• Construction timeline - Century

     


Scope of Work

  • Please note that project tasks, costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors.

    Fall/Winter 2018

    • Entry Security

    The front office area will be renovated to improve the line of sight to the front door, enhance entry security, streamline access into the building, and better monitor visitors to the school. After the start of each school day, all doors will be locked and new entrances will direct students, parents, and visitors directly to the front offices where they will need to check in. This is part of the safety and security measures occurring throughout the district. At Century, these measures also include: security cameras, card key access, strobes, and visual warning inside and outside the building

    • Turf Field and Lights

    This project is currently in the land use process. If the necessary permits are processed in time, we hope to begin construction in late fall 2018 with the objective of having the new field available for use in spring 2019. View the current site plan.

    Construction budget: $2.2 million

    Summer 2019

    • Roofing, Flexible Furniture

    Upcoming improvements include roofing upgrades and flexible classroom furniture (FFE).

    • CTE Renovations

    Classrooms will be renovated and upgraded for several CTE programs. This work is expected to start in May 2019, with substantial completion by the end of August 2019. Work being done includes:

      • Business/Student Store - new finishes and flooring, collaborative walls, lightingand flooring, collaborative walls, lighting upgrades, student store improvements toupgrades, student store improvements to include new prep area, HVAC improvements, electrical upgrades, add three-part sink, dishwasher/sanitizer.
      • Computer Technology
        • Room 101A - renovate clean maker space to include finishes, flooring, collaborative walls, power/cable management, add transparency.
        • Room 101B - renovate to include collaborative walls, power/cable management, lockable storage, add transparency
        • Room 105 - collaborative walls, overhead power/cable management, storage.
      • Culinary Arts - renovation to classroom area, build out similar to Liberty Culinary Arts program, commercial kitchen casework and shelving, upgrade ventilation and power, add dishwasher/sanitizer.
      • Early Childhood - install new modular building to include two classrooms (high school and preschool), kitchen area, office space, and storage.
      • Engineering (Rm 102) - add transparency, collaborative walls, power/cable management, lockable storage.
      • Graphic Design - collaborative room finishes, flooring, add transparency.
      • Health Science - collaborative walls in lab, new double sink, finishes and flooring, data and power upgrades, storage and lighting upgrades.

    Construction budget: $2.2 million

    Completed Projects

    • DAS

    A distributed antenna system (DAS) is installed to ensure that first responders can communicate between themselves throughout all areas of the building. This safety-related project incorporates cable and antennae that boost the radio signals on the first responders' operating frequencies and was completed in May 2018.

  • Project Manager 

    Cornerstone Management Group

    • In-building radio communication/DAS: Todd Johnson
    • Entry security: Mary Dolan
    • Renovations/CTE expansion: Mary Dolan
    • New turf field: Becca VandeWalle

    Architect/Engineer

    • DAS: AWS Communications
    • Renovations/CTE expansion:
      • BLRB Architects (architectural design)
      • Sazan Group (electrical, mechanical, plumbing, fire protection)
    • Turf field: AKS Engineering & Forestry

    Contractor

    • DAS: Reece