Skip To Main Content

Project Updates

July 20, 2023

Photos 1 and 2: the modular housing for the uninterrruptible power supply is in place (the floor was also reinforced to support its weight).

housing for UPS

UPS housing

Photo 3: each battery module is placed in its slot in the housing.

slots for UPS batteries

Photo 1: the floor platform is being prepared for installation of the new uninterruptible power supply.

floor platform for UPS installation

Photo 2: crew members take measurements to prepare placement of the UPS.

measuring to prepare for UPS placement

Photo 1: temporary walls fully enclose the work area for the current phase of fireproofing in the data center/network room.

work area enclosed by temporary walls

Photo 2: care must be taken while working above live servers to prevent fireproofing material from damaging them.

fireproofing over servers

Photos 3 and 4: a temporary structure covers up a server rack as fireproofing takes place directly overhead (protective insulation sheets are placed around the structure during work). Fans between the top of the structure and the servers help keep them cool. After a successful inspection, the ceiling grid can be re-installed and the project moved on to the next phase.

temporary structure protects server rack from fireproofing work

fireproofing in a corner of the network room

Photo 1: a fire damper has been installed above the ceiling grid in the data center/network room.

fire damper above ceiling grid

Photo 2: temporary walls form a perimeter around the current work area.

temporary walls for work area

Photo 3: the main underlying issue for fireproofing is to prevent sprayed material from entering the still-operational servers. A temporary covering structure will be built as a solution. The project foreman demonstrates the use of insulating sheets that will be placed as side covers. These coverings still allow air circulation around the servers while protecting them.

demonstrating use of insulation to protect servers from fireproofing material

Photo 4: in the hallway, the spaces for the former windows have been drywalled and painted over.

hallway windows removed, covered with drywall

Photo 1: "crash" bars (also known as panic hardware) have been added to the entry vestibule doors.

vestibule doors with installed hardware

Photo 2: the old windows in the network room have been removed and covered with drywall to more securely enclose and fireproof the room.

drywall replaces old windows in network room

Photo 3: final installation of fixtures will complete the bathroom renovation.

fxitures to be installed in bathroom

Photos 1 and 2: after removal of protective plastic around wires and conduit, fire-proofing of the first quadrant of work (ceiling) in the network room has been completed. Next comes the tricker area between the server racks (covered in plastic).

fire-proofing of north section of network room ceiling

fire-proofing of south section of network room ceiling

Photos 3 and 4: doors have been added to the vestibule in the front office and the entrance to the second floor hallway.

doors added to office vestibule

doors added to second-floor hallway entrance

Photo 1: new fixtures have been added in the renovated bathroom.

new fixtures in bathroom

Photos 2 and 3: special paint will be applied to the ceiling and walls of the network room to minimize the impact and spread of a fire.

ceiling and racks in network room

walls of network room

Photo 1: new doors will be delivered shortly for the newly-painted vestibule and applications office doorways.

trimmed vestibule doorway

Photo 2: the trim and drywall around the doorway also have been painted inside the applications office.

painted applications office doorway

Photo 3: tile has been installed in the renovated bathroom.

tile in renovated bathroom

Photo 1: the new vestibule and applications office doorways have been sheetrocked and trimmed.

sheetrocked vestibule

Photo 2: a view of the new applications office doorway from inside the office.

interior of applications office doorway

Photo 3: renovations continue in the single bathroom.

bathroom renovation

Photos 1-3: crew members are about to sheetrock over the framing in the entry vestibule and the new doorway into the applications office.

vestibule doorway sheetrocking

exterior of applications office doorway framing

interior of new applications office doorway

Photo 4: new plumbing and drainage has been added as part of the bathroom remodeling.

new plumbing and drainage in bathroom

Photo 1: framing has been added for the new vestibule doorway in the reception area.

framing for new vestibule doorway

Photo 2: a new doorway has been cut out in the applications office.

new door cutout for applications office

Photo 3: a new doorway has been framed and sheetrocked for access to the second floor.

doorway on second floor hallway

Photo 4: in the shower/bathroom area, crew members get ready to cut into the concrete floor to install new pipe and drainage.

preparing for concrete cutting

Photo 1: a crew member installs protective plastic sheeting to separate the construction area and prevent construction dust from the Board Room, where the receptionist and applications staff are temporarily housed.

installing protective plastic sheeting

Photo 2: a temporary door has been installed to allow limited entry from the vestibule construction area into the building interior.

temporary doorway into building interior

Photo 3: the shower room is being prepared for remodeling.

preparations for shower room remodeling

Photo 1: this is what the entry vestibule looks like now.

Administration Center vestibule before remodeling

Photo 2: a new doorframe has been installed into the first-floor hallway.

vestibule doorframe into hallway

Photo 3: a view into the vestibule from the hallway.

view from hallway to vestibule