2021 - Renovations
Photos 1-2: trees have been been planted in the plaza area and other areas have been hydroseeded. Small bushes and other plantings are next to come. As they establish, they will grow to provide a more dramatic and welcoming entrance to the school.
Photo 3: inside, work continues to install the elevator from the main floor to the cafeteria below.
Photo 4: security hardware is being installed for the entry doors; electrical and security cabling will follow.
Photos 1-3: exterior work is nearing completion as hydroseeding and landscaping are underway. This year, the school received a renovated front plaza, new bus dropoff, updated parent dropoff, new blacktop play area, and upgraded access trails from the neighborhoods to the campus.
Photo 4: inside, work continues to complete installation of the new elevator by mid-October.
Photo 5: hardware and security installation continue for the new entry vestibule.
Photo 1: the site is being prepared for upcoming paving.
Photo 2: students gather on the new blacktop play area adjacent to the playground where grass used to be. Two new basketball hoops were added.
Photo 3: crew members assess grading and compaction of the access trails from the south and east neighborhoods into campus as they prepare for paving.
Photo 4: preparations continue for one of the access trails south of the playground.
Photo 1: fresh soil has been applied to prepare for landscaping around the new walkways and plaza at the front of the school.
Photo 2: this aerial view shows remaining site work being done. Between the playground and parking lot, an irrigation line is being relocated. At the south of the campus, a trail is being constructed to the new access road being built.
Photo 3: a new access road, required by Clean Water Services, is being constructed to provide for vehicle passage between the parking lot and the swale at the south end of campus. The work is being managed by Washington County.
Photo 1: this aerial view shows the site work that is being completed around the campus. The bus loop at the top right is complete as well as the renovated dropoff area and parking lot.
Photos 2 and 3: a new plaza was constructed at the front of the school. Landscaping will be installed shortly.
Photo 4: the wall between the main office and the new ADA restroom is finished.
Photo 5: after the doors are installed, the new entry vestibule will help secure access into the building.
Photo 6: railings have been added to the reconstructed stairs. Plywood covers the area for the elevator shaft under construction.
Photo 7: work continues around the school schedule on the elevator pit and shaft; these will be covered up during school hours.
Photo 8: ceiling tiles now cover up the HVAC ductwork and upgrades in the media center. HVAC upgrades included the addition of air conditioning throughout the building.
Photo 9: in the cafeteria, HVAC is delivered via these wall units.
Photo 1: site work continues around the campus to wrap up before the start of school.
Photos 2 and 3: contractors fill forms with concrete for benches/landscaping containers at the front of the school building.
Photo 4: wiring of the new entry vestibule will connect to the security system.
Photo 5: work continues on the new stairs to the cafeteria to finish the construction.
Photo 6: the elevator pit will be covered up before the start of school.
Photo 1: this aerial view shows the extent of the site work on the campus.
Photo 2: paving has started in the parent dropoff/parking lot.
Photo 3: the bus loop is being compacted to prepare for paving.
Photos 4-6: the new concrete stairs to the cafeteria have been poured. Crew members set up framing for the bannister as another welds supports in place.
Photo 7: a crew member is installing a support frame for an HVAC cassette in the library.
Photo 8: in the main office, HVAC work is wrapping up. The wall between the office and the new ADA restroom has been sheetrocked and a security panel installed.
Photo 1: hardscaping (such as curbs and sidewalks) is being constructed around the renovated parent dropoff/parking lot.
Photo 2: to prepare for a concrete pour, the sidewalk area around the bus loop has been framed and the base gravel is being compacted. Bases for the new parking lot lights have been installed
Photo 3: a crew member installs an anchor for the door frame to the new ADA-accessible bathroom.
Photos 4-6: HVAC duct work and connections continue in the main office, library and classrooms.
Photo 1: bases for the parking lot lights have been installed, and crew members are framing for the nearby curbs.
Photo 2: this aerial view shows grading and more definition of the bus dropoff loop (at top) and the parent dropoff/parking lot renovation.
Photo 3: members of the School Board and Citizens Bond Oversight Committee tour the construction on campus as part of a series of project visits.
Photo 4: concrete has been poured over the underground plumbing lines in the new ADA-accessible restroom; framing of the room comes next.
Photos 5 and 6: crew members are installing the anchors for the elevator shaft that will allow ADA access into the cafeteria from inside the building.
Photo 7: a piece of HVAC duct is installed in the library ceiling.
Photos 1-2: most of the parent dropoff/parking lot and bus dropoff area has been excavated as trenching for underground utilities begins.
Photo 3: a new ADA-accessible restroom is being added adjacent to the main office.
Photo 4: work on the elevator shaft continues.
Photo 5: removed ceiling tiles in the library expose the HVAC ductwork being upgraded to add air conditioning.
Photo 6: HVAC condensate lines and new HVAC units and ventilation fans have been installed on the exterior of the building.
Photos 1-3: excavation continues in the dropoff/parking lot areas.
Photo 4: air conditioning units are being added throughout the building.
Photo 5: conduits for HVAC condensate lines are being installed in the walls.
Photo 6: excavation continues for the elevator footings adjacent to the cafeteria.
Photo 7: gravel is being smoothed out around the modular building to prepare for hardscaping.
Photos 1-2: old asphalt, walkways and curb are being demolished and removed from the current dropoff/parking lot area, and the pathway area is being excavated.
Photo 3: the area around the new modular building has been graded.
Photo 4: an air conditioning unit is being placed in the main office and other rooms. Condensate lines hang from the unit to be connected later.
Photo 5: a crew member installs conduit for the HVAC lines.
Photos 6 and 7: classrooms in the modular building are finished.
Photos 1-3: now that all sections of the modular building have been set, work is underway to install the roof and exterior trims as well as to finish the interior classrooms.
Photo 4: inside the main building, demolition of the ramp and stairs to the cafeteria area has begun. A new elevator and ramp will be constructed in their place.
Photos 5-6: new air conditioning units are being installed in the classroom and library ceilings.
Photo 7: a crew member works on conduit lines for the air conditioning.
Photos 1 and 2: foundation footings for the modular building have been poured and crew members begin removing the forms. Utilities are being trenched between the foundation and the school building.
Photos 1 and 2: surveying, measurements and staking are taking place to ensure proper placement of forms for the modular building's concrete foundation.
Photo 3: dirt is being backfilled in an area where old pipes have been removed.
Photos 1 and 2: excavation of the modular building site removes excess dirt and prepares the ground to begin building the foundation.
Photo 3: fencing, erosion control, pipes and other materials are ready to be installed.
The two portables near the playground area are being removed to make way for a new modular building and development of a new bus loop.
Photos 1 and 2: crew members prepare the remaining portable for transport.
Photo 3: the portable is positioned and ready to go.
Photos 1-3: exterior work is nearing completion as hydroseeding and landscaping are underway. This year, the school received a renovated front plaza, new bus dropoff, updated parent dropoff, new blacktop play area, and upgraded access trails from the neighborhoods to the campus.
Photo 4: inside, work continues to complete installation of the new elevator by mid-October.
Photo 5: hardware and security installation continue for the new entry vestibule.
Photo 1: the site is being prepared for upcoming paving.
Photo 2: students gather on the new blacktop play area adjacent to the playground where grass used to be. Two new basketball hoops were added.
Photo 3: crew members assess grading and compaction of the access trails from the south and east neighborhoods into campus as they prepare for paving.
Photo 4: preparations continue for one of the access trails south of the playground.
Photo 1: fresh soil has been applied to prepare for landscaping around the new walkways and plaza at the front of the school.
Photo 2: this aerial view shows remaining site work being done. Between the playground and parking lot, an irrigation line is being relocated. At the south of the campus, a trail is being constructed to the new access road being built.
Photo 3: a new access road, required by Clean Water Services, is being constructed to provide for vehicle passage between the parking lot and the swale at the south end of campus. The work is being managed by Washington County.
Photo 1: this aerial view shows the site work that is being completed around the campus. The bus loop at the top right is complete as well as the renovated dropoff area and parking lot.
Photos 2 and 3: a new plaza was constructed at the front of the school. Landscaping will be installed shortly.
Photo 4: the wall between the main office and the new ADA restroom is finished.
Photo 5: after the doors are installed, the new entry vestibule will help secure access into the building.
Photo 6: railings have been added to the reconstructed stairs. Plywood covers the area for the elevator shaft under construction.
Photo 7: work continues around the school schedule on the elevator pit and shaft; these will be covered up during school hours.
Photo 8: ceiling tiles now cover up the HVAC ductwork and upgrades in the media center. HVAC upgrades included the addition of air conditioning throughout the building.
Photo 9: in the cafeteria, HVAC is delivered via these wall units.
Photo 1: site work continues around the campus to wrap up before the start of school.
Photos 2 and 3: contractors fill forms with concrete for benches/landscaping containers at the front of the school building.
Photo 4: wiring of the new entry vestibule will connect to the security system.
Photo 5: work continues on the new stairs to the cafeteria to finish the construction.
Photo 6: the elevator pit will be covered up before the start of school.
Photo 1: this aerial view shows the extent of the site work on the campus.
Photo 2: paving has started in the parent dropoff/parking lot.
Photo 3: the bus loop is being compacted to prepare for paving.
Photos 4-6: the new concrete stairs to the cafeteria have been poured. Crew members set up framing for the bannister as another welds supports in place.
Photo 7: a crew member is installing a support frame for an HVAC cassette in the library.
Photo 8: in the main office, HVAC work is wrapping up. The wall between the office and the new ADA restroom has been sheetrocked and a security panel installed.
Photo 1: hardscaping (such as curbs and sidewalks) is being constructed around the renovated parent dropoff/parking lot.
Photo 2: to prepare for a concrete pour, the sidewalk area around the bus loop has been framed and the base gravel is being compacted. Bases for the new parking lot lights have been installed
Photo 3: a crew member installs an anchor for the door frame to the new ADA-accessible bathroom.
Photos 4-6: HVAC duct work and connections continue in the main office, library and classrooms.
Photo 1: bases for the parking lot lights have been installed, and crew members are framing for the nearby curbs.
Photo 2: this aerial view shows grading and more definition of the bus dropoff loop (at top) and the parent dropoff/parking lot renovation.
Photo 3: members of the School Board and Citizens Bond Oversight Committee tour the construction on campus as part of a series of project visits.
Photo 4: concrete has been poured over the underground plumbing lines in the new ADA-accessible restroom; framing of the room comes next.
Photos 5 and 6: crew members are installing the anchors for the elevator shaft that will allow ADA access into the cafeteria from inside the building.
Photo 7: a piece of HVAC duct is installed in the library ceiling.
Photos 1-2: most of the parent dropoff/parking lot and bus dropoff area has been excavated as trenching for underground utilities begins.
Photo 3: a new ADA-accessible restroom is being added adjacent to the main office.
Photo 4: work on the elevator shaft continues.
Photo 5: removed ceiling tiles in the library expose the HVAC ductwork being upgraded to add air conditioning.
Photo 6: HVAC condensate lines and new HVAC units and ventilation fans have been installed on the exterior of the building.
Photos 1-3: excavation continues in the dropoff/parking lot areas.
Photo 4: air conditioning units are being added throughout the building.
Photo 5: conduits for HVAC condensate lines are being installed in the walls.
Photo 6: excavation continues for the elevator footings adjacent to the cafeteria.
Photo 7: gravel is being smoothed out around the modular building to prepare for hardscaping.
Photos 1-2: old asphalt, walkways and curb are being demolished and removed from the current dropoff/parking lot area, and the pathway area is being excavated.
Photo 3: the area around the new modular building has been graded.
Photo 4: an air conditioning unit is being placed in the main office and other rooms. Condensate lines hang from the unit to be connected later.
Photo 5: a crew member installs conduit for the HVAC lines.
Photos 6 and 7: classrooms in the modular building are finished.
Photos 1-3: now that all sections of the modular building have been set, work is underway to install the roof and exterior trims as well as to finish the interior classrooms.
Photo 4: inside the main building, demolition of the ramp and stairs to the cafeteria area has begun. A new elevator and ramp will be constructed in their place.
Photos 5-6: new air conditioning units are being installed in the classroom and library ceilings.
Photo 7: a crew member works on conduit lines for the air conditioning.
Photos 1 and 2: foundation footings for the modular building have been poured and crew members begin removing the forms. Utilities are being trenched between the foundation and the school building.
Photos 1 and 2: surveying, measurements and staking are taking place to ensure proper placement of forms for the modular building's concrete foundation.
Photo 3: dirt is being backfilled in an area where old pipes have been removed.
Photos 1 and 2: excavation of the modular building site removes excess dirt and prepares the ground to begin building the foundation.
Photo 3: fencing, erosion control, pipes and other materials are ready to be installed.
The two portables near the playground area are being removed to make way for a new modular building and development of a new bus loop.
Photos 1 and 2: crew members prepare the remaining portable for transport.
Photo 3: the portable is positioned and ready to go.