• Bond construction timeline for Groner

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $6.5 million

    Summer 2022

    • Window Replacements

    The existing single-paned windows will be replaced with new, double-paned windows for greater energy efficiency and comfort.

    October 2021 - March 2022

    • Gym Repairs

    After discovery of roof truss deficiencies during seismic work, the gym (and underlying cafeteria) were closed as a safety precaution while repairs are being made. These include structural engineering and installation of steel beams to provide additional support for the gym's roof trusses. In the meantime, a temporary gym is being rented and was constructed in October 2021 at the back of the school to provide space for PE and other activities for students until the existing gym is repaired. 

    COMPLETED

    • Building Improvements

    Groner underwent extensive renovations throughout the building, including safety and seismic upgrades, roofing and domestic water pipe replacement. During this work, deficiencies were discovered in a roof truss in the gym, requiring repairs.

    • Flexible Furniture

    Flexible furniture (FFE) was delivered in summer 2018. Research shows this type of furniture enhances the learning environment and increases student engagement.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Building improvements: John Abel
    • FFE: Karyn Rainone

    Architects/Engineers

    • Window replacements: Mahlum Architects / PRC Engineering
    • Building improvements: Mahlum Architects / AKS Engineering

    General Contractors

    • Window replacements: tbd (bid date Jan. 12, 2022)
    • Building improvements: Inline Construction
    • FFE:
      • McDowell-Craig (desks)
      • School Specialty (seating)