• Bond construction timeline - Imlay

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors.

    Summer 2019

    • Flexible Furniture

    Imlay classrooms will receive flexible furniture (FFE) in summer 2019. Research shows this type of furniture enhances the learning environment and increases student engagement.

    Summer 2020

    • Renovations

    Renovations will take place in the Imlay building that include a roofing upgrade and safety improvements such as DAS, security cameras, interior door locks, and alert/warning systems.

    Completed Project

    • Floor Polishing

    Not originally part of the bond project list, aging floor tiles prompted the addition of this project. The tiles were removed from the front entry area, and the underlying concrete was polished in summer 2018. The result is a "new" - and lower-maintenance - floor.

  • Goal / Project

    Estimated Cost

    security camera Prioritize Safety and Security

    School safety upgrades

    • Interior door locks
    • Strobes, visual warning inside and outside
    • Security cameras
    • Improve line of sight from office to front door
    • Card key access - exterior doors
    • Alert button at front desk
    • Glass film at main door
    • Upgrade in-building radio communication
    • Improve in-building public safety communication capability

    $281,303

      

    building under construction Renovate and Repair Aging Schools

    Current infrastructure improvements

    • Roofing
    • Strip old floor tiles and polish flooring  (added June 2018)

     

    • 116,885
    • 68,335

    computer monitor; technology  Provide a Modern Education for Every Student

    Educational Technology (classroom)

    • CRT monitor replacement
    • Classroom projectors
    • Voice amplification
    • Wireless access points
    • Whiteboards
    • Document cameras
    • Student computers
    • Licensed staff computers
    • Classified staff computers
    • Elementary gymnasium audio/visual system

    491,342

      

    Student Achievement

    • Flexible classroom furniture

     

    • 273,290

    Total Investment

    $1,231,155

     

  • Project Manager 

    Cornerstone Management Group

    • Floor polishing: Rick Cunningham 

    Architect

     

    Contractor