Dropoffs (2018)
March 26, 2019
Over spring break, crews are adjusting a couple curbs to make turns easier in the dropoff and exit areas.
Striping is complete and shows the new traffic flows that separate out cars and buses.
See the site map to view traffic flows and parking areas.
Landscaping will be added in the next few weeks.
Paving of the dropoff areas has been completed and parking stalls have been painted.
Photos 1 and 2: Crew members are paving the bus dropoff area with asphalt.
Photo 3: Paving of the parent dropoff area is almost done.
Milestones
Aug. 31, 2018 - parent/bus dropoff areas completed.
July 23, 2018 - work begins on parent/bus dropoff.
June 18, 2018 - mobilization to begin remodeling of parent/bus dropoffs and parking lot.