Skip To Main Content

Project Cost Estimates

These are the original estimates as presented in the bond promise. Scope may be added or subtracted as needs warrant and as opening up of buildings determines the full scope of needs. Project budgets will increase or decrease accordingly as well as adjust for prevailing costs of materials and labor. The project scope page has the most current information.

Goal / Project

Estimated Cost

security camera
Prioritize Safety and Security

School seismic upgrades

School safety upgrades

  • Interior door locks
  • Strobes, visual warning inside and outside
  • Security cameras
  • Improve line of sight from office to front door
  • Card key access - exterior doors
  • Local door alarms for outside doors
  • Alert button at front desk
  • Fire doors on alert button at front desk
  • Glass film at main door
  • Upgrade in-building radio communications

$2,520,000

368,845

  

building under construction
Renovate and Repair Aging Schools

Current Infrastructure Improvements

  • Boiler replacement
  • Roofing
  • Add air conditioning
  • Upgrade HVAC
  • Water pipe replacement
  • Direct digital controls

 

  • 587,447
  • 1,391,837
  • 1,278,521
  • 747,494
  • 616,092
  • 1,101,704

computer monitor; technology
 Provide a Modern Education for Every Student

Educational Technology (classroom)

  • CRT monitor replacement
  • Classroom projectors
  • Voice amplification
  • Wireless access points
  • Whiteboards
  • Document cameras
  • Student computers
  • Licensed staff computers
  • Classified staff computers
  • Student audio/video production devices - media/learning center

466,017

  

Student Achievement

  • Flexible classroom furniture

 

  • 364,017

Total Investment

$9,442,114