W.L. Henry Bond Projects
Scope of Work
-
Please note that project renderings, costs and schedules may change due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $11.6 million
March 2020 - February 2021
- New Gym
An exciting addition to the campus is a new gymnasium that enables dedicated use for PE and activities, separate from the cafeteria, and which can serve as an emergency shelter for the community in case of a major earthquake. Construction is expected to begin in March 2020 and finish by February 2021.
Spring 2021
- Security Upgrades
After completion of the gym, W.L. Henry's existing security systems will be upgraded with such measures as security cameras, interior door locks, and alert/warning systems; this work is expected to be completed in spring 2021.
Summer 2021
- Upgraded Entry Vestibule
Better monitoring and limited entry into the building will result after upgrades to the entry vestibule.
COMPLETED
- Building Improvements
During the summer of 2020, the existing building underwent renovations that included seismic, HVAC and roofing upgrades.
- Parent/Bus Dropoff Areas
From June to August 2020, the parent/bus dropoff areas was modified to separate personal vehicles from buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.
- Flexible Furniture
New flexible furniture (FFE) was delivered to W.L. Henry classrooms in summer 2019. Research has shown the furniture to promote engagement and learning.
- Playground
W.L. Henry's playground was installed on a safer, rubberized tile surface in summer 2018, and students can now play rain or shine on a new, synthetic turf area.
- Modular Building
Due to permitting delays, W.L. Henry's new modular building, originally scheduled for summer 2018, was installed in November 2018. The permanent building houses three classrooms and includes a bathroom facility. The modular replaces the temporary, two-classroom, no-bathroom portable, which was demolished on March 23, 2018.
Contractors
-
Project Manager
Cornerstone Management Group
- Modular building, playground: Rick Cunningham
- Gym/renovations: Rick Cunningham
- Entry vestibule: John Abel
Architects/Engineers
- Modular building, playground: 3J Consulting, Inc.
- Gym: Mahlum Architects
- Entry vestibule: Process-PDX
Contractors
- Modular building: Five Star Builders
- Playground
- Site work: Five Star Builders, Inc.
- Structure: Cascade Recreation
- Rubber tile: NW Playground Equipment
- Gym/renovations: Emerick Construction
- Entry vestibule: tbd - bid date Feb. 23, 2021*
*grouped with Indian Hills, Minter Bridge, and Tobias entry vestibule projects