Aug. 2, 2022
-
Photos 1-4: the exteriors of the gym, buildings on the south side of campus, and the cafeteria have been painted.
Photo 5: painting is taking place on the drama/music building.
Photo 6: walkway awnings are also being primed and painted.
July 19, 2022
-
Photos 1-5: painting is now taking place along the courtyard buildings. Spartan branding will be applied in specific areas once painting is finished.
Courtyard area
Cafeteria/commons building
Locker/weight room building
Wood shop building
Technical education building
July 12, 2022
-
Photos 1-3: priming and painting of the building exteriors begin at the front of the school, including the administration building...
...the gymnasium...
...and the theater building.
June 28, 2022
-
Photo 1: power washing cleans the buildings of dirt and other debris before painting.
Photos 2-4: painting has started behind the music building.
June 14, 2022
-
Photo 1: the stucco on the south wall of the auditorium has been patched and primed.
Photo 2: a crew member applies caulk and tape around windows to prepare for painting.
Photo 3: a vent on the commons building has been sealed and caulked.
Photo 4: a vertical gap that ran between walls of the commons is now filled and sealed.
-
Before exterior painting can begin, some stucco repairs must be made where needed, as determined by our consultant's annual inspection. This ensures against water intrusion into the buildings
Photos 1 and 2: stucco is being patched along the south wall of the auditorium. Crew members mix the base compound to apply along the primed area.
Photos 3 and 4: other areas of repair include stucco around the media center doors and vents on the commons building. There is also a gap along the corner of the commons wall (to the crew member's left) that will be bridged and patched.