• Construction timeline for Admin Ctr


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, and other factors. Projected budget: $1.7 million.

    Spring 2022-Summer 2023

    • Data Center Renovations

    Renovations in the data center continue with phase 2 work, including fireproofing of the network room to allow installation of a new uninterruptible power system. The windows have been removed, and walls added and painted over.

    Due to supply chain delays, the UPS arrived in spring 2023 and is currently being installed over the summer break.

    COMPLETED

    • Entry Vestibule, Restroom

    The first-floor entry vestibule was renovated with additional doors and access card entry to upgrade security and monitoring of visitors into the building. Doors and access card entry also were added to the second floor.

    The non-gender restroom on the first floor was upgraded with new flooring, fixtures, and addition of an infant changing table.

    • Data Center Renovations (Phase 1)

    Housings for servers and network equipment were updated in early 2022 in the first phase of renovations to the data center.

    • DAS

    A distributed antenna system (DAS) ensures that first responders can communicate between themselves throughout all areas of the building. This safety-related project incorporates cable and antennae that boost the radio signals on the first responders' operating frequencies. This project was completed in August 2019.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Data center, renovations: John Abel / Luke Harkness

    Architect/Engineer

    • Data center (phase 1): Interface Engineering
    • Data center (phase 2) and other renovations: Process PDX

    Contractor

    • Data center (phase 1): Global Electric
    • Data center (phase 2) and other renovations: Inline Construction
Last Modified on June 26, 2023