store is undergoing renovations to expand counters and casework, add sinks, and build a new opening. This is just one of many career-technical education spaces that will be worked on.

    Student store renovations

    Photo 5: Work continues in the early childhood education classroom to replace underground pipe as well as overhead HVAC ducts.

    Pipe repair/trenching and HVAC ductwork

June 21, 2019

  • Video: Project update by Glencoe senior Andrew Goodwin

    Photo 1: Walls in the main office have been demolished.

    Main office demolition work

    Photo 2: canopies adjacent to the gym and theatre have been removed to prepare for construction of the new weight room.

    Removing canopies to prepare for weight room construction

June 17, 2019

  • The main office has been cleared out, the HVAC system and wiring exposed, and walls have been marked for demolition.

    Main office has been cleared

    HVAC ductwork and wiring

    The old football shed has been demolished. The new, north parking lot will eventually extend into that area.

    Old football shed demolished  

Nov. 2018 - Parking Lot Changes

  • During October and early November, the parking lots were redesigned based on an evaluation from our traffic engineers and other feedback. The latest design can be viewed in the site plans section.

Oct. 1, 2018 - Neighborhood Meeting

  • A neighborhood meeting was held at Glencoe to preview the proposed designs for additions and renovations to the campus, accommodating a growing enrollment of up to 400 more students. The goal is to start construction in May 2019 and conclude by the end of summer 2020. Seismic retrofits are included as part of the improvements. BLRB architects answered questions from the audience - consolidated into primary, common themes here:

    • Land use process - plans will be submitted to the City of Hillsboro shortly; the City is likely to schedule public hearings and an opportunity for public comment in the next few months
    • Relocation/staging of students and classrooms during construction - a plan will be in place; this may not always be "comfortable," but the priority will be on protecting students, yet allowing them to safely observe progress
    • Improving safety - unsecured entry will be reduced with the new main entrance and vestibule design as well as by enclosing and connecting the cafeteria addition to the main building
    • Glencoe Road traffic - staff knows this is an issue and has commissioned a traffic study to evaluate flows; potential solutions for improvement will likely require funding beyond the current bond budget
    • Fire lane access (between gym and field) - concerns were raised about cars driving through and parking, as well as needed access for theatre loading; since this lane cannot be blocked, signage or other operational solutions will need to address these concerns
    • Band trailer storage/parking and theatre storage - this is a known concern as storage will need to be relocated
    • Traffic flow and congestion - concerns were raised about ingress/egress, numbers/idling of buses, neighborhood parking, crosswalk access in lots; expansion/redesign of the parking lots is expected to help alleviate these concerns (with minimal impact to existing mature trees) as well as the just-approved District policy ECG to minimize bus idling
    • Digital/technology/electrical access - additions/renovations will be constructed to the latest, state-of-the-art standards, including wireless access points and Chromebook cart plug-ins (Chromebook carts were already delivered in early 2018 as part of the first bond-funded technology roll-out)
    • Murals - graphic design instructor already has been in touch to potentially incorporate student-led designs

    View the presentation here. Read Olivia Singer's article for Pamplin Media Group/Hillsboro Tribune.

Milestones

  • Oct. 1, 2019 - steel beams begin to be erected for the media center addition.

    Comments (-1)
  • Sept. 26-27, 2019 - community signing of steel beam that will be erected in cafeteria addition.

    Comments (-1)
  • Aug. 30, 2019 - construction of south parking lot and summer 2019 interior renovations completed; punchlist items in progress.

    Comments (-1)
  • June 17, 2019 - work begins on building improvements and the south parking lot.

    Comments (-1)
  • June 5, 2019 - the groundbreaking ceremony commemorating the official start of construction on the main building.

    Comments (-1)
  • May 1, 2019 - preparations begin for renovations, starting with abatement in the football shed and mobilization of equipment and materials.

    Comments (-1)
  • Oct. 1, 2018 - Neighborhood meeting held to review proposed design for additions/renovations

    Comments (-1)