Sept. 8, 2021

  • Photos 1-3: concrete replacement is complete at the fronts of the gym and main office.

    aerial view of gym front with new concrete

    aerial view of school office front with new concrete

    aerial view of finished concrete replacement

    Comments (-1)

Aug. 18, 2021

  • Photos 1-2: concrete is poured and smoothed for the landing area in front of the main office.

    crew smoothing freshly-poured concrete

    aerial view of nearly-finished concrete repairs

    Photo 3: concrete work is nearly finished at the front of the main office.

    nearly-finished concrete work in front of main office

    Photo 4: work is finished in front of the gym. New bike racks have been added for student and staff use.

    finished concrete work in front of gym

Aug. 3, 2021

  • Photos 1-3: the stair sections have been joined in front of the gym and the main office. Framing for new curb has started and the gravel in between is being compacted for construction of additional walkways.

    aerial view of concrete replacement

    concrete work in front of gym

    concrete work in front of main office

July 28, 2021

  • Photos 1 and 2: the concrete stairs have been poured in front of the gym and the main office.

    concrete stairs in front of gym

    concrete stairs in front of main office

    Photo 3: this aerial views shows the extent of the concrete replacement work so far.

    aerial view of concrete repair work

    Photo 4: the concrete sides for the ADA access ramp have been poured in preparation for the base pour.

    ADA access ramp sides

July 23, 2021

  • Photos 1-4: framing for concrete stairs and ADA access ramp are in place for an upcoming concrete pour.

    stair frames in front of gym

    stair frames in front of main office

    aerial view of concrete repair work

    crew members frame ADA access ramp

July 8, 2021

  • Photos 1 and 2: in phase 1 of the concrete repair project, all the old concrete has been removed from the front of the gym. The ground has been excavated, and new base rock is being applied.

    adding base rock to site

    smoothing out base rock

    Photo 3: an additional project this summer has been the installation of a new monument sign with electronic screen at the front of the school.

    Hilhi's new monument sign

June 23, 2021

  • Photos 1 and 2: fencing has been erected to close off the front of the main gym in preparation for upcoming concrete repairs.

    fenced off gym front

    fenced off gym front