Century Bond Projects
Sept. 10, 2021
-
Photos 1-3: scaffolding has been removed from the areas of work around the auxiliary gym for the EIFS replacement. Coming soon is the final coating to seal the EIFS.
Aug. 11, 2021
-
Photos 1 and 2: the skin coating is being applied on the new EIFS; when this is completed, scaffolding will start to be taken down.
Aug. 3, 2021
-
Photo 1: scaffolding encircles the sections of the building near the auxiliary gym that are undergoing the phase 2 EIFS installation.
July 27, 2021
-
Photos 1 and 2: EIFS work continues on the north side of the school adjacent to the auxiliary gym.
Photo 3: final painting completes the EIFS work on the theatre section of the building
July 15, 2021
-
Photo 1: the EIFS replacement on the exterior of the theatre area is complete.
Photos 2-4: work progresses on replacing the EIFS on other sections of the school building.
July 6, 2021
-
Photos 1 and 2: scaffolding boards are being removed from the top of the completed theater wing and lowered by a large forklift.
Photo 3: work continues in the auxiliary theatre wing.
June 30, 2021
-
Photo 1: on the theater wing, the styrofoam insulation layer has been installed and crew members are now applying a concrete slurry mix to the exterior walls.
Photo 2: at the back of the auxiliary gym, base coating has been applied to most of the exterior walls.
June 22, 2021
-
Photo 1: scaffolding surrounds the auxiliary gym area at the back of the school where the old EIFS has been removed and the base coating applied to most of the area.
Photos 2 and 3: the base coating has been applied around the theatre wing and EIFS membrane panels are ready to be installed.
June 15, 2021
-
Photo 1: a base coat (blue) for the new EIFS siding has been added to the southeast corner of the building (auditorium area).
Photo 2: at the very top of the building, a crew member applies a weatherproofing coat (black) at the edge of the roof and side walls to prevent water intrusion. Weatherproofing will be applied at all seams of the building.
Photos 3 and 4: on the northeast corner of the building (auxiliary gym area), stripping of the old EIFS is well underway.
June 7, 2021
-
Photos 1-3: up on the scaffolding, crew members burn off the remaining styrofoam, while below, others mix the "mud" that will be placed over the exposed walls.
Photo 4: scaffolding and netting have been installed in the second work area.
June 1, 2021
-
Photo 1: a crew member builds up the scaffolding near the HVAC mechanical units at the back of the school to prepare this area for EIFS removal.
Photo 2: in the first area (theater), nearly all of the EIFS styrofoam layer has been removed.
May 26, 2021
-
Photo 1: scaffolding and netting now wrap the full corner of the auditorium building for EIFS replacement. The netting keeps the removed EIFS close to the building.
Photo 2: crew members work along the scaffolding to remove the EIFS.
Photo 3: removing the EIFS requires scraping off the top hard coating, then the styrofoam underneath.
Photo 4: the remaining glue along the side of the building will need to be scraped off before adding the replacement EIFS.
May 18, 2021
-
Scaffolding surrounds the corner of the building where the first section of the EIFS siding will be replaced.