Sept. 5-6, 2023: First Days of School

Aug. 23, 2023 - Grand Opening

  • August 24, 2023 - On Wednesday, Aug. 23 HSD held a dedication and ribbon-cutting ceremony for Tamarack Elementary School - its 27th elementary school and final major project of the district’s $515 million 2017 capital construction bond. More than 600 community members, staff, students, contractors, community partners, and elected officials were in attendance for the festivities. U.S. Congresswoman Suzanne Bonamici joined Superintendent Reiman, Hillsboro Mayor Steve Callaway, School Board Chair Mark Watson, and Principal Christy Walters in delivering remarks. Following the ribbon-cutting ceremony, attendees were welcomed into the school for tours, celebratory cake, photo opportunities, and meeting teachers.

    Tamarack Elementary School was constructed on an eight-acre site for $40.8 million, the third and final new school based on a prototype already built at Brookwood and Atfalati Ridge Elementary Schools. With a capacity of 600 students in the 73,500 square-foot, two-story building,Tamarack will serve as an academic and community center for the developing South Hillsboro area. Special features of the school include: a solar rooftop array; a lighted, synthetic turf field striped for youth soccer and baseball/softball; and beautiful murals along the central hallway, called “learning street,” that represent the seasons in a tamarack forest. The school’s mascot, the river otter, is prominently incorporated in these landscapes. Also housed at Tamarack are K-8 Hillsboro Online Academy teachers and staff. Scroll down to see 51 photo highlights...

    Evento destacado: Gran inauguración de la Escuela Primaria Tamarack
    El miércoles, 23 de agosto, HSD llevó a cabo una ceremonia de inauguración y corte de listón para la Escuela Primaria Tamarack, su escuela primaria número 27 y el último gran proyecto del bono de construcción de capital de 2017 de $515 millones del distrito. Más de 600 miembros de la comunidad, miembros del personal, estudiantes, contratistas, socios comunitarios y funcionarios electos asistieron a las festividades. La congresista estadounidense Suzanne Bonamici acompañó al superintendente Reiman, al alcalde de Hillsboro, Steve Callaway, al presidente de la Mesa Directiva, Mark Watson, y a la directora Christy Walters para brindar sus discursos inaugurales. Después de la ceremonia de inauguración, los asistentes fueron recibidos en la escuela para realizar recorridos, comer una rebanada de pastel de celebración, tomar fotografías y conocer a los maestros.

    La Escuela Primaria Tamarack fue construida en un terreno de ocho acres por $40.8 millones y fue la tercera escuela nueva basada en un prototipo ya utilizado en las escuelas primarias Brookwood y Atfalati Ridge. Con una capacidad de 600 estudiantes, el edificio de Tamarack de 73,500 pies cuadrados y dos pisos servirá como un centro académico y comunitario para el área en desarrollo del Sur de Hillsboro. 

    Las características especiales de la escuela incluyen: una matriz solar ubicada en su techo; un campo de césped artificial iluminado y marcado para los juegos de fútbol juvenil y béisbol/softbol; y hermosos murales a lo largo del pasillo central, llamado «La calle del aprendizaje», que representan las estaciones que se producen en un bosque de alerces. La mascota de la escuela, nutria de río, está incorporada destacadamente en estos paisajes. 

    El edificio de Tamarack también cuenta con la presencia de maestros y miembros del personal de Hillsboro Online Academy K-8. Desplácese hacia abajo para ver 51 fotografías destacadas...



















































Aug. 16, 2023

  • Photo 1: installation of the seasonal murals on learning street is now complete, highlighting the tamarack forest in spring, summer, fall and winter.

    view of murals on learning street

    Photo 2: the addition of the spring and fall murals completes the installation.

    composite of spring and fall murals

    Photo 3: the secure entry vestibule is nearly complete; a mural with all seasons of the tamarack forest represented greets visitors as they enter.

    main entry with mural

    Photo 4: the main office is ready for visitors as staff go over the equipment.

    main office

    Photos 5 and 6: colorful rugs appropriate to each classroom grade level add to the finishing touches and match the environmental theme of the school.

    rug in kinder classroom

    rug in 4th-grade classroom

Aug. 8, 2023

  • It's down to the finishes! Crew members are working to complete the murals, lighting, gym and playgrounds. Hydroseeding and landscape cleanup will be coming soon.

    Photos 1 and 2: the "summer" mural is being installed, the second of four murals on learning street. The crew affixes and smooths each panel to assemble the whole picture.

    starting installation of summer mural

    adding panel to summer mural

    Photos 3 and 4: pendant lamps are going into the learning areas.

    installation of pendant lamp

    pendant lamps in a learning area

    Photo 5: an initial varnish coat and striping have been added to the wooden gym floor.

    striping on gym floor

    Photos 6 and 7: protective rubberized tiles are being added to the playground area and swingset.

    rubberized tiles on playground

    rubberized tiles at swingset

July 27, 2023

  • With the building structure, tiles and painting completed, work now moves to the final finishes that help to secure the building, complete the gym, and add school spirit to the building.

    Photos 1 and 2: installation of the secure entry vestibule is taking place next to the main office. Visitors will be required to check in at the office before they can pass through the second set of doors into the building.

    installation of entry vestibule

    view of main entrance under construction

    Photo 3: the gym floor continues to be assembled.

    assembly of gym floor

    Photo 4: the winter mural has been installed, the first of four seasonal scenes that will be placed along learning street (another mural representing all the seasons will be installed at the building entrance).

    installed mural of winter scene

    Photo 5: the remaining pylons await installation of their seasonal mural.

    view of learning street with winter mural installed

    Photo 6: the Tamarack horizontal logo has been added above the serving line in the cafeteria.

    horizontal logo in cafeteria

    Photo 7: the circular badge logo appears in the gym adjacent to the stage.

    circular badge logo in gym

    Photo 8: the folding door is being installed between the gym and cafeteria, enabling closure to separate the spaces as needed.

    folding door installation

July 20, 2023

  • Photo 1: walkways and landscaping continue to be installed around the campus.

    aerial view of campus

    Photo 2: the main entrance and courtyard are nearly complete.

    main entrance to school

    Photos 3 and 4: furniture has been moved into the classrooms, ready to be arranged.

    furniture moved into first-floor classroom

    furniture moved into second-floor classroom

    Photo 5: technology staff work on unpacking student Chromebooks and staff computers and moving the equipment into their respective classrooms.

    unpacking and moving classroom technology

    Photo 6: panels are being added to finish up the main office.

    finishing main office

    Photo 7: installation of the gym floor has started, with the wood slats arranged in position.

    gym floor slats in position for installation

    Photo 8: crew members apply the gym floor underlayment before the wood slats are placed.

    applying gym floor underlayment

July 13, 2023

June 28, 2023 - Century Students Help Move In

  • It takes a lot of hands to move furnishings into the new school building. Several students from Century High School volunteered part of their summer to unpack and place equipment, furniture and books into their proper rooms.

June 22, 2023

  • As the campus gets closer to its substantial completion date of June 30 (enabling occupancy), finishes such as carpeting, cabinetry and doors are being installed throughout the building, and sitework such as paving and concrete is nearly done. Note that landscaping, wall graphics, and other final touches will continue after this date.

    Photo 1: carpeting and countertops are being installed in the main office.

    finishing main office

    Photo 2: installation of cabinetry is complete in the staff workroom.

    staff workroom cabinetry

    Photo 3: with all the ceiling tiles in, this classroom is ready for furniture to be moved in.

    classroom ready for furniture

    Photo 4: glass now encloses the think tank area, which will provide a space for students to collaborate.

    glass installed for think tank

    Photo 5: partitions and doors have been installed for the restroom stalls.

    restroom stalls

    Photo 6: members of the volunteer Citizens Bond Oversight Committee gather in the media center to listen to an update on the project.

    CBOC members in media center

    Photo 7: student volunteers from Century helped shelve the hundreds of books in the bookcases.

    books shelved in media center bookcases

    Photo 8: the CBOC members look out over the gym from the stage area.

    CBOC members overlook gym

    Photo 9: acoustic tiles have been applied on the stage/music room walls.

    acoustic tiles in stage area

    Photo 10: outside, the "boulder" seats are arranged in the outdoor learning area.

    boulder seats in outdoor learning area

June 15, 2023

  • Photo 1: an aerial view of the paving work; the east (parent) parking lot has been fully paved, while the west (bus dropoff) parking lot is undergoing paving.

    aerial view of paving site work

    Photo 2: the asphalt crew lays out and smooths the asphalt from the dump truck.

    asphalt paving crew at work

    Photo 3: crew members set up the reinforcing bars for a concrete walkway.

    installing rebar for concrete walkway

    Photo 4: asphalt has been poured for the hard play areas.

    aerial view of play area under construction

    Photo 5: storefront windows and doors have been installed into the gym.

    storefront installation at gym

    Photo 6: the serving counter and roll-up window are now in place in the kitchen/cafeteria area.

    serving counter and window for kitchen

    Photo 7: the covered outdoor play area serves as a storage/staging area for additional doors and windows.

    doors stored in outdoor play area

    Photo 8: crew members push bookcases in place in the media center.

    installing media center bookcases

    Photo 9: cabinetry is being installed in the main office.

    main office cabinetry installation

    Photo 10: painting continues in the think tank, learning street and other areas of the building.

    painting think tank area

June 9, 2023

  • Photo 1: exterior siding has been installed on the south side of the building (along Kinnaman Street) and the outdoor learning area is taking shape.

    aerial view of south side of building

    Photo 2: concrete has been poured for additional walkways and the bases for the playgrounds, creating more definition at the north of the building.

    aerial view of play areas at north of building

    Photo 3: once the concrete is poured, it needs to be leveled and smoothed out.

    smoothing poured concrete

    Photo 4: "boulder" seats are incorporated into the concrete edges of the outdoor learning area.

    boulder seats installed for outdoor learning area

    Photo 5: the front door has been installed at the main entrance to the building, and rails have been added to the walls to anchor exterior siding.

    front door installed at main entrance

    Photo 6: the media center is now fully painted and cabinetry is starting to be installed. A crew member buffs the concrete floor.

    media center prepped for casework

    Photo 7: tilework and sink installations are completed in one of the bathrooms.

    tiled bathroom with new sinks

    Photo 8: in the kitchen, appliances are starting to be installed.

    installed kitchen appliances

June 2, 2023

  • Photo 1: crews are installing hardscaping for the playground bases and for sidewalks inside the campus.

    aerial view of construction so far

    Photo 2: on the south side of the building, siding is being added to the exterior walls and work continues on the outdoor learning area and swale.

    aerial view of south side of campus

    Photo 3: inside, the stainless steel work surfaces are being installed in the kitchen.

    installing kitchen work surfaces

    Photo 4: painting of the gym ceiling is complete.

    painted gym ceiling

    Photo 5: a crew member seals the joints in the HVAC ductwork.

    sealing HVAC duct joints

    Photo 6: sheetrocking is nearly complete on learning street.

    learning street sheetrocked

    Photo 7: the media center is painted and being prepped for cabinetry installation.

    painted media center

    Photo 8: tile is being installed in the bathroooms.

    tiling in bathroom

    Photo 9: cabinetry, tack and white boards, and classroom technology has now been installed in all classrooms.

    nearly-completed classroom

May 25, 2023

  • Photo 1: this aerial photo shows the completion of roofing work on top of the building. In the foreground, the covered play area has been fully roofed.

    aerial view of construction so far

    Photo 2: crew members distribute rock ballast on the rooftop. The ballast offers protection from heat and wind, and distributes weight across the roof. After being hauled up via a loader, the rock is distributed across the roof with a spreader and evened out with rakes.

    distributing roof rock

    Photo 3: the outdoor learning area is being framed for a concrete pour. Seating "boulders" are moved to their designated places.

    framing outdoor learning area

    Photo 4: the gym ceiling is being painted as a crew member outside checks the window seals now that the exterior brick has been installed.

    painting gym ceiling

    Photo 5: sheetrock is being custom-cut in the think tank area.

    sheetrocking think tank area

    Photo 6: projectors are being installed in all classrooms, part of the classroom technology package.

    installing classroom projector

    Photo 7: the elevator has been installed and ready to be wired up.

    installed elevator

May 19, 2023

  • Photos 1 and 2: these aerial photos show the site work in progress, including hardscaping for the playground, roofing for the covered play structure, and the solar panels recently installed on the building.

    aerial view of construction so far

    aerial view of solar panels on building

    Photo 3: crew members frame the area for the base of the playground swings.

    framing for swing area

    Photo 4: sheetrocking continues throughout the building interior, including tricky cutting and placement around the cafeteria area ceiling.

    sheetrocking around cafeteria ceiling

    Photo 5: concrete is buffed along learning street to prepare for polishing.

    buffing concrete along learning street

    Photo 6: the glass doors have been installed for entry into the STEAM lab.

    glass doors for STEAM lab

    Photo 7: sheetrocking of the pylons along learning street is nearly complete to prepare for installation of graphic murals.

    sheetrocked pylons along learning street

    Photo 8: crew members install large HVAC ductwork along a second-floor classroom hallway.

    HVAC duct installation in classroom hallway

    Photo 9: installation of tackboards and marker boards follow after painting of classrooms.

    installing tackboard in classroom

May 12, 2023 - Site Walk-through

May 5, 2023

  • Photo 1: roofing work and hardscaping for the playground area continues.

    aerial view of construction so far

    Photo 2: concrete has been poured for the outdoor learning area.

    concrete for outdoor learning area

    Photo 3: in the gym, sheetrock and low-voltage wiring continue to be installed.

    gym construction so far

    Photo 4: sheetrocking of the pylons along learning street and installation of the ceiling panels underneath has begun.

    construction along learning street

    Photo 5: on the second floor, finishing of the think tank and adjacent learning area continues.

    construction of think tank

    Photo 6: nearly all of the classrooms have been painted, with installation of cabinetry and countertops following the painting.

    painted classroom with cabinetry

April 28, 2023

  • Photo 1: it was a beautiful day for roofing the building and continuing to construct the top of the covered play area.

    aerial view of construction so far

    Photo 2: rubberized pellets have been added to the nearly-complete synthetic turf field.

    aerial view of newly-installed turf field

    Photo 3: crew members work on framing the hardscaping around the playground area.

    framing for hardscaping

    Photo 4: the base of the outdoor learning area is being compacted to prepare for a concrete pour.

    compacting base for outdoor learning area

    Photo 5: windows have been installed and sheetrocking continues in the gym.

    construction in gym

    Photo 6: framing work is in progress under the clerestory windows overlooking the learning street.

    framing under clerestory windows

    Photo 7: a second-floor classroom in the northeast corner is ready for painting.

    classroom prepped for painting

    Photo 8: in a kinder classroom on the first floor, windows have been installed and cabinetry is nearly complete.

    kinder classroom continues to be completed

April 13-14, 2023 - Site Walk-Through and Planning Team Tour

  • Take a walk through the Tamarack construction site in this video:

     

    Preparing for the School's Opening

    Planning for the school year has started in earnest at Tamarack — one of the highlights is the coordination of STEM and environmental science programming with the Oregon Museum of Science and Industry (OMSI). A tour of the project site on Friday, April 14, guided by Principal Christy Walters, provided insight into the available spaces and potential areas for curricular and programming activities.

    In addition to four group learning areas, the school also houses a STEAM lab, video production lab, and a think tank group work area.

    Photo 1: visiting the site were: Dave Laubenthal, OMSI Creative Director; Steve Tritz, OMSI Senior Director of Statewide and Community Engagement; Abby Jones, Tamarack planning teacher (6th grade); Christy Walters, Tamarack principal; and Sharon Angal, Tamarack planning teacher (2nd grade).

    planning group at front of gym

    Photo 2: Ms. Walters highlights features of one of the learning areas and the view of the learning street beyond.

    Walters showing learning area

    Photo 3: 6th-grade teacher Abby Jones sees her new, second-floor classroom for the first time, at the northeast corner of the building.

    teacher Angal in new classroom

    Photo 4: 2nd-grade teacher Sharon Angal claims her new classroom, located in the middle of the second floor.

    teacher Jones in new classroom

    Photo 5: the planning group checks out the area for the think tank, which is just starting to be framed. The think tank will be a glass-enclosed collaborative workspace for student groups to work on and present their projects.

    viewing think tank area

April 6, 2023

  • Photo 1: at the entrance to the school, windows have been framed and crew members are installing sheathing under the canopy.

    construction at front entrance

    Photo 2: the kitchen is getting sheetrocked.

    sheetrocking kitchen area

    Photo 3: concrete has been poured for the steps in the middle of the gym benches.

    concrete gym bench steps

    Photo 4: a crew member determines placement for a plumbing elbow in a second-floor ceiling.

    placing plumbing elbow in ceiling

    Photo 5: plumbing is being installed in a second-floor restroom.

    restroom plumbing installation

    Photo 6: a crew member bends a conduit to fit above the media center.

    bending conduit pipe

    Photo 7: casework is starting to be installed in painted classrooms, including these cubbies and cupboards.

    installing classroom casework

    Photo 8: cabinetry casework is also installed below the windows.

    casework underneath windows

    Photo 9: the culmination of data wiring will be the network room, which will house servers as well as connections to the district's fiber optic network.

    wiring to the network room

March 31, 2023

  • Photo 1: this aerial view shows the start of hardscaping between the field and building as well as continued work on the covered play area and building exterior.

    aerial view of campus construction so far

    Photo 2: masons add brick from the bottom to the top of the exterior of the gym.

    bricklaying on gym exterior

    Photo 3: a crew member prepares for a concrete pour for the steps in the middle of the gym benches.

    preparing concrete pour for gym bench steps

    Photo 4: concrete pours are also taking place on the stairway landings.

    concrete work on stairway landing

    Photo 5: hoods and other equipment are starting to be installed in the kitchen.

    hood installed in kitchen

    Photo 6: a crew member works on the electrical connections to a circuit box.

    connecting circuit box wiring

    Photo 7: the elevator chute has been framed on the second floor.

    framed elevator chute

    Photo 8: after drywall installation and taping is done, painting of the classrooms progresses.

    painting of classroom

    Photo 9: in the courtyard learning area, insulation is being added under the canopy rooftop.

    adding insulation under canopy roof

March 23, 2023

  • Photo 1: framing of the offices shows through the entrance of the school; above, windows are being framed on the second floor.

    front entrance of school under construction

    Photo 2: members of the Citizens' Bond Oversight Committee are shown the location of a mural highlighting the spring season of a tamarack forest.

    CBOC members shown mural location

    Photo 3: the bottom portion of the gym's concrete benches have been poured.

    formed concrete benches in gym

    Photo 4: a crew member adds insulation to the overhead plumbing.

    installing overhead pipe insulation

    Photo 5: drywall mud is being smoothed in one of the classrooms.

    smoothing drywall in classroom

    Photo 6: a soffit is being added off of a classroom ceiling.

    adding soffit to classroom ceiling

    Photo 7: HVAC ductwork is being installed in the classroooms.

    installing HVAC in classroom

    Photo 8: crew members continue adding brick to the building exterior.

    bricklaying on building exterior

March 16, 2023

  • Photo 1: construction of the front entrance to the building continues as crew members apply roofing tar above.

    front entrance of school under construction

    Photo 2: a mason applies finishing brick to a corner wall of the courtyard.

    laying brick on courtyard wall

    Photo 3: strips are applied over insulation to provide seam backing for exterior wall panels.

    applying backing strips for wall panels

    Photo 4: one crew member guides data wiring along a holding "basket" while another pulls it through; nearly 15 miles of wiring for devices and access points are being installed throughout the building.

    installing data wiring

    Photo 5: insulation is being cut to size to fit into the wall frames.

    cutting insulation to fit

    Photo 6: crew members cut ductwork pieces to fit the HVAC duct pathways.

    cutting HVAC ductwork

    Photo 7: it's a team effort to fit and connect HVAC duct pieces together.

    connecting HVAC ductwork

    Photo 8: concrete has been poured into the first level of the gym benches.

    concrete fills first level of gym bench

March 8, 2023

  • Photo 1: this aerial view shows continued framing of the front entry and roofwork.

    aerial view of construction to date

    Photo 2: exterior insulation is being applied around the windows along the building's back walls as well as backing strips for the exterior panels.

    installing exterior building insulation

    Photo 3: in the rear courtyard, bricklaying of the wall is nearly complete.

    brickwork along rear courtyard wall

    Photo 4: crew members are constructing the forms for the concrete benches in the gym, surrounded by ductwork yet to be installed.

    constructing concrete forms for gym benches

    Photo 5: framing surrounds one of the second-floor learning areas.

    framing for a learning area

    Photo 6: a crew member works on the plumbing for one of the bathroom areas.

    installing bathroom plumbing

    Photo 7: drywall is cut to fit over the remaining wall framing in one of the classrooms.

    cutting drywall for first-floor classroom

    Photo 8: a second-floor classroom's walls are nearly finished; protective paper covers the concrete floor.

    nearly-finished second-floor classroom

March 2, 2023

  • Photo 1: offices in the administration wing are being framed as the front entrance becomes more defined.

    front entrance of school under construction

    Photo 2: brick is being applied on the exterior of the building; this is the southeast corner of the school building.

    bricklaying along southeast corner of building

    Photo 3: brickwork lines the wall of the rear courtyard.

    brickwork along rear courtyard wall

    Photo 4: windows have now been installed in over half of the building.

    window installation on back of building

    Photo 5: framing is nearly complete along learning street; clerestory windows above the gym will bring in natural daylighting.

    framing constructed along learning street

    Photo 6: drywall installation in the kitchen area is complete.

    sheetrocked kitchen area

    Photo 7: drywall also has been installed on most of the first-floor classroom walls on the west side of the building.

    drywalled classroom

    Photo 8: westside second-floor classrooms are undergoing installation of drywall.

    classroom undergoing drywall installation

Feb. 17, 2023

  • Photos 1 and 2: framing for windows is being constructed. Some windows already have been installed for initial testing against water intrusion; the rest will follow once the installation method has been verified.

    window frame installation on south wall

    initial window installation

    Photos 3 and 4: roof timbers are being installed over the covered play area.

    roofing installation over covered play area

    contractor verifies roof timbers

    Photos 5 and 6: decorative finishing brick is being laid over sheathed exterior walls.

    brick being laid on west wall

    mason lays brick on sheathed wall

    Photos 7 and 8: interior work also continues as crew members install electrical conduit and wiring for lighting, power and security systems.

    crew member installs conduit

    crew member adds wiring in conduit

Feb. 6, 2023

  • Photo 1: drywall is starting to go up in the hallway for the utility rooms as well as the rest of the kitchen area.

    walls in utility room hallway

    Photo 2: overhead work continues in the gym to add fire sprinklers and conduit and to prepare for installation of HVAC ductwork.

    overhead work in gym

    Photo 3: the view of learning street to the east shows framing progress so far of classrooms and other spaces.

    view down learning street to east

    Photo 4: a welder secures roof beams and joists over the administration area.

    welding roof joists

    Photo 5: framing is going up in the office areas in the administration area.

    framing of offices in administration area

    Photo 6: hardscaping is starting to be installed at the front of the school.

    start of hardscape installation

    Photo 7: trees and other landscaping are ready to be planted in the beds of the parent dropoff/parking lot.

    landscaping plants for parent parking lot

    Photo 8: this aerial views shows the progress on the exterior and roofing so far.

    aerial view of construction progress

Jan. 31, 2023 - time lapse

  • A time-lapse video of construction from Feb. 2022 - Jan. 2023:

Jan. 26, 2023

  • Photos 1 and 2: these aerial views show exterior construction progress to date, from the front of the school (facing southeast) and the back of the school (facing northwest).

    aerial view of school construction at front

    aerial view of school construction at back

    Photo 3: crew members prepare a roof section with weatherproofing underlayers where the solar panels will be installed.

    installation of roof underlayers

    Photo 4: masons construct the trash enclosure outside of the kitchen area.

    constructing trash enclosure

    Photo 5: a crew member walks along the first floor of the learning street, in front of where a learning area and the STEAM lab will be constructed.

    first-floor learning street construction

    Photo 6: grids are installed under the roof to secure conduit lines. At the left is a doorframe into what will be an electrical room off of the stairwell.

    adding grid for conduit lines

    Photo 7: a view of learning street and classroom construction so far from the second floor.

    learning street construction viewed from second floor

    Photo 8: the courtyard area at the back of the school is being constructed behind the media center.

    rear courtyard under construction

Jan. 20, 2023

Jan. 12, 2023

  • Photo 1: work continues on framing the administration section of the building.

    framing in administration area

    Photo 2: a view of construction from the second floor along learning street facing west.

    learning street construction facing west

    Photo 3: second-floor classrooms are being enclosed with framing.

    framing second-floor classrooms

    Photo 4: a view of construction from the second floor along learning street facing east; the roofing canopy is nearly halfway done.

    interior construction progress along learning street

    Photo 5: a crew member prepares wiring for ceiling fixtures in the kitchen area.

    installing wiring for ceiling fixtures

    Photo 6: masons construct a concrete enclosure for equipment outside the kitchen area.

    concrete structure for equipment

    Photo 7: this aerial view to the south provides perspective of the extent of construction on the campus, including the site for the covered play area and the start of walkways along the campus.

    aerial view of campus construction toward the southwest

    Photo 7: the view of the campus to the north shows sheathing about halfway complete along the back of the building.

    aerial view of campus construction toward the north

Jan. 5, 2023

  • Photo 1: crew members begin adding forms for concrete pathways between the building and parking lot.

    framing for concrete pathway

    Photo 2: framing is being erected for the first-floor classroom walls along the learning street.

    framing for first-floor classrooms

    Photo 3: on the second floor, framing continues along the perimeter at the back of the building.

    framing for back of building

    Photo 4: the view of learning street toward the east shows the current progress of interior construction.

    interior construction progress along learning street

    Photo 5: masons are building up the play wall between the posts for the covered play area.

    building play wall

Last Modified on September 7, 2023