2019 Archive

Photo 1: the classroom hallway has been sheetrocked; HVAC ducts continue to be installed.

sheetrocked hallway

Photo 2: a crew member installs trim around the windows in a classroom.

window trim installation

Photo 3: inside, framing for the walls of the media center begins.

media center framing

Photo 4: outside, window frames for the media center await installation.

media center window frames

Photo 5: landscaping has been planted in the courtyard area.

landscaping of courtyard area

Photo 1: sheetrock is being installed on the classroom walls.

sheetrocked classroom

Photo 2: more ductwork and framing in the classroom hallway toward the media center.

construction in hallway area

Photo 3: crew members work on the rafters of the media center.

work on media center rafters

Photo 4: view of the media center construction toward the east.

media center construction

Photo 5: a concrete seating area adjacent to the main building.

concrete seating area

Photo 6: a crew member caulks and weatherproofs the window exteriors.

caulking of window

Photo 1: crews work on installing roofing material above the classroom area of the addition.

roofing work

Photo 2: roofing work is also being done over the media center area.

roofing over media center

Photo 3: the corridor from the commons into the addition is being framed.

corridor under construction

Photo 4: framing and ductwork continue in the hallway area.

media center hallway construction

Photo 5: a crew member installs electrical conduit in a classroom.

installing electricial conduit in classroom

Photo 6: insulation is being installed in the classroom areas.

insulation in classroom walls

Photo 1: the plaza area has been formed. The columns on the right will support an overhead canopy that protects the plaza area between the cafeteria and the media center. Windows are being installed in the classrooms sections.

plaza area

Photo 2: at the south end of the addition, beams have been completely installed and crew members work on the rest of the roofing framework for the media center.

workers framing roof of media center

Photos 3 and 4: HVAC ducts are beginning to line the tops of the classroom hallway and inside the classrooms.

classroom hallway under construction

classroom under construction

Photos 1 and 2: inside the building, moisture-resistant gypsum board is being installed over the wood framing that defines the classroom spaces, while plumbing work is underway.

sheetrock work

plumbing work

Photo 3: an aerial view of the building shows continuation of the roofing work, and columns erected for the plaza area.

aerial view of media center construction

Smoothing of the exterior concrete takes out the rough edges of the textures and scores (created by inserting fiberglass shapes into molds before the concrete walls were poured), while roofing work continues over the classroom spaces.

exterior concrete work

aerial view of Evergreen

Just a few more custom-cut joists to go ...

roof joists for Evergreen

Wood framing starts going up on the interior of the classroom walls.

wood frames ready for installation

wood framing installed on interior concrete walls

Work continues on framing the roof areas over the classroom spaces, and more joists have been custom-cut and craned in place over the media center area. HVAC ductwork is awaiting installation.

aerial view of Evergreen

framing of a classroom in the Evergreen addition

crew members working on the classroom roof joists

view of Evergreen

HVAC ductwork awaiting installation

Crew members work on the wood framing that outlines the classrooms spaces in the media center wing and take measurements to prepare for work in the other sections of the wing. Concrete has been poured to form the adjacent plaza area.

wood framing in media center construction site

measuring on concrete wall of media center

aerial view of media center construction site

Crew members continue constructing the forms for the concrete tilt walls.

Evergreen construction site

Evergreen construction site

Crew members continue to work on framing out the concrete tilt walls for the new media center, including cutting the wood, constructing the frames, and measuring (and re-measuring) the dimensions.

aerial view of media center construction site

cutting wood for frames

installing wood frames for forms

verifying wood frame dimensions

Photo 1: Sept. 3 was the first day of school for 7th-graders, who conduct an introductory activity in the newly-remodeled cafeteria area. Highlights are natural daylighting from the long skylight and a bright, polished concrete floor.

student activity in cafeteria

Photo 2: Gone now is the pit in front of the stage, which was leveled out to the rest of the floor and creates much more space for students.

view of cafeteria toward stage

Photo 1: construction has leveled out the pit area to expand the commons, and a new skylight provides natural daylighting.

Evergreen

Photo 2: solatubes brighten the hallways by bringing in natural daylighting.

Evergreen

Photo 1: aerial view of the construction area for the media center addition shows crew members constructing framing for the concrete footings.

Aerial view of media center addition construction area

Photo 2: this is what the framing looks like on the ground.

Construction of frames for media center footings

Photo 3: the back parking lot is under construction to provide additional staff parking during the school day.

Aerial view of back parking lot construction

Photo 4: roofing work continues; note the skylight being constructed on the left center over the commons area.

Aerial view of roofing work

Photo 5: the pit area is being demolished and will be leveled to expand the commons area.

Demolition of the pit area

Photo 6: hallways have been covered with special sheetrock to provide additional seismic bracing; crew members have begun painting as ventilation work continues overhead.

Hallway are painted as ventilation work continues overhead

Photo 1: Grading continues on the site for the media center addition and roof repair and reroofing begins.

Aerial view of Evergreen project site

Photos 2 and 3: Tiles have been removed from ceilings and sheetrock from walls to allow for upgrades to ductwork, wiring and shear walls.

Crews work on ceiling wiring

School hallway with exposed ceiling and wall

Photo 4: A new classroom (created from the old library) has been sheetrocked. Piping work continues.

Piping work in new classroom

Photo 5: The cafeteria area is being renovated.

Cafeteria renovations
 

All the concrete and grass areas have been removed from the area for the media center addition.

Media center construction area

The concrete has been broken up and excavated in the area for the new media center addition.

Evergreen construction site

Walls and doors in the new classrooms have been framed, and sheetrock is being installed on the interior walls.

Sheetrocking of classroom interior

Framing for exterior classroom door

In the old library, crews have demolished the interior and are now installing the framing, ductwork and cabling for six new classrooms. Some lockers were moved from the hallways to make way for future doorways into the classrooms.

Remodeling of old library
HVAC ducts for new classrooms
Installing ductwork in new classrooms
Framing for doorways to new classrooms

As work continues on demolishing the old library inside, crews stage equipment and materials in the outside courtyard. This area is now closed off and inaccessible to non-construction personnel.

Crews prepare for construction on the new library/media center

Crews are preparing the old library for demolition on April 29, to be replaced by the new library/media center addition.

Preparing for library demolition

Preparing for library demolition

Evergreen Middle School's bond project to expand the school was presented at a neighborhood meeting. Exhibits included the proposed site plan, building elevations, and floor plans. Attendees had the opportunity to ask questions of the project architects and consultants. See the meeting notes and exhibits.

Construction is expected to begin by summer 2019, subject to completion of design and construction documents, as well as land use and permit approvals. The project is expected to be completed in summer 2020.

Milestones

Sept. 23, 2019 - start erecting concrete tilt walls.

Aug. 30, 2019 - construction of interior renovations completed.

June 18, 2019 - renovation begins on interior hallways, cafeteria/commons, and existing classrooms.

June 6, 2019 - light grading and removal of the concrete in the area of the media center addition begins.

April 29, 2019 - demolition work on the old library has begun.