Montage

Sept. 19, 2019

  • The modular building is fully occupied with the Little Jags preschool (photo 1) and the high school early childhood education classroom (photo 2).

    preschool classroom

    high school ECE classroom

    Comments (-1)
  • Photo 1: furniture and supplies have been moved into the preschool classroom.

    moving into preschool classroom

    Photos 2 and 3: the kitchen and high school student classroom are ready for move-in.

    ktichen in modular building

    early childhood education classroom

Aug. 7, 2019

  • The modular building for the early childhood education program is nearly complete, with the punch list expected to be itemized next week.

    Modular building exterior

    classroom in modular building

    kitchen area in modular building

  • Photos 1-3: inside the building, the rooms are being prepared for the installation of flooring and coving.

    One of the modular's classrooms

    One of the modular's classrooms

    Installing coving at the base of the room

    Photos 4-5: the exterior of the building has been painted, a walkway to the entrance has been installed, and a crew member cleans up the area.

    North side of modular building

    West side of modular building being cleaned

June 13, 2019

  • All five pieces have been assembled and the rooftop was placed above. Crews will continue working on interior finishing and the roofing.

    Final assembly of modular building

June 12, 2019

  • The first of five pieces of the new modular building has been placed.

    The first piece of the modular building is placed

    The site stands ready for the next piece.

    View of modular building site with crane

    The second piece of the new modular building is placed.

    Aerial view of modular building placement

June 4, 2019

  • The foundation is ready for the modular building.

    Aerial view of the foundation.

May 21, 2019

  • Forms are being constructed for the modular building's foundation. They will be filled with concrete and the building will be placed and assembled above the foundation.

    Construction of forms for the modular building's foundation

    Crews inspect and adjust the foundation forms

May 10, 2019

  • Pipe is being laid underground to prepare for the new modular building that will house the early childhood education program.

    Laying of underground pipe

    Underground pipe installation

Milestones

  • June 12, 2019 - the placement of the modular building begins.

    Comments (-1)
  • April 24, 2019 - crews begin preparing the site for excavation and pipework.


    Comments (-1)