2018 - Playground, Furniture
The play area has been completed and ready for the start of school. A school alumnus tested it out and declared it "very nice" - the swings were his favorite.
August 21, 2018
Photo 2: The synthetic turf is being stretched across the play area, which creates a mud-free space for students.
August 14, 2018
Installation of the play structure is complete. Next steps are placement of rubberized tiles around the structure and installation of the synthetic turf play area.
August 7, 2018
July 31, 2018
July 24, 2018
July 16, 2018
Photo 1: The gravel base is poured as part of the foundation for the new play structure.
Photo 2: Flexible furniture in one of the classrooms.
July 10, 2018
July 3, 2018
June 26, 2018
Contractors have cleared the area for the school's new playground, which will have a new play structure and a rubberized tile surface for added safety.