• construction timeline for Butternut Creek

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $6.4 million.

    October-November 2021

    • Street Improvements

    Improvements will be made to Southview Street adjacent to the new bus dropoff entrance, including new sidewalk and paving. These are required by our land use permit with Washington County as a condition for the campus renovations.

    COMPLETED

    • Campus Renovations

    Over summer 2021, the Butternut Creek campus underwent several renovations that included: safety and seismic upgrades, parent/bus dropoff improvements, addition of air conditioning to the HVAC system, and a new entry plaza. The portables were replaced with a permanent, modular building housing two classrooms. The entry vestibule was renovated to upgrade security and limit visitor access into the building. A new elevator, delayed by supply chain issues, was completed in the fall to provide ADA access between the main floor and the cafeteria.

    • Domestic Water Pipe Replacement

    In summer 2020, new domestic water pipe was installed throughout the Butternut Creek building to replace aging pipe.

    • New Playground

    Butternut Creek had a new playground installed in summer 2018. The play structure includes eight swings and ground-floor activities that are ADA-accessible. It is installed on a safer, padded tile surface (replacing the existing wood chips). Students also have a 1500 square-foot artificial turf playspace that can be used rain or shine.

    • Flexible Furniture

    Flexible furniture (FFE) was delivered in summer 2018. Research shows this type of furniture enhances the learning environment and increases student engagement.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Renovations: Emil Hameed
    • Entry vestibule: John Abel

    Architect/Engineer

    • Renovations: Mahlum Architects / AKS Engineering
    • Entry vestibule: Process-PDX

    General Contractor

    • Renovations and entry vestibule: Par-Tech Construction
Last Modified Yesterday at 10:17 AM