• aerial of WL Henry campus

  • construction timeline for WL Henry

     


Scope of Work

  • Please note that project renderings, costs and schedules may change due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $11.6 million

    March 2020 - February 2021

    • New Gym

    An exciting addition to the campus is a new gymnasium that enables dedicated use for PE and activities, separate from the cafeteria, and which can serve as an emergency shelter for the community in case of a major earthquake. Construction is expected to begin in March 2020 and finish by February 2021.

    Spring 2021

    • Security Upgrades

    After completion of the gym, W.L. Henry's existing security systems will be upgraded with such measures as security cameras, interior door locks, and alert/warning systems; this work is expected to be completed in spring 2021.

    Summer 2021

    • Upgraded Entry Vestibule

    Better monitoring and limited entry into the building will result after upgrades to the entry vestibule.

    COMPLETED

    • Building Improvements

    During the summer of 2020, the existing building underwent renovations that included seismic, HVAC and roofing upgrades.

    • Parent/Bus Dropoff Areas

    From June to August 2020, the parent/bus dropoff areas was modified to separate personal vehicles from buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

    • Flexible Furniture

    New flexible furniture (FFE) was delivered to W.L. Henry classrooms in summer 2019. Research has shown the furniture to promote engagement and learning.

    • Playground

    W.L. Henry's playground was installed on a safer, rubberized tile surface in summer 2018, and students can now play rain or shine on a new, synthetic turf area.

    • Modular Building

    Due to permitting delays, W.L. Henry's new modular building, originally scheduled for summer 2018, was installed in November 2018. The permanent building houses three classrooms and includes a bathroom facility. The modular replaces the temporary, two-classroom, no-bathroom portable, which was demolished on March 23, 2018.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Modular building, playground: Rick Cunningham
    • Gym/renovations: Rick Cunningham
    • Entry vestibule: John Abel

    Architects/Engineers

    • Modular building, playground: 3J Consulting, Inc.
    • Gym: Mahlum Architects
    • Entry vestibule: Process-PDX

    Contractors

    • Modular building: Five Star Builders
    • Playground
      • Site work: Five Star Builders, Inc.
      • Structure: Cascade Recreation
      • Rubber tile: NW Playground Equipment
    • Gym/renovations: Emerick Construction
    • Entry vestibule: tbd - bid date Feb. 23, 2021*

     

    *grouped with Indian Hills, Minter Bridge, and Tobias entry vestibule projects