• Bond construction timeline for Farmington View

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $5.4 million

    Fall 2020

    The parent/bus dropoff area will be remodeled to enhance the safety of both pedestrians and drivers as well as to promote more orderly flow of traffic with additional queueing.

    Summer 2021

    Farmington View will be undergoing renovations in summer 2021 that include safety and seismic upgrades, equipment replacements and upgrades, and roofing.

    Completed Projects

    • New Playground

    Students were excited about their new playground upgrades that promote healthy play and exercise. The play structure, with ground-level ADA-accessible activities, was installed in summer 2018 on a safer, padded tile surface, and has an accompanying all-weather, synthetic turf play area.

    • Flexible Furniture

    New flexible furniture (FFE) was delivered to the school in summer 2018. Research has shown that this type of furniture helps stimulate student engagement and learning.

    • Modular Building

    The existing portables were replaced with a new permanent, modular building that includes two classrooms and restrooms. The modular building was installed in summer 2018.

  • Project Manager  

    Cornerstone Management Group

    • Modular building, playground: Rick Cunningham
    • FFE: Karyn Rainone

    Architect/Engineer

    • Modular building, playground: 3J Consulting, Inc.

    Contractor

    • Modular building: Five Star
    • Playground
      • Site work: Five Star Builders, Inc.
      • Structure: Cascade Recreation
      • Rubber tile: NW Playground Equipment
    • FFE
      • McDowell-Craig (desks)
      • School Specialty (seating)