• Timeline for Administration Center projects


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, and other factors. Projected budget: $1.4 million.

    Summer 2022

    • Entry Vestibule, Restroom

    The entry vestibule will be renovated to provide added security and better monitoring of access into the building. The restroom also will be upgraded.

    Spring-Summer 2022

    • Data Center Renovations

    Renovations in the data center continue with phase 2 work to install fireproofing of the network room and an upgraded uninterruptible power system.

    COMPLETED

    • Data Center Renovations (Phase 1)

    Housings for servers and network equipment were updated in early 2022 in the first phase of renovations to the data center.

    • DAS

    A distributed antenna system (DAS) ensures that first responders can communicate between themselves throughout all areas of the building. This safety-related project incorporates cable and antennae that boost the radio signals on the first responders' operating frequencies. This project was completed in August 2019.

Contractors

  • Project Manager

    Cornerstone Management Group

    • Data center, renovations: John Abel / Luke Harkness

    Architect/Engineer

    • Data center (phase 1): Interface Engineering
    • Data center (phase 2) and other renovations: Process PDX

    Contractor

    • Data center (phase 1): Global Electric
    • Data center (phase 2) and other renovations: Inline Construction
Last Modified on June 6, 2022