Skip To Main Content

Project Archive

Virtual Preview / Guión del recorrido virtual

Dec. 18, 2020

A couple finishing touches have been added over the past month:

A monument sign at the entrance to the campus

Brookwood monument sign

A dedication plaque highlighting the year of final construction and the key people and firms behind the project implementation; this has been placed at the main entry to the school.

Brookwood dedication plaque

Brookwood dedication plaque

As reported by Max Egener and photographed by Jaime Valdez, view the article, "Brookwood Elementary: Hillsboro's first new bond-funded school," published in the "Hillsboro Tribune" on Aug. 22, 2020, by Pamplin Media.

Photo 1: synthetic turf has been laid for the play field; there is striping for youth soccer, baseball and softball.

aerial view of synthetic turf field

Photos 2 and 3: concrete walkways are being poured at the front of the school.

crew members smooth out fresh concrete

concrete pour at front of school

Photo 4: one of the buddy benches provides a prime view of the play field (this may be a temporary location).

buddy bench next to play field

Photo 1: the staff parking lot and bus dropoff (left side) has been paved and striped, while the parent dropoff/parking lot (right) is being prepared for paving.

aerial view of parking lots

Photos 2 and 3: concrete is being poured for the walkways on the east side and entryway of the building.

aerial view of concrete pour on east side of building

crew members pouring concrete for building walkways

Photo 4: near the play field, crew members build the forms for the concrete walkway there.

building forms for concrete walkway

Photos 5-6: student furniture has been delivered and placed in the primary (photo 5) and upper elementary (photo 6) classrooms.

primary classroom furniture

upper elementary classroom furniture

Photo 7: PE equipment has been stacked in the gym, waiting to be stored.

PE equipment in gym

Photo 8: carpeting has been laid in the learning areas.

carpeting in learning area

Photos 1-2: concrete work continues in the parking lot, playground area and the rest of the site.

concrete work in parking lot

form ready for concrete pour

Photo 3: base fabric and gravel are being laid on the new playing field to prepare for turf installation.

base fabric and gravel on play field

Photos 4-5: doors have been installed in the entry vestibule into the main office area.

entry doors

doors into main office

Photos 6-7: stainless steel equipment and walk-in refrigerators/freezers shine in the kitchen.

kitchen equipment

walk-in refrigerators/freezers

Site work:

Photos 1-2: a curb extruder applies the concrete around the perimeter of the parking lot as crew members smooth out the wet curb.

concrete curb extrusion

aerial view of curb work

Photo 3: concrete is being poured for the walkways near the covered play area and to the rear of the building.

concrete pour of walkways

Photo 4: the play field is being prepared for the turf base installation.

aerial view of play field under construction

Inside the building:

Photos 5-7: work is wrapping up inside the building, including installation and welding of stairway balusters, projector installation in classrooms, and final coats of paint.

installation of stairway balusters

installation of classroom projector

painting final coat

Final finishes continue to be applied inside the building, including office carpeting, final painting, and cleaning. Site work begins to refine the exterior spaces.

Photos 1 and 2: concrete is being poured for the base of the new playground. The holes are where the posts will be placed before rubberized tiles are installed over the base.

concrete pour for playground base

aerial view of playground base

Photo 3: gravel is craned to the top of the building for roofing.

gravel craned to rooftop

Photo 4: base rock is being added to the parking lot area.

base rock application and grading of parking lot

Photos 1 and 2: the Brookwood Bobcat benches have been placed along the walkway at the back of the school.

first pair of Brookwood benches

second pair of Brookwood benches

Photo 3: concrete has been poured for the outdoor learning area behind the school.

patio area behind the school

Photo 4: grading continues in the parking lot and play field areas.

aerial view of site work

Photo 5: a crew member constructs a concrete form on the west side of the building.

constructing concrete form

Photo 6: carpeting is starting to be laid in the main office and other office areas.

carpeting installating in main office

Photo 7: construction of the serving area continues in the cafeteria.

cafeteria serving area under construction

Photo 8: acoustic tiles have been installed and pads are being placed along the walls of the gym.

wall pad installation in gym

Photo 1: lines for basketball and volleyball have begun to be painted on the polished gym floor. The cafeteria beyond is nearly finished.

new gym sport lines

Photo 2: overhead electrical and security work continues in the main office area.

main office area

Photo 3: cabinetry is being installed in the media center.

cabinetry installation in media center

Photo 4: the main corridor receives the final painting.

painting of main corridor

Photos 5 and 6: tack and whiteboards have been installed in this classroom, and a panel along the door adds a touch of Brookwood red.

classroom view to windows

classroom view to hallway

Photos 7 and 8: exterior work continues around the building.

concrete forms behind building

front of school building

Photo 9: the field lights have been installed and crews excavate and grade the site to prepare for the synthetic turf field and parking lot. Demolition of the old school has been completed. (photo from June 2)

aerial view of site work

Photo 1: this aerial view shows the progress of demolition of the old building as interior and site work continue for the old building.

aerial view of full campus site as of May 12

Photo 2: the demolition crew separates out metal, concrete and wood so that they may be appropriately recycled.

separating out demolition material

Photo 3: in the kitchen area, appliances are being installed as the walk-in freezers are prepared for operation.

installation of kitchen appliances

Photo 4: the wood in the gym floor continues its conditioning before it is polished.

wood gym floor curing

Photo 5: wood panels have been installed in the classroom hallways.

wood paneling in hallways

Photo 6: a glass-enclosed "think tank" room is placed adjacent to an upper-grade learning area on the second floor.

glass-enclosed think tank room

Photo 7: the media center looks out to the rear of the campus.

media center under construction

Demolition continues on the main building ahead of schedule. Board members Lopez, Spross and Watson were joined by Superintendent Scott on Friday, May 8, to get their "bites" in on the kindergarten wing of the old building.

The process started on Monday, May 4, as Principal Caldwell initiated the first bites on the rear wing adjacent to the developing new school

The farewell to the old Brookwood has begun. Unfortunately, coronavirus-related restrictions prevented a formal good-bye.

Demolition had already started on the covered play area when the playground and then the portables were taken down. In their place will be the new synthetic turf field for the new Brookwood school. Preparation for the demolition of the existing building is expected to begin on Saturday, and actual demolition starting next week for the next several weeks.

Photo 1: this aerial view shows exterior work happening in many areas of the site, including: removal of the old covered play area (top left), installation of roofing on the new covered play area (bottom center), and framing for concrete pours of the new sidewalks behind the school (right).

aerial view of project site

Photo 2: crew members install remaining siding on the exterior of the building.

siding installation

Photo 3: flooring has been installed in the kitchen area.

kitchen area construction

Photo 4: installation of the wood floor continues like assembling puzzle pieces in the gym.

gym floor installation

Photo 5: the concrete floor in the main corridor is being smoothed.

concrete floor smoothing

Photo 6-8: cabinets and lighting are being installed in the classrooms; first-floor classrooms are nearly complete.

first-floor classroom with cabinetry

lighting installed in classroom

cabinetry installation in second-floor classroom

Photo 9: learning area.

learning area

Photo 1: glazing is placed between a classroom and the corridor.

glazing installation

Photo 2: at the rooftop, electrical and security conduit is being installed.

conduit installation

Photo 3: the concrete floor is being smoothed before polishing.

concrete floor smoothing

Photo 4: the wood floor is being laid in the gym.

wood floor installation in gym

Photos 5 and 6: cabinetry has been installed in the main office and is being installed in the classrooms.

main office cabinetry

classroom cabinetry installation

Photo 7 and 8: exterior work continues as a crew member installs the framing for the siding on the west wall and paint is being applied to the underside of the covered play area.

siding frame installation

painting underside of covered play area

One of several beams is placed by crew members on top of a post for the covered play area. Watch the video to see how this was done as well as progress on the building.

Watch the video showing project progress as of March 31, 2020:

Watch the video showing project progress as of March 23, 2020:

Photo 1: first floor classrooms have been painted and ceiling grids are being installed.

painted classroom with ceiling gridwork

Photo 2: crew members continue working on HVAC and windows in the gymnasium area.

gymnasium construction work

Photo 3: a view from the second floor of the building hallway, facing east.

building hallway

Photo 4: the east side of the building, near the entrance.

east side exterior

Photos1-4: Exterior weather proofing is installed and windows are sealed

sheetrocked classroom

exterior brickwork on Brookwood building

 

gym construction with basketball hoops

 

crew members working on gym windows

Photos 1-2: classrooms and the classroom hallway on the first floor have been sheetrocked.

sheetrocked classroom

sheetrocked classroom hallway

Photo 3: basketball backboards and hoops have been installed in the gym.

gym construction with basketball hoops

Photo 4: crew members are illuminated through the plastic sheeting currently on the gym windows.

crew members working on gym windows

Photo 5: a first-floor conference room ready to be painted.

nearly-finished conference room

Photos 6 and 7: ductwork installation continues on the second floor.

exposed HVAC ducts

workers cutting HVAC ducts to size

Photo 8: a crew member installs siding on the south side of the building.

installing siding on the building

Photos 1-3: sheetrocking has started in the gym area, and is nearly finished in the main office area and conference rooms in the northeast corner of the building.

sheetrocking gymnasium wall

sheetrocking on office wall

sheetrocking on conference room wall

Photos 4-5: installation of HVAC ductwork continues throughout the building.

installing HVAC ductwork

HVAC ductwork in classroom hallway

Photo 6: walk-in freezers have been installed in the kitchen area of the building.

walk-in freezers

Photos 1 and 2: sheetrocking has begun in interior offices.

sheetrocking interior office

patching sheetrock

Photo 3: a stack of sheetrock awaits installation in one of the classrooms.

classroom interior under construction

Photo 4: insulation in a hallway will be covered shortly.

exposed hallway insulation

Photos 5 and 6: outside, brickwork continues and crew members start applying spacers that will hold the exterior siding.

brickwork

applying exterior spacers

Photo 1: framing work continues in a classroom hallway.

hallway area construction

Photo 2: view of the gym from the cafeteria space.

view of gym under construction

Photo 3: installing HVAC ductwork in a classroom area.

ductwork installation in classroom area

Photo 4: construction continues in a classroom corridor.

classroom corridor construction

Photos 1 and 2: work continues on the building envelope as well as brickwork around the building.

northwest exterior corner of Brookwood construction

bricklayers at work

Photo 3: framing defines the hallway corridor.

framing of hallway corridor

Photo 4: framing and ductwork in the gym area.

framing and ductwork in the gym area

Photo 5: construction of the main office area continues.

main office construction

Photos 6 and 7: on the second floor, sheetrocking is being installed in the classrooms and learning corridors.

sheetrocked classrooms

workers installing sheetrock

Photo 1: roofing material is craned up to the rooftop.

craning of roofing material

Photo 2: a view of the interior corridor. The cafeteria and gym areas are on the left, and classrooms are on the right.

interior corridor under construction

Photo 3: workers are installing insulation and conduit in a classroom area. HVAC ducts await installation.

classroom area construction

Photo 4: on the second floor, classrooms are framed out.

second floor classroom framing

Photo 5: a crew member installs sheetrock on a classroom wall.

sheetrock installation

Photo 1: a metal worker applies welding to one of the stairways.

worker welding stairway

Photo 2: trimming and smoothing the structural steel.

trimming and smoothing the structural steel

Photo 3: a view of the second floor construction.

second floor construction

Photo 4: a crew member cuts framing for the building interior.

cutting steel framing

Photos 5 and 6: sheathing and moisture barrier are being installed on the building exterior.

installation of exterior sheathing

installation of exterior moisture barrier

Photo 7: verifying measurements of the exterior insulation

verifying measurements

Photo 1: interior corridor shows framing of cafeteria and gym to the left and classrooms to the right.

interior view of Brookwood construction

Photo 2: HVAC ducts are being staged in the cafeteria, awaiting installation.

HVAC ducts await installation

Photo 3: second-floor classrooms are being framed.

framing of second-floor classrooms

Photo 4: crew members work in the bathroom area.

construction in bathroom area

Photos 5 and 6: insulation blocks are being installed on the exterior of the building over the blue weatherproofing membrane.

several crews installing exterior insulation

pair of workers installing insulation block

Photo 1: stairs are being installed and welded in the west side of the building.

installation of steel stairs

Photos 2 and 3: a mockup of a classroom shows where tack and display boards will be placed.

mockup of tack board in classroom construction

mockup of display board in classroom construction

Photos 4 and 5: views from the second floor of the building.

second floor view to the west

second floor view to the east

Photo 6: a crew member cuts a piece of steel to add to the building frame.

cutting steel bar

Photos 7 and 8: views from the first floor of the building.

first floor view to the west

first floor view to the east

Testing of a manufacturer's window ensures the product passes the air and water leakage requirements. To test air leakage, a pressure differential is applied to the window. For the water test, 8 inches of rain and 41 mph (gale force) winds are simulated for 15 minutes against the window (this represents an unusual, very heavy rainstorm). The product passed both tests. Watch this video to see how the testing was done.

In the meantime, construction continues on the exterior and interior of the building. The following video provides the latest update.

Sheathing is complete around the exterior walls of the building. Watch the time-lapse video of construction so far, starting Aug. 1, then take a look at an inside view of the building.

Photos 1 and 2: sheathing in section B has begun, and crew members are verifying that frames are level

sheathing on exterior walls

verifying levels of wall framing

Photos 3 and 4: exterior and interior views of the entry and office area construction

exterior of entry and office area

interior construction of entry and office area

Photo 5: interior view of construction from the cafeteria area

cafeteria area construction

Sheathing has been installed on the walls in section A, and work continues on framing and installing wall panels in section B. Watch this video for aerial and interior views of the project.

Walls are being framed along the steel structure.

aerial view of Brookwood construction

crew members sort and assemble the wall struts

crew members install the wall struts

a crew member checks a wall strut

Floor and roof panels have been installed.

aerial view of Brookwood construction

Floor and roof panels are being installed on the steel beams in section B of the building.

installation of floor panels on steel beams

aerial view of Brookwood building construction

Crew members weld steel beams that will form the roof of the second section of the building.

welders at work on the roof frame

Brookwood construction site

Work continues on framing the second floor of the first section of the building, including part of the gymnasium, as steel is being erected for the next section.

welding steel on gymnasium frame

aerial view of second floor framing work

aerial view of Brookwood construction site

Crew members fasten the second floor frames to the first section of the structure to prepare for a concrete pour, as the beams start going up for the next section of the building.

aerial view of building framing

crew member fastens floor frame to structure

aerial view of building construction site

Crew members are midway through the installation of the second floor base in section A.

Installation of second floor base

Photo 1: a crane brings in cross-beams, three at a time, for the crew to weld, each in its place, to the steel frame.

installation of second-floor beams

Photo 2: aerial view of the installation of the second-floor beams.

aerial view of steel framing

Photo 1: workers smooth out concrete after it is poured into the foundation frame for the new building. It is a finely-choreographed routine that includes moving concrete into empty spaces, monitoring the proper depth, roughly smoothing with a wooden board, and then finely smoothing with a special tool.

workers smoothing poured concrete

Photo 2: an aerial view shows the area being worked on. The crew has to work quickly after the concrete is poured.

aerial view of workers smoothing concrete

Photo 3: an aerial view of the whole foundation and building site. Building of the structure will begin shortly after all the concrete has been poured and cured (hardened).

aerial view of concrete pour

Footings have been filled with concrete. Crews are trenching to install utility pipes and conduit.

Aerial view of Brookwood construction site

Crew members construct the forms for the foundation footings in section B as others add and compact gravel around the set footings in section A.

Working on foundation forms

Working on foundation forms

Compacting gravel around foundation footings

Compacted gravel around foundation footings

Photo 1: concrete pouring continues for the foundation footings in section A; section B is starting shortly

Photo 2: the area housing the former kindergarten portables has been demolished

aerial view of concrete pour for foundation footings

demolition of kindergarten portables

Concrete is poured into the footings for the building foundation. Crews smooth out the pour and continue to finish reinforcing the forms.

Crews work on pouring and smoothing concrete

Aerial view of concrete pouring of foundation

Reinforcing footing for foundation

Smoothing out poured concrete

 

Crews work on excavating the foundation for the building:

Aerial view of Brookwood construction site

Crews work on trenching

Trenches for foundation work

Preparations for foundation

The site for the new building is being filled with gravel, graded and compacted.

Brookwood site preparations

Gravel truck dumps its load

The construction area has been fenced off and equipment is being mobilized. The walkway on the south and west sides of the campus helps ensure that pedestrians are separated from the staging areas and vehicle traffic. For your safety, do not enter the fenced-off construction areas.

Brookwood construction zone and pedestrian walkway

Families, staff and community members enjoyed the spring sunshine as they celebrated the official launch of the project to build a new replacement school for Brookwood Elementary.

One of the common themes for speakers Dr. Michelle Jensen, Board member Erika Lopez, teacher Barb Nasewytewa, and student Carly Hernandez was to look forward to a modern learning environment in a bright 73,700 square-foot, two-story building and new play fields. The $40.5 million invested from the 2017 Bond will enable the school to accommodate up to 600 students in the growing community.

Fourth-grader Carly is especially looking forward to being in the first class of sixth-graders when the school opens for the 2020-21 school year. 

Another theme was the gratitude to all who made this possible, from the district leaders and the project staff who were involved in the early planning and design, to the community and voters who approved this investment in education.

Construction is expected to begin on May 1, 2019, and continue through August 2020.

DLR Group, architects for the new Brookwood Elementary School, has produced a virtual tour of the building.

Time Capsule Found!

Nov. 2, 2018 - The time capsule buried by first-graders in 1999 was unearthed. Due to damage to the container, the contents had to be retrieved earlier than directed by the students, and will be displayed at the school. Read more.

Brookwood Elementary School Time Capsule (1999)

Have we found the time capsule buried by Brookwood first-graders in 1999? A metal detector scan by our facilities staff seems to indicate so. Although we can't open it until Dec. 16, 2019, we will be digging it up on Friday, Nov. 2, at 8 a.m., in advance of the construction for the replacement school. Brookwood alumni and families are especially invited to attend - let's see what we find!

Brookwood Alumni Encouraged to Submit Photos

Photo of existing Brookwood Elementary School

June 11, 2018 - Are you an alumnus of Brookwood? We’d like to create a database of photos and memories from students who attended the school over its 65-year history. If you have things you’d like to share, please e-mail them to Bond Marketing Specialist Jane Siguenza at siguenzj@hsd.k12.or.us or by mail: 3083 NE 49th Place, #201, Hillsboro, OR 97124.

View Facebook post

Milestones

May 1, 2020 - demolition of the old school begins with the portables.

Aug. 9, 2019 - the final pour for the foundation slab.

June 20, 2019 - concrete poured into foundation footings.

May 6, 2019 - Mobilization of equipment has begun as crews prepare to start building on May 8.

April 29, 2019 - the school's groundbreaking ceremony was held to officially launch the project.

GROUNDBREAKING GALLERY