Video: directly-overhead view of Transportation building structure.
Photo 1: aerial view of the Transportation building under construction. Liberty's nearly-finished sustainable agriculture/design building can be seen in the upper left corner.
Photo 2: aerial view of masons laying concrete masonry units in the shop storage areas.
Photo 3: ground-level view of bricklaying of the storage areas from the shop space.
Photo 4: view of conference room construction from the front entry area.
Photo 5: view of the carpentry office and storage areas.
Nov. 26, 2019
Photo 1: aerial view of construction of the walls that will form the shop spaces for maintenance, carpentry and CTE.
Photo 2: aerial view of the whole building. The training office is beginning to take shape in the bottom center right of the building.
Photos 3 and 4: ground-level views of the outside of the maintenance shop and the training office.
Nov. 12, 2019
Interior walls continue to be built up with reinforced concrete masonry. Steel beams also are being installed to provide additional structural support.
Nov. 5, 2019
On the exterior, crew members smooth out the grooves made in the concrete that provide architectural interest. Inside, walls continue to be built up with reinforced concrete masonry.
Oct. 29, 2019
Reinforced concrete masonry continues to be added to the interior walls of the building, and the crew checks to ensure everything is level.
Oct. 22, 2019
Photo 1: aerial view of the Transportation building site
Photo 2: reinforced concrete masonry is being laid to form the interior walls of the Transportation building
Photo 3: a welder works on one of the roof joist braces
Oct. 15, 2019
The west side of the parking lot is ready for paving.
Oct. 8, 2019
Photo 1: sunrise shines through the building shell.
Photo 2: the project crew meets early to discuss the day's tasks.
Photo 3: an aerial view shows all the walls erected and one of the parking lots paved over.
The site is being prepared for erection of tilt walls this week and paving next week.
Sept. 9, 2019
A total of 600 cubic yards of concrete was poured for the foundation slab. Crew members are now preparing forms for the tilt walls. At the top left corner, Liberty's sustainable agriculture/design building is being constructed on the other side of Jacobsen Road.
Sept. 3, 2019
Concrete for the foundation slab is being poured and smoothed.
Aug. 23, 2019
Construction continues to prepare the foundation for the site.
Aug. 12, 2019
Concrete footings have been poured and trenches for utility lines are being excavated.
July 22, 2019
The site for the new Transportation and Support Services facility on Jacobson Street (behind Liberty High School) has been excavated and graded. A large hill of gravel sits on the site waiting to be used -- these loads were transported in advance of the upcoming two-month closure of Cornelius Pass Road.
July 12, 2019
Josh Sierra, site superintendent for Robinson Construction, and Rick Cunningham, project manager for Cornerstone Construction, commemorate the start of construction.
Milestones
Sept. 3, 2019 - concrete is poured for the foundation slab.