• Bond construction timeline - Ladd Acres

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revise scope, and other factors.

    Summer 2019 Projects

    • Flexible Furniture

    In summer 2019, Ladd Acres classrooms will receive new flexible furniture (FFE) that promotes engagement and learning. Work will also begin on replacing the domestic water piping.

    Summer 2020 Projects

    • Improvements, New Gym, Playground

    Ladd Acres will undergo major renovations in summer 2020 with the construction of safety and seismic upgrades and the addition of air conditioning. A new, dedicated gymnasium for PE and activities - separate from the cafeteria - and an upgraded, ADA-accessible playground will be exciting additions for the Ladd community.

    Completed Projects

    • Parent/Bus Dropoff

    Ladd Acres' parking lots and parent/bus dropoffs were completely remodeled in summer 2018. The traffic pattern of the new dropoff areas will separate personal vehicles from the buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

    • Fencing

    New fencing and gates were installed in summer 2018 to enclose the perimeter of the school building for additional safety and security.

  • Goal / Project

    Estimated Cost

    security camera Prioritize Safety and Security

    School safety upgrades

    • Upgrade public address system
    • Strobes, visual warning inside and outside
    • Security cameras
    • Card key access - exterior doors
    • Alert button at front desk
    • Security fencing
    • Glass film at main door
    • Upgrade in-building radio communications

    $448,001

    School seismic upgrades

    503,592

    Parent/bus dropoff improvements

    1,103,051

    Playground upgrades

    189,000

    building under construction Renovate and Repair Aging Schools

    Current Infrastructure Improvements

    • Add air conditioning
    • Water pipe replacement

     

    • 1,477,735
    • 165,297

    Building renovation/enhancement

    • Construct new gymnasium - eliminate cafegymitoriums

     

    • 2,550,000

    computer monitor; technology  Provide a Modern Education for Every Student

    Educational Technology (classroom)

    • CRT monitor replacement
    • Classroom projectors
    • Voice amplification
    • Wireless access points
    • Whiteboards
    • Document cameras
    • Student computers
    • Licensed staff computers
    • Classified staff computers
    • Elementary gymnasium audio/visual system

    366,755

      

    Student Achievement

    • Flexible classroom furniture

    269,549

      

    Total Investment

    $7,072,980

  • Project Managers

    Hillsboro School District

    • Water pipe replacement: Jim Peterson

    Cornerstone Management Group

    • Parent/bus dropoff: Todd Johnson
    • Fencing: Luke Harkness

    Architect/Engineer

    • Parent/bus dropoff: 3J Consulting

    Contractors

    • Parent/bus dropoff: Kerr Contractors
    • Fencing: Town & Country Fence Co. of Oregon