Project Updates

Project Updates

Nov. 2020 - an article in the fall issue of "A Look Inside" highlights the results of the fiber optic project and impacts of bond investments in technology.

Feb. 5, 2020 - The District and City jointly commemorate the first connections to the HiLight fiber network service at an event held at Evergreen Middle School.

March 2019: construction is slated to begin on the City's dark fiber ring backbone.

Jan. 22, 2018 - first rollout of student technology (Chromebook carts) to schools is implemented, continuing through April 2018. 

Milestones

Aug. 31, 2020 - the final connection is made at Groner K-8; all 44 existing buildings are now online.

Feb. 5, 2020 - District and City officials jointly commemorate the first connections.

Feb. 19, 2019: City-HSD partnership formalized with signing of intergovernmental agreement.

Aug. 27, 2018: District and City enter into partnership to construct fiber optic network.

Jan. 22, 2018: first phase of technology rollout begins.