2020 Project Schedule
The table below lists projects that are wrapping up (from previous year) in 2020 or starting in 2020.
NOTE: Project schedules are subject to change due to permitting processes and unforeseen or additional scope. Gray-shaded areas illustrate the current timeline and duration of each project. Anticipated start dates are in green and are at the beginning of the project timeline; expected completion dates for the final tasks are in red at the end of the timeline.
| School / Building | Project Description | 2020 | 2021 | |||||||||||||||||
| Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | ||
| Brookwood ES | New school construction | COMPLETE | ||||||||||||||||||
| R.A. Brown MS | Seismic, roofing, HVAC, water pipe, DDC, painting (summers only) | COMPLETE | ||||||||||||||||||
| Century HS | Roofing | COMPLETE | ||||||||||||||||||
| Eastwood ES | Roofing | COMPLETE | ||||||||||||||||||
| ES28 (North Plains area) | New school construction | COMPLETE | ||||||||||||||||||
| Evergreen MS | New addition | COMPLETE | ||||||||||||||||||
| Glencoe HS | New addition, roofing, HVAC, renovations, parking lots, CTE | COMPLETE | ||||||||||||||||||
| WL Henry ES | New gym | COMPLETE | ||||||||||||||||||
| Building and dropoff improvements | COMPLETE | |||||||||||||||||||
| Hillsboro HS | Major renovations, roofing, HVAC, CTE, electrical upgrade | COMPLETE | ||||||||||||||||||
| Parking lot improvements | COMPLETE | |||||||||||||||||||
| Hillsboro Online | Furniture | COMPLETE | ||||||||||||||||||
| Imlay ES | Roofing | COMPLETE | ||||||||||||||||||
| Indian Hills ES | Building improvements | COMPLETE | ||||||||||||||||||
| Ladd Acres ES | Oct 2020-Aug 2021: new gym | COMPLETE | ||||||||||||||||||
| Liberty HS | Roofing | COMPLETE | ||||||||||||||||||
| McKinney ES | Oct 2020-Aug 2021: new gym; Summer 2021: building improvements. | COMPLETE | ||||||||||||||||||
| Miller Big Picture | Roofing, furniture | COMPLETE | ||||||||||||||||||
| Minter Bridge ES | New gym | COMPLETE | ||||||||||||||||||
| Mooberry ES | Complete gym (March), playground (April) | COMPLETE | ||||||||||||||||||
| North Plains ES | New gym | COMPLETE | ||||||||||||||||||
| Dropoff improvements | COMPLETE | |||||||||||||||||||
| South Meadows MS | Furniture | COMPLETE | ||||||||||||||||||
| Transportation & Support Services | New construction | COMPLETE | ||||||||||||||||||