Skip To Main Content

2021 Project Archive

Virtual Tour, Oct. 2021

First Day of School, Sept. 9, 2021

Dedication & Open House, Sept. 2, 2021

Open house program - provides more information about Atfalati Kalapuya history, the school mascot and colors, and the artwork and quotations located throughout the school.

Photos 1-8: finishing touches are being added to the campus and furniture arranged as work nears completion.

  • Main entry

main entry

  • Main office

main office

  • Learning streeet

learning street

  • Think tank (second floor)

think tank

  • Classroom

classroom

  • Learning area

learning area

  • Gymnasium

gymnasium

  • Covered play area

covered play area

Photos 1 and 2: crew members install rubberized tile squares on the playground, providing a safer and softer surface than the typical barkdust for children to play on.

rubberized tile on playground

installing rubberized tile under play structure

Photo 3: the parent dropoff/parking lot is being ground and repaved after months of wear and tear from heavy construction vehicle use.

repaving parking lot

Photo 4: finishing covers are being installed in the cafeteria serving area.

finishing cafeteria serving area

Photo 5: the fold-up gym divider is installed; this separates the gym from the commons/cafeteria area when needed.

fold-up gym divider

Photo 6: the wood floor in the gym is completed; next comes sanding and sealing.

completed wood floor in gym

Photo 7: a first-floor restroom area is finished.

finished restroom sinks

Photo 8: furniture is being arranged in every classroom, ready for incoming students.

classroom with arranged furniture

Photos 1 and 2: exterior wall panels are being installed around the covered play structure and ceiling panels underneath to finish up the structure.

covered play wall panel installation

covered play ceiling panel installation

Photo 3: this aerial photo shows the progress of the hardscaping and landscaping at the front of the building.

aerial view of building hardscaping and landscaping

Photos 4-6: inside the building, finishes are being completed throughout, including the gym and commons area, the learning street, and the restrooms.

nearly finished gym

finishing up the learning street

restroom finishes

Photos 1 and 2: concrete is being poured and smoothed for the walkways at the front of the school.

aerial view of front courtyard under construction

smoothing out concrete walkways

Photo 3: a crew member cleans up the playground area in preparation for installation of the play structure.

playground area pre-installation cleanup

Photo 4: construction and finishes continues in the gym, including installation of the basketball hoops.

gym under construction

Photo 5: the framing for the cafeteria service counter is ready for installation in front of the kitchen area.

cafeteria service area under construction

Photo 6: crew members take measurements in the elevator shaft.

elevator shaft measurements

Photo 7: the upper portion of the learning street is primed and ready for final painting and graphics.

primed learning street area

Photo 8: the think tank continues to be constructed; glass panels will enclose the room.

think tank room construction

Photo 1: masons apply brick to the remaining exposed portion of the gym, now that the windows are completely finished.

masons apply brick to gym exterior

Photo 2: construction of hardscaping and walkways continues at the front entry of the school building.

hardscaping of front entry of school building

Photo 3: conduit and wiring continue to be installed in the ceiling grid of the commercial kitchen area.

ceiling work in commercial kitchen area

Photo 4: the large wall in the commons/cafeteria area is a blank slate ready for application of graphic art.

blank wall of commons/cafeteria

Photo 5: drywall mud has been smoothed and the ceiling painted in the gym.

ready-to-finish gymnasium

Photo 6: in the learning street, sheetrocking and mud application and smoothing are complete.

ready-to-paint learning street

Photo 7: a first-floor classroom is being prepared for installation of its whiteboard and other classroom technology.

first-floor classroom prepped for technology installations

Photo 8: on the second floor, the ceiling grid is installed and nearly ready for ceiling tile installation.

second-floor classroom with unfinished ceiling

Photo 9: the "pony wall" in this second-floor learning area is one of four that will be finished with graphic art.

unfinished second-floor learning area

Photos 1 and 2: the parent/visitor parking lot is getting paved.

aerial view of parking lot paving

paving of parking lot

Photo 3: crew members install the roof panels above the gym.

installing roof panels

Photo 4: a view of the construction work at the front entry.

front entry construction work

Photo 5: doors are being installed at the front, main entry as well as the side entrances of the building.

installation of entry doors

Photo 6: installation of the security system continues.

security system installation

Photo 7: tackboard has been installed in the first-floor classrooms.

tackboard installation in classroom

Photo 8: one of the restroom areas has started to be tiled.

tiling of restroom area

Photo 9: sheetrocking of the walls in the gym is nearly finished.

sheetrocking of gym walls

Photo 10: construction continues around the think tank area. Screens along stairwells and open common areas have been installed throughout the building.

think tank area construction

Photo 1: a crew member applies drywall mud around the windows high above the learning street.

applying drywall mud above learning street

Photos 2 and 3: sheetrocking work continues in the learning street area as well as in the gym and commons. Classroom sheetrocking is done.

sheetrocking in learning street

sheetrocking in gym

Photo 4: crew members install large HVAC ducts in a second-floor classroom as work on weatherstripping windows occurs outside.

installing large HVAC ducts in classroom

Photo 5: one of the carpentry crew reaches for a wire high up in the ceiling as part of her work in a second-floor classroom.

reaching for a wire in the ceiling

Photo 6: the polished concrete floor in a second-floor classroom reflects the daylight coming in from the windows. The floor will be covered with protective, heavy-duty paperboard as casework and finishes are installed.

polished floor in second-floor classroom

Photo 7: a balustrade is being delivered for installation on one of the stairways.

delivering stair balustrade

Photo 8: forms have been set for concrete walkways at the entry of the school as part of the continued work on the hardscapes. A bench already has been poured.

concrete forms at school entry

Photo 1: an aerial view of the south side of the school shows the exterior work in progress, including hardscaped areas and walkways.

aerial view of south side of school under construction

Photo 2: concrete work for the plaza area adjacent to the media center is complete; irrigation lines are starting to be installed for the landscaped beds.

concrete plaza area

Photo 3: crew members pour and shape concrete into the forms for curbs in the parent/visitor parking lot.

pouring curbs for parking lot

Photo 4: concrete work is also taking place at the front entry and sides of the building.

concrete work at front of school

Photo 5: inside the building, cabinetry is being lifted to the second floor to install in classrooms and learning areas.

lifting cabinetry for second-floor classrooms

Photo 6: the final sheet of drywall is installed in one of the second-floor classrooms.

installing last sheet of drywall

Photo 7: a second-floor classroom has been completely sheetrocked and ready for cabinetry installation.

sheetrocked second-floor classroom

Photo 8: the learning street construction continues to progress.

learning street construction progress

Photo 1: sheetrock continues to be installed over the insulation on the learning street.

learning street construction progress

Photo 2: lighting fixtures and ceiling grids have started to be installed in first-floor classrooms.

first-floor classroom ceiling work

Photo 3: in a second-floor classroom, the concrete floor is scrubbed and cleaned before cabinetry and casework are installed.

cleaning concrete floor in classroom

Photo 4: concrete has been poured and is being smoothed for the small plaza next to the media center.

smoothing out fresh concrete on plaza

Photo 5: aerial view of the concrete pour in the plaza area.

aerial view of plaza concrete pour

Photo 6: a walkway is framed for an upcoming concrete pour.

framing for concrete walkway

Photo 7: an aerial view of the recently-poured curbing for the parent dropoff and visitor parking lot.

aerial view of parking lot curbing

Photo 1: an aerial view of the installed synthetic turf field.

aerial view of turf field

Photo 2: "crumb rubber" is dispensed onto the turf field. The crumb rubber, typically made from pulverized car tires, prevents the artificial grass blades from matting, provides more bounce on the field, and cushions impacts during play.

dispensing crumb rubber onto turf field

Photo 3: a dispenser truck is filled with more crumb rubber.

filling dispenser with crumb rubber

Photo 4: crew members install fixed louvers on the windows at the back of the building.

installing window louvers

Photo 5: a form is being built for concrete seating behind the media center.

building concrete form for seating

Photos 6 and 7: casework and cabinetry are being installed in the first-floor classrooms.

crew member cuts cabinetry to size

cabinetry installed in first-floor classroom

Photo 1: crew members smooth out and line up a section of turf over another before sewing them together.

smoothing out turf section

Photo 2: it takes a team to keep the edges of turf sections lined up as they are sewn together.

sewing turf sections together

Photo 3: this aerial view shows all the exterior construction activity, from the turf area to the covered play area and to the roof and siding of the building.

aerial view of construction area

Photo 4: the walk-in refrigeration units have been installed in the kitchen area.

installed walk-in refrigeration units

Photos 5: another piece of HVAC duct is installed in the commons area.

duct installation

Photos 6 and 7: priming of sheetrock has begun in the first-floor classrooms and hallways.

priming sheetrock

smoothing primed sheetrock

Photo 8: the concrete floor in one of the classrooms is being buffed.

buffing concrete floor

Photo 1: a truss is being lifted to the top of the roof beams on the covered play area.

lifting truss to roof beams

Photo 2: on one side, a crew member settles the truss into place (his counterpart does the same on the other side).

placing truss section

Photo 3: about a third of the trusses have been placed so far. Beyond the covered play area, masons are laying large concrete blocks above the trash enclosure.

partially-trussed covered play area

Photo 4: another truss is being transported to be installed over the covered play area.

transporting truss

Photo 5: in the kitchen area, the walk-in refrigerator and freezer units are starting to be installed.

starting installation of walk-in refrigerator

Photo 6: a crew member uses a laser level to take measurements on the drywall in one of the second-floor classrooms.

using laser level for measurement

Photo 7: inside, looking out at a crew member applying weatherstripping to the second-floor windows.

installing window weatherstripping

Photo 1: an aerial view of the work applying the fine gravel layer for the turf field base.

aerial view of turf field preparations

Photo 2: a bulldozer and a compactor work together to even out gravel on the field.

equipment smoothing out gravel

Photo 3: brick masonry work and installation of window frames continues on the west side of the building .

masonry and window framing work

Photo 4: at the back of the media center, brickwork is completed, and preparations begin to apply building siding.

exterior siding preparation

Photo 5: the frame for the scoreboard is installed in the gym.

installing scoreboard frame

Photo 6: security cabling is installed in a hallway ceiling.

installing security cable

Photo 7: in a second-floor classroom, a polisher stands ready to smooth and polish the concrete floor.

concrete polisher in unfinished classroom

Photo 8: installation of insulation batting and sheetrock continue in the second-floor classrooms.

stack of sheetrock to be installed in classroom

Photo 1: pipe and conduit continue to be worked on in the kitchen area.

pipe and conduit work in kitchen

Photo 2: a crew member cuts framing for one of the second-floor learning areas.

framing work in learning area

Photo 3: insulation is stacked and ready to be installed inside the gym and commons area.

interior of gym under construction

Photo 4: ductwork for HVAC continues to be added in a first-floor classroom.

HVAC ductwork in first-floor classroom

Photo 5: asphalt has been paved in the covered play area.

asphalt paved in covered play area

Photo 6: exterior work continues at the main entry.

main entry under construction

Photo 7: an aerial view of construction at the front of the school.

aerial view of front construction

Photo 8: an aerial view of construction at the back of the school.

aerial view of back construction

Photo 1: steel and masonry are going up for the covered play structure on the east side of the campus. Beyond it, siding and brickwork are starting to envelop the school building's exterior.

building covered play structure

Photo 2: gravel continues to be laid for the base layer of the synthetic turf field in preparation for cement treatment.

laying gravel base for turf field

Photo 3: an aerial view of the campus, showing construction activity in many areas.

aerial view of campus under construction

Photo 4: a drainage pipe is being installed for the entry canopy.

drainage pipe installation under entry canopy

Photo 5: at the back of the building, brick is starting to be laid on the wall outside the media center.

laying brick on exterior media center wall

Photo 6: a first-floor classroom has been sheetrocked. HVAC ducts stand ready to be installed in the ceiling.

first-floor classroom construction

Photo 7: a view from the second floor down the learning street shows framing is complete along the corridor and sheetrocking has begun.

view of learning street under construction from second floor

Photo 8: insulation and sheetrock are being installed in second-floor classrooms.

second-floor classroom construction

Photos 1 and 2: crew members work carefully as a team to install panes of glass in the gym window frames.

raising a glass pane for installation

installing a glass pane in a gym window

Photo 3: concrete is poured and smoothed for the walkways and around the masonry base of the covered play structure.

pouring concrete for covered play structure perimeter

Photo 4: the permeable membrane has been laid and gravel is being applied to the base of the synthetic turf field.

installing gravel base for turf field

Photo 5: crew members are installing some vertical framing above the commons entry area.

installing vertical framing for commons entry

Photo 6: water heaters have been installed in one of the utility rooms.

water heaters in utility room

Photo 7: many of the first-floor classrooms have been sheetrocked, like this one.

sheetrocking in first-floor classroom

Photo 8: a view of one of the first-floor learning areas and corridor shows insulation installed in the walls; sheetrocking is next.

first-floor learning area under construction

Photo 1: the covering straw is being removed from the playing field to prepare for an upcoming cement treatment.

removing straw from field

Photo 2: roof beams have been placed above the columns for the covered play structure. Beyond, siding has been installed on the east side of the building and brickwork continues at the front.

view of east side of building and structural steel for covered play structure

Photo 3: crew members install the vertical framing for the wall between the gym and the learning street.

installing vertical framing for gym/corridor wall

Photos 4 and 5: insulation and sheetrock continue to be installed in "dried-in" areas.

crew member screws in sheetrock

crew member reaches to install insulation

Photo 6: a crew member screws in a plate to cover a wiring path. The standard framing is pre-cut with these paths, which are used to string wiring inside walls, but is not needed in windows.

crew member screws in covering plate

Photo 1: steel has arrived for the covered play structure.

aerial view of structural steel for covered play structure

Photo 2: bricks have started to be laid for the ball wall of the covered play structure.

bricks laid for ball wall

Photo 3: the concrete perimeter has been poured for the playground.

aerial view of playground concrete perimeter

Photo 4: roofing work and framing continue.

aerial view of roofing work

Photo 5: crew members install sheetrock in the kitchen area.

sheetrock installation in kitchen area

Photo 6: more sheetrock is piled and ready to be installed in the kitchen.

pile of sheetrock in kitchen

Photo 7: a crew member assembles conduit in a corridor ceiling.

assembling conduit in corridor ceiling

Photo 1: this aerial view shows the exterior work and roofing so far on the building.

aerial view of building construction

Photo 2: masons start the bricklaying on the east side of the building.

masons applying bricks

Photos 3 and 4: framing and fence posts begin to define the playground area.

aerial view of playground framing

framing around playground area

Photo 5: sheetrock is starting to be installed in areas "dried in" by finished roofing.

sheetrock installation

Photo 6: a crew member works on the copper pipes around a large HVAC duct.

working on copper pipes

Photo 1: crews coat finished sections of the rooftop with tar, while others install panels in another area to prepare for coating.

coating part of roof with tar

Photo 2: this aerial view of the construction site shows grading of the playground area (bottom left), completed concrete footings for the covered play area (center), and the roofing work being done on the building (right).

aerial view of play area site work and roofing work

Photo 3: the wood frames used for the concrete footings for the covered play area are removed and cleaned.

exposed concrete footings

Photo 4: plumbing and other tubing snake through the framing for the kitchen area.

tubing framing for kitchen area

Photo 5: a couple crew members install ceiling beams under the cover for the outdoor learning area, while another cuts more pieces to the right size.

installing ceiling beams

Photo 6: a large HVAC duct is pieced together above an office and corridor area.

piecing HVAC duct together

Photos 1 and 2: installation of the roof is nearing completion.

view of unfinished front entrance

crew member working on rooftop

Photo 3: sheathing continues to be installed around the exterior of the school.

aerial view of unfinshed back of school

Photo 4: crew members work on positioning conduit behind the stage.

working on conduit

Photo 5: a crew member affixes wall framing to the ceiling framing in the second-floor bathroom area.

affixing framing

Photo 1: a crew member cuts framing for the interior walls; behind him are the administrative offices.

cutting framing for walls

Photos 2 and 3: installing HVAC ductwork in the media center area.

installing HVAC ductwork

ductwork above framed media center

Photo 4: inside the gym facing west.

gym section under construction

Photo 5: the learning street facing east; the gym and commons area are to the left.

learning street under construction

Photo 6: the learning street from the second floor, facing west; classrooms are on the left and gym on the right.

view of unfinished learning street from second floor

Photo 1: sheathing continues to be installed on the building exterior.

sheathing installation

Photo 2: welders work on a roof beam.

welding roof beam

Photo 3: plumbing rough-ins in what will be a second-floor bathroom.

plumbing rough-ins

Photo 4: sparks fly from cutting of a roof panel.

sparks from roof panel cutting

Photo 5: in one classroom, a crew member trims framing pieces.

crew member trims framing

Photo 6: in another classroom, an overhead pipe is being worked on.

overhead pipe work

Photo 1: an aerial view of the back of the school, looking to the north.

aerial view of back of school

Photo 2: crew members cut framing to size before installing each piece to the side of the building.

cutting framing pieces

Photo 3: welders configure steel beams into a frame that will be placed on the side of the rooftop.

welding steel beams

Photo 4: a view of continuing construction inside the learning street, looking to the east.

continued learning street construction to the east

Photo 5: HVAC ductwork continues to be installed in the ceiling areas.

HVAC ductwork installation

Photo 1: roof panels are being installed above the classroom wing.

roof panel installation

Photos 2 and 3: aerial views of the exterior show the progress of framing and sheathing installation.

sheathing installation on the north side of the building

sheathing installation on the south side of the building

Photo 4: a view of the learning street under construction, looking to the east; steps are starting to be installed on the main staircase.

learning street construction to the east

Photo 5: viewing the first-floor classroom wing from the learning street.

first-floor classroom wing under construction

Photo 6: the commons/cafeteria and kitchen areas under construction as viewed from the second floor.

commons and kitchen areas under construction

Photo 7: the gym under construction; the stage and main offices lie beyond.

gym under construction

Photos 1 and 2: steel beams for the staircases have been installed in the middle of the building.

main staircase framing

second staircase framing

Photo 3: in the first-floor classroom hallway, HVAC ductwork has been added to the plumbing conduit in the ceiling.

installing HVAC ductwork in unfinished ceiling

Photos 4 and 5: framing for walls and windows are completed on the south side of the building for the first- and second-floor classroom wings.

first-floor classroom wall framing

second-floor classroom wing framing

Photo 6: crew members attach framing pieces to the building exterior.

attaching exterior framing pieces

Photo 7: roof deck panels are affixed to the building's girders.

affixing roof deck panels

Photos 1 and 2: concrete is being poured on the second-floor decking on the southwest side of the building.

second-floor concrete pour on southwest side of building

view of the building construction from the northwest

Photos 3 and 4: roof panels are being added to the structure.

aerial view of roof panel installation so far

crew members installing roof panels

Photo 5: framing, plumbing and conduit installation continue on the first floor.

first-floor framing and plumbing installation

Photos 6 and 7: exterior sheathing continues to be installed. Photo 6 shows a view from the interior of second-floor classroom areas. Photo 7 shows a view of the northeast corner of the building

interior view of building sheathing installation

northeast corner of building sheathing

Photos 1-3: sheathing is being applied to the exterior framing of the building; crew members cut pieces to fit around doors and windows.

northeast corner of framed building

crew applies a cut pieces of sheathing around exterior door

crew cuts sheathing to size

Photo 4: window and wall frames are reflected in the wet second-floor concrete; this area comprises the classroom section.

window and wall framing on second floor

Photo 5: a view of the learning street under construction, toward the east.

eastward view of learning street under construction

Photo 6: a view of the framing of the first-floor classrooms toward the southwest; conduit is being installed in the ceilings above.

southwest view of framed first-floor classrooms

Photo 1: this aerial view shows the progress of structural construction so far.

aerial view construction progress

Photo 2: external framing, starting in the northeast corner, includes spaces to install windows.

external framing of northeast corner of building

Photo 3: a view of the learning corridor to the west from the second floor; to the right is the gym and stage area and to the left are classroom spaces.

view to the west of learning corridor under construction

Photo 4: preparations continue toward another concrete pour of the second-floor decking

second-floor decking prepared for concrete pour

Photo 5: a view of the northwest corner of the building, where the main entry will be located.

northwest corner of AFES building under construction

Photo 1: the final half of the second-floor decking is being installed; the concrete for the floor slab is expected to be poured after Thanksgiving.

installation of second-floor decking

Photo 2: a view from the second floor down the learning corridor to the east (the gym is on the left).

view down the learning corridor

Photo 3: a crew member installs framing for the exterior wall of the building.

installing exterior framing

Photo 4: a crew member installs framing for the exterior wall of the building.

installing exterior framing

Photo 5: on the first floor, framing, plumbing and fire sprinkler pipe are being constructed.

first-floor framing and pipe

The beam signed by the community on Oct. 12, 13 and 15 is lifted, placed and welded to the entry area of the school building's structure. Although it will be eventually covered up as construction continues, the beam will lie overhead as visitors enter the building and will be an importance piece of the school's history.

Photo 1: this aerial view shows the work done on the school building so far. Concrete has been poured on the second-floor decking on the southeast side of the building (bottom right).

aerial view of AFES building construction

Photo 2: a crew member secures a roof joist to the structural steel.

crew member secures roof joist

Photo 3: an aerial view of the site construction; the staff parking lot is at the top left and the play field is at the top right of the campus. Beyond are the homes in the Sunset Ridge development

aerial view of AFES construction site

Photo 1: the sun was just starting to rise as work began for the day.

sunrise between ES28 steel beams

Photos 2-4: crew members smooth out fresh concrete on the second-floor decking as it continues to be poured in each section.

overhead view of second-floor decking

crew members smooth out freshly-poured concrete

overhead view of concrete pour and smoothing

Photo 5: crew members installing a ceiling joist are silhouetted against the rising sun.

installing ceiling joist at sunrise

Photo 1: the second-floor decking continues to be installed and prepared for next week's concrete pour.

preparing second-floor decking for concrete pour

Photo 2: roof trusses are also being installed between the structural steel.

roof truss installation

Photo 3: this birds-eye view shows the construction of the school building so far.

aerial view of building construction

Martin Granum, School Board member, started the event with an acknowledgment recognizing the Atfalati indigenous peoples' land. School Board Chair Erika Lopez provided remarks about the significance of ES28 to the North Plains and district community, describing special features of ES28, which joins the existing North Plains Elementary in educating the city's students. City of North Plains Mayor Teri Lenahan highlighted some historic aspects of North Plains education, noted the partnership between the city and the district, and the importance of the new school to a modern education for our children.

 

Highlights from the community beam signing:

An update to the Board on the name finalist for ES28, "Atfalati Ridge," can be viewed on the Board's meeting video for the Oct. 13 work session.

David Harrelson, the Tribal Historic Preservation Officer of the Confederated Tribes of the Grand Ronde, speaks to the Board about the history and culture of the indigenous people of the area.

Daria Bingham, Title VII Native American Program Manager for the District, shares feedback from the Native American Parent Advisory Committe.

Casey Waletich, Chief Operations Officer, also provides information on the upcoming mascot selection process.

Photos 1 and 2: decking has started to be installed between the first and second floors as welding continues on the structural steel beams.

installing inter-floor decking

welding interior steel beam

Photo 3: the skeleton of the gym continues to be built out as more girders and seismic bracing are installed.

gym structure skeleton

Photo 4: this aerial view shows construction progress so far. The area for the lighted, synethic turf field is to the left, the school building under construction in the middle, and the paved and striped staff parking lot is to the right.

aerial view of ES28 campus under construction

Photos 1 and 2: welders have started to secure the joint connections for the structural steel beams.

welding interior steel beams

welding perimeter steel beams

Photo 3: a crane stands ready to lift more steel girders for the building.

building structure waiting for more girders

Photos 1 and 2: steel trusses are being added to the top of the first-floor beams.

aerial view of truss erection

crew members place steel truss into position

Photo 3: the concrete benches on the south side of the gym have been poured; the stage area is to the right.

concrete benches and stage in gym area

Photos 1-3: structural steel for the building is starting to be erected, with a crane raising up each beam to be assembled and affixed by crew members .

aerial view of first structural steel assembly

steel beam being craned to position

crew members affix beam in place

Photo 4: the concrete benches for the gym continue to be built up.

concrete bench framing

Photo 5: this aerial view show the site construction work so far.

aerial view of ES28 construction site

Photo 1: framing for a gym bench is nearly finished and ready for a concrete pour.

concrete form for gym bench

Photo 2: concrete for the stage area already has been poured.

concrete stage area

Photo 3: utility connections stick up out of the building foundation.

utility connections in foundation

Photo 4: structural steel (at bottom of photo) is ready to be installed for the building.

aerial view of site with structural steel laydown

Photo 1: framing for curbs continues around the play field.

adding curb forms for play field

Photo 2: forms are being constructed for a gym bench. To the left, concrete has been poured for the stage area.

constructing form for gym bench

Photo 3: this aerial view shows the foundation completely poured (middle), utility trenching (bottom left), and continued work on curbing the play field (right).

aerial view of construction site progress

Photo 1: fence posts have been installed around the play field.

fence posts for play field

Photo 2: crew members start building the frames for concrete curbs that will be poured around the fence posts.

framing for curbs around fence posts

Photo 3: the foundation is about 75% poured, with the remaining section ready for concrete.

aerial view of nearly done foundation

Photo 4: this aerial view of the full site shows the progress to date.

aerial view of full ES28 site

Photo 1: crew members install reinforcing bars (rebar) for the next concrete pour for the foundation.

rebar installation for foundation

Photo 2: this aerial view shows areas of concrete already poured for the foundation as other areas are prepared for future pours.

aerial view of prepped foundation

Photo 3: now that the staff parking lot is done (top left of site), grading work is starting on the turf and multi-purpose fields (right side).

aerial view of full ES28 site

Photo 1: utility conduits are being installed as part of foundation work.

utility conduit installation

Photo 2: curbing is complete in the staff parking lot.

aerial view of staff parking lot curbing

Photo 3: site groundwork continues to build up the foundation and staff parking lot.

aerial view of ES28 site work

Photos 1-3: construction continues to build up the foundation footings, while curb has been poured for the staff parking lot and bus loading zone.

aerial view of ES28 site toward north

northeast corner of foundation

aerial view of staff parking lot construction

Photo 1: an aerial view shows work continuing to construct the building foundation as well as grading, at the upper left corner, of the area for the staff parking lot and bus loading zone.

aerial view of ES28 site toward north

Photo 2: trenching continues as foundation footings are being completed.

overhead view of building foundation

Photo 3: materials are being unloaded for the construction work.

unloading of materials

Photo 1: utility pipes are being laid in the foundation trenches.

aerial view of utility pipe installation

Photos 2-3: work continues to add to the foundation footings.

aerial view of foundation work facing southwest

northeast footings of foundation

Photos 1-3: construction continues on the ES28 site with foundation work and utility trenching.

aerial view of ES28 site construction

northeast corner of foundation work

north side of foundation work

Cement is poured into the forms for footings in the next phase of foundation work, with crew members directing the pour and smoothing out the poured concrete.

worker directs concrete pour

forms for footings getting concrete pour

crew member smooths concrete in form

Photos 1 and 2: aerial views of the current foundation work .

aerial view of fES28 sote

aerial view of northeast corner of foundation

Photo 3: more forms are being constructed for concrete pours.

form for concrete

Photos 4-5: finished footings

finished footing

compacting around footing

Photos 1 and 2: aerial views of the foundation work and current footings that have been poured.

aerial view of foundation construction

aerial view of northeast corner of foundation

Photos 3-5: crew members at work on different areas of the foundation, prepping for next construction steps.

crew members installing more rebar on footing

crew members adjusting footings

crew members cutting wood for forms

Foundation footings are more evident as the concrete forms continue to be framed and rebarred.

aerial view of foundation forms

oblique aerial view of southeast foundation corner

concrete form filled with rebar

Framing of concrete forms, including placement of rebar, for the foundation are being built throughout the site as trenching for utility lines continues.

framing of concrete forms

rebar placement in concrete form

worker building concrete form

rebar boxes for concrete form

utility trenching

Trenches have been cut and frames are being built to prepare for concrete pours for the foundation.

aerial view of site as of May 11

trenches and frames for foundation concrete pours

The footprint of the building is becoming more evident as grading continues. Utility pipes await upcoming trenching and installation.

grading outlines building footprint

aerial view of building footprint

Grading continues as trucks bring in more gravel onto the ES28 building site.

gravel trucks supply the site

aerial view of continued grading on the site

Cement treatment has been applied and sand/gravel is being laid and graded on the area for the parent parking lot and the building.

aerial view of construction site

aerial view of grading on site

Excavation has begun for the parent dropoff and parking lot, which will be followed by excavation for the building site and cement treatment.

aerial view of initial excavation

The general contractor is starting preliminary site work, including surveying and preparing for erosion control, in the Sunset Ridge development location of the school. Mobilization of equipment, excavation, and grading will follow.

This aerial view is from the north facing south toward Hillsboro.

aerial view of ES28 site

aerial view of initial work at ES28 site

View talking points and answers to frequently-asked questions regarding North Plains area enrollment growth and its impacts on the timing and construction of the new elementary school.

North Plains y la escuela primaria #28 - Informe actualizado sobre el proyecto de construcción del bono: puntos de discusión y preguntas frequentes.