• Construction will occur in four phases beginning in March 22, 2019, and expected to run through Aug. 19, 2020 (revised completion date). As of Oct. 9, phase 1 has been completed, and phase 2 is currently underway and scheduled to finish Nov. 21. Phase 3 is scheduled to begin on Dec. 4. Phase 4 has been advanced by three months, with an expected start date of Jan. 6, 2020. The updated phasing plan below shows buildings that will undergo renovations during each phase.

    This accelerated schedule helps ensure that the affected buildings can be turned over to our contractor as soon as possible to start the renovation work and complete the full bond project on time. Phase 3 and 4 implementation will overlap from January through April 2020. To accommodate this schedule, 26 classrooms that were going to be moved before each of these phases will instead be moved at one time to portables in the parking lot in mid- to late November, where they will remain through the end of the school year. Instructional time will not be affected.

    During the school year, when a phase begins, the associated areas will be cordoned off and inaccessible to students and school staff. During the summer, the entire campus will be closed to upgrade roofs and other exterior areas. For everyone's safety, do not enter construction zones.

    The entrance from the neighborhood into this area also will be closed; students will need to enter campus through the main entry.

Construction Phasing Plan (PDF)

If you are having trouble viewing the document, you may download the document.

Plan Para Las Fases De Construcción en Hilhi (PDF)

If you are having trouble viewing the document, you may download the document.