2022-23 Project Schedule

  • The table below lists projects that are taking place in 2022 and into 2023.

    NOTE: Project schedules are subject to change due to permitting processes and unforeseen or additional scope. Gray-shaded areas illustrate the current timeline and duration of each project. Unless otherwise noted, summer projects (June-August) are expected to begin the week of June 20 and end before August 19, when schools are closed for the summer.

     

    School / Building Project Description 2022 2023
    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
    Administration Center Upgrade data center (phase 1)
    Renovations to data center (phase 2 - fire rating), entry vestibule, restroom
      COMPLETE
    Phase 1
        COMPLETE
    Renovations
                             
    Atfalati Ridge ES Protective net installation (turf field)   COMPLETE                                    
    Century HS Softball home run fence, dugout renovations     COMPLETE
    HR fence
                    Softball dugouts              
    Groner K-8 Jan-Mar: gym repairs
    Summer: window replacement
    COMPLETE
    Gym repairs
        COMPLETE
    Windows
                             
    Hare Field Domestic water pipe replacement         COMPLETE                          
    Hillsboro HS Exterior painting           COMPLETE                          
    Ladd Acres ES Play area blacktop replacement           COMPLETE                          
    Liberty HS Solar array, softball dugouts                   Oct-Feb: Solar array
    Jan-Feb: softball dugouts
                 
    McKinney ES Replace domestic water pipe           COMPLETE                          
    Miller East Security gates     COMPLETE                                
    Minter Bridge ES Feb: Security gates
    Spring: Trash enclosure
      COMP
    Gates
    COMPLETE
    Trash enclosure
                               
    Mooberry ES Feb: Gate fixes
    Mar/Spring: HVAC lobby terminal unit
      COMP
    Gates
    COMPLETE
    HVAC
                                   
    North Plains ES Window replacement, stucco repairs, exterior painting
    HVAC unit replacement, security fence
              COMPLETE                  
    Orenco ES Security fencing
    Entry Vestibule
        COMP
    Fence
        COMPLETE
    Vestibule
                             
    Rosedale ES Perimeter fencing                     COMPLETE                  
    Tamarack ES New construction in south Hillsboro (2021-2023)     Phase 2 building construction  
    Tobias ES New bus dropoff           COMPLETE                          
    Transportation (Walnut St) Roofing, HVAC/DDC, renovations
    upgrade electrical service/generator
              COMPLETE
    Roofing, HVAC, renovations
      Generator            
    West Union ES Window replacement           COMPLETE                          
    Witch Hazel ES Gym roofing           COMPLETE                          
    Entry vestibules Group 3: Imlay, Orenco, Patterson, Rosedale
    Group 4: Free Orchards, Groner, Lincoln Street, Witch Hazel, Admin. Ctr.
              COMPLETE                        
    Window security film Feeder 1 (Century, Brown, Butternut Creek, Imlay, Indian Hills, Ladd Acres, Reedville, Tobias) COMP                                        
    Window security film Feeder 4 (Admin. Ctr., Transportation [at Jacobson], Peter Boscow, Liberty, Poynter, Eastwood, Lenox, Mooberry, Orenco, Quatama, West Union) COMP                                        
    Window security film Feeder 2 (Transportation [at Walnut], MEC, Glencoe, Evergreen, Atfalati Ridge, Free Orchards, Jackson, Lincoln Street, McKinney, North Plains, Patterson)       COMPLETE                                
    Window security film Feeder 3 (Facilities, Hilhi, South Meadows, Brookwood, Farmington View, Groner, W.L. Henry, Minter Bridge, Rosedale, Witch Hazel)       COMPLETE