2021 Project Schedule

  • The table below lists projects that are wrapping up (from last year) in 2021 or starting in 2021.

    NOTE: Project schedules are subject to change due to permitting processes and unforeseen or additional scope. Gray-shaded areas illustrate the current timeline and duration of each project. Anticipated start dates are in green and are at the beginning of the project timeline; expected completion dates for the final tasks are in red at the end of the timeline.

     

    School / Building Project Description 2021 2022
    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
    Atfalati Ridge ES June 2020-Aug 2021: New school construction COMPLETE                          
    Butternut Creek ES Building/dropoff improvements, modular building, roofing           COMPLETE                        
       - Southview Street improvements                                  
    Century HS EIFS replacement         COMPLETE                        
    ES29 (South Hillsboro) New construction (2021-2023)         Phase 1 - COMPLETE     Phase 2 building construction
    Farmington View ES Building/dropoff improvements, roofing           COMPLETE                          
    Groner K-8 Summer: building improvements, roofing
    Oct-Mar: gym repair
              Renovations - COMPLETE Gym repairs            
    WL Henry ES March 2020-March 2021 COMPLETE                                    
       - Summer: entry vestibule, add AC (cafeteria, library)           COMPLETE                          
    Hillsboro HS Summer: concrete replacement
    Fall: landscaping
              COMPLETE                          
    Hillsboro Online /
    Peter Boscow
    Building improvements, roofing, portables     COMPLETE                          
    Indian Hills ES Entry vestibule, street improvements           COMPLETE                          
    Jackson ES Jan-Oct: new gym COMPLETE                      
       - Building improvements       COMPLETE                          
    Ladd Acres ES Oct 2020-Aug 2021: new gym COMPLETE                          
       - Building improvements, playground     COMPLETE                          
    McKinney ES Oct 2020-Aug 2021: new gym COMPLETE                          
       - Building improvements     COMPLETE                          
    Miller Big Picture Pathways Center     COMPLETE                  
    Minter Bridge ES May 2020-Feb 2021: new gym COMPLETE                                      
    North Plains ES Building improvements, playground           COMPLETE                          
    Quatama ES Entry vestibule                                          
    Tobias ES Entry vestibule, additional roofing           COMPLETE                          
    West Union ES MDF (network) room           COMPLETE                          
    Feeders 1 and 2 Window security film                     COMPLETE