2019-21 - Additions/Improvements

July 30, 2021

Final touches were added following the substantial completion of major renovations, including:

  • A new monument sign at the main parking lot entrance to the school

new monument sign

  • And an updated entrance door for the counseling center.

counseling center entrance

Access security is also being added to the exterior theatre doors and the basement cafeteria area.

Principal Claudia Ruf hosts a virtual tour of the latest renovations at Glencoe High School, marking the completion of bond projects at the school.

Ver en español

Work on the Glencoe Road half-street improvements is complete. Traffic signals at the intersection of the north parking lot and Glencoe Road have been activated, improving the safety of pedestrians and vehicles at this important crossing. Note that there are now two lanes of exit from the parking lot.

aerial view of completed Glencoe Road improvements

aerial view of traffic signals at intersection

aerial view of completed north parking lot

Photo 1: paving on the campus half of Glencoe Road is complete and sidewalks have been re-constructed.

Glencoe Road improvements nearly complete

Photo 2: crew members are installing new landscaping along the improved street.

aerial view of landscape installation on Glencoe Road

Photo 1: Glencoe Road half-street improvements include installation of a new storm drain line, which is nearly complete. Paving is expected to start next week, weather permitting.

aerial view of Glencoe Road improvements

Photo 2: the traffic lights at the intersection of the north parking lot and Glencoe Road will be activated once the road construction is done. Note that there are now two lanes exiting from the parking lot to allow better queueing of drivers turning left or right onto Glencoe Road.

aerial view of north parking lot intersection

Photos 1-3: work in the north parking lot is nearly complete, with landscaping being installed. The tennis courts just got their nets and are ready to play on once facilities re-open.

aerial view of parent dropoff/student parking lot

aerial view of new tennis courts

aerial view of north parking lot area

Photo 4: exterior repainting will refresh outlying buildings, including the softball batting cage and dugouts.

repainting softball building

Photos 5 and 6: furniture has been delivered to the media center and health science classrooms in the building addition. The building trades classroom as well as the new classrooms on the renovated second floor also received new furniture.

furniture in media center

furniture in health science classroom

Photo 7: machinery is being placed in the building trades workshop.

machinery in building trades workshop

Photos 1 and 2: these aerial views of the north parking lot area show asphalt paving is completed and the tennis courts are ready for their overlay. Traffic signals will be placed soon at the entrance from Glencoe Road, where road improvements continue.

aerial view of north parking lot

aerial view of parent dropoff/parking area

Photos 3 and 4: crews scrub and prepare the tennis courts for upcoming overlay and striping as concrete is poured for the walkway between the courts and the back of the building.

scrubbing tennis court

pouring concrete walkway near tennis court

Photo 5: the courtyard area adjacent to the cafeteria addition is now fenced in, with landscaping to add a finishing touch.

cafeteria courtyard

Photo 6: painters add the finishing coat of Glencoe crimson over the primer on the roof of the existing cafeteria.

painting cafeteria roof

Photo 7: power cabling has been added to the nearly-finished construction trades workshop.

power cabling hanging in construction trades workshop

Photos 8 and 9: fume hoods have been installed between the science prep room and classrooms/labs, and countertops added to the classroom casework.

fume hood in prep room

science classroom/lab

Photo 1: crew members install LED lighting fixtures in the building entryway.

lighting fixture installation in entryway

Photo 2: another team determines the best way to mount the stairway barriers.

mounting stairway barriers

Photo 3: HVAC ductwork and ceiling have been painted, and lighting installed in the renovated construction trades area.

finishing paint and lighting in construction trades area

Photo 4: on the second floor, concrete floors are being polished in remaining classrooms.

concrete floor polishing in classroom

Photos 5-6: cabinetry and fume hoods are being installed in the new science classrooms.

cabinetry in new science classroom

fume hoods awaiting installation

Photo 7: sunlight shines through the finished skylights in a hallway on the renovated second-floor area.

sun shining through skylights

Photo 8: the new tennis courts have been paved and fine grading of the base is underway in the north parking lot.

aerial view of north parking lot

Photo 1: concrete has been poured for the curbs in the north parking lot, outlining the site.

aerial view of curb installation in north lot

Photo 2: a plaza area and sidewalks have been poured around the cafeteria addition.

plaza adjacent to cafeteria addition

Photos 3-4: in the renovated construction trades area, HVAC ductwork is complete and lockers have been added.

HVAC ductwork in construction trades area

lockers in construction trades area

Photos 5-7: skylights have been added to a hallway in the second-floor renovations, and lighting installed in the ceiling grids of hallways and classrooms.

skylights in second-floor hallway

lighting installed in second-floor hallway

lighting installed in second-floor classroom

Photo 1: Glencoe branding has been added to the cafeteria expansion.

branding mural on cafeteria beam

Photo 2: the restroom in the cafeteria expansion is getting some finishing touches.

finishing restroom in cafeteria expansion

Photo 3: in the old cafeteria, walls are being repaired and new sheetrock applied.

repair of old cafeteria walls

Photo 4: new HVAC ducts are connected on the second floor.

large HVAC ducts

Photo 5: polishing of the concrete floors and painting have started in the renovated second-floor classrooms.

polishing of classroom floor

Photo 6: a crew member installs the ceiling grids that will cover up ductwork and conduits.

installing ceiling grid

Photos 7-8: cement treatment is being added to reinforce the fill in the north parking lot; curbing will follow shortly. At the west edge of campus, work continues to improve Glencoe Road.

cement treatment in north parking lot

aerial view of north parking lot under construction

Photo 1: school signage has been added to the entry canopy.

Glencoe front entrance

Photo 2: fence posts surround the new site for the tennis courts, as grading for the south parking lot renovation continues.

aerial view of parking lot grading

Photos 3-5: concrete work along the west side of the school is complete, framing the team room, weight room and the building addition.

concrete walk in front of team room

concrete walk in front of weight room

concrete walk on west side of building addition

Photos 6 and 7: sheetrocking and new duct installation continue in the second floor renovations.

sheetrocked hallway

2nd floor classroom under construction

Photos 8 and 9: in the new media center, lights are installed and crews are finishing up ceiling features, including above the circulation desk and the acoustical "wings" in the main area.

ceiling work above circulation desk

unfinished acoustical wings in ceiling

Photo 10: staff and classroom belongings are being moved into the first floor of the addition.

moving in staff belongings

Finishes are being added to the building and cafeteria additions. Framing is complete for the new classrooms and labs on the second floor (conversion from the old library). Exterior site work continues, including the start of roofing over the entry canopy, installation of concrete pads at the entrances to the team and weight rooms, and renovation of the north parking lot.

Work continues in the cafeteria and building additions to complete construction in May.The old library on the second floor of the main building is being converted into new science labs.

Photo1: acoustic "sails" have been installed on the ceiling of the cafeteria addition; along with the wall panels, these will help dampen noise levels.

ceiling acoustic panels

Photos 2-3: crew members add finish to the drywall in the counseling office; carpet has been laid in this section (and covered for protection), as well as in offices and conference rooms.

drywall finishing

counseling office

Photo 4: cabinetry and other finishes continue to be installed in the health science classooms in the building addition.

health science classroom cabinetry

Photos 5-7: construction continues in the media center to add design features, including glazing in the hallway into the main building, which also overlooks the entry area (5), installing the frames for glazing for the study rooms (6), and cabinetry for the librarian's desk area.

hallway from media center into main building

installing glazing frames for study rooms

view behind librarian

Photo 8: crews grade the entry area at the front of the building to prepare for paving.

grading entry area

Photo 9: on the second floor of the main building, plastic tubing provides ventilation into the abatement areas of the former library.

temporary plastic ventilation tubing old library

Photos 1 and 2: work continues on the cafeteria addition as crew members paint acoustic tiles for the walls (1) and another mounts posts for paneling next to the east-facing door (2).

crews paint acoustic panels

worker mounts posts for paneling

Photo 3: the entry canopy has been installed between the addition and the existing building.

entry canopy installed

Photo 4: the counseling office on the first floor of the building addition is nearing completion.

counseling office construction

Photo 5: cabinetry is being installed in a health science classroom on the first floor of the building addition.

health science classroom cabinetry construction

Photo 6: work continues on second-floor media center to finish installation of HVAC and glazing, as well as sheetrocking and smoothing of the concrete floor.

media center construction

Photo 7: in the existing building, the old library is being demolished to make room for new science labs, and the other labs are being renovated on the second floor.

old library demolition

Crew members assemble the entry canopy for the building addition in the parking lot at the front of the school. Later this week, the entire canopy will be craned up and attached to the building. In other work, the old media center is undergoing demolition, a new water pipe has been trenched in the construction trades classroom area, and construction of the interior of the building addition continues. Watch the video to view project work to date:

Glazing and brickwork has been installed in the cafeteria addition while, inside, the floor is being polished. The construction trades classroom renovation (former weight room) is nearing completion. Work continues in the building addition housing the media center, health science classrooms and offices. Watch the video to view project work to date:

Team and weight rooms have been completed, while work continues in the cafeteria and media center/classroom additions as well as in the construction trades classroom renovation. Watch the video to view project work to date:

Photo 1: the weight room has been finished and equipment moved in for use by students.

finished weight room

Photo 2: the team room is ready for furniture move-in.

finished team room

Photo 3: work continues in the cafeteria addition to install HVAC and framing.

construction in cafeteria addition

Photo 4: conduit and wiring is being installed in the freshly-painted office area of the new media center.

construction of media center office area

Photo 5: HVAC ductwork and framing continue to be installed on the second floor of the media center addition.

construction of media center office second floor

Photo 6: a view from the top of the stairs of the media center addition to the school's future entry vestibule below.

construction of media center stairwell

Photos 1-3: Exterior work including outer walls and roof continue.

exterior work continues

exterior work continues

exterior work continues

Photos 4-5: Crews being to install HVAC.

HVAC installation

HVAC installation

Photos 1-3: continued work on the cafeteria addition.

northeast corner of cafeteria addition

interior of cafeteria addition

overhead piping in hallway area of cafeteria additiong

Photos 4-5: the team room is nearing completion.

exterior view of team room

interior view of team room

Photos 6-7: workers add finishing touches to the weight room addition.

exterior view of weight room addition

interior of weight room addition

Photos 8-9: framing of offices and classrooms continues on the first floor of the media center/classroom wing, while sheetrocking is starting on the second floor.

construction on first floor of media center addition

second floor of media center addition

Roofing and ductwork continue in the cafeteria addition:

roofers above the cafeteria addition

northeast corner of cafeteria addition

ductwork in cafeteria ceiling

cafetria view to the north

Construction of the additions continues on schedule; watch the project video to see the current status.

Photo 1: roofing asphalt has been partially applied over the media center/addition roof. The remainder is expected to be added, weather permitting, over winter break, after which roofing panels can be installed. Once the building has been "dried in," work on fireproofing and interior walls can begin.

aerial view of media center roof

Photo 2: crew members work on applying and smoothing out concrete over the metal framing to provide an even surface for the exterior panels.

smoothing out exterior concrete

Photo 3: roof decking has been installed over the entry corridor.

entry corridor under construction

Photo 4: brick is being laid around the exterior of the team room as sheetrock is being delivered and installed inside.

team room bricklaying

Photo 5: the cafeteria addition has roof decking installed, awaiting asphalt application.

northeast corner of cafeteria addition

Photo 1: the exterior of the building has been sheathed.

view of building sheathing

Photos 2 and 3: framing of the first and second floor interiors continues.

first floor construction

second floor construction

Photo 4: crew members work on the framing of part of the entry corridor.

entry corridor framing

Photo 5: brick is starting to be laid around the team room.

team room bricklaying

Photo 1: crew members hang wiring on the ceiling of the new weight room addition.

weight room under construction

Photo 2: work continues in the team room installing ducts and conduit.

team room construction

Photo 3: metal framing is cut to size and installed in the cafeteria addition.

cafeteria addition construction

Photos 4-6: rooftop HVAC units have been placed on top of the media center addition as framing and sheathing continue on the first and second floors.

aerial view of rooftop HVAC units on media center construction

first floor of media center construction

second floor of media center construction

Photo 1: the cafeteria addition is taking on more definition with wall and roof framing. The arrow indicates the location of the steel beam signed by community members on Sept. 26.

cafeteria addition under construction (view to north)

Photo 2: a view of the addition toward the adjacent, existing cafeteria.

cafeteria addition under construction (view to east)

Photos 3, 4 and 5: sheathing is enclosing the exterior of the media center addition while, inside, work continues on the steel framing of the first and second floors.

exterior view of media center construction

media center first floor construction

media center second floor construction

Photos 6 and 7: HVAC ductwork is being installed in the team room as work continues on the exterior.

ductwork installation in team room

framing work on team room window

Photo 8: in the weight room, HVAC ductwork is also being installed.

ductwork installation in weight room

Photo 1: an aerial view of the cafeteria addition after installation of steel beams for the roof.

aerial view of cafeteria addition

Photo 2: the steel beam, signed by community members, sits in the middle of the structure.

signed steel beam

Photo 3: HVAC ductwork is being installed in the team room.

HVAC ductwork in team room

Photo 4: sheathing now encloses the walls of the weight room.

sheathing encloses weight room walls

Photo 5: framing of the exterior border of the roof.

roof border framing

Photos 1 and 2: the concrete masonry walls for the cafeteria addition have been erected.

cafeteria addition walls

cafeteria addition hallway

Photos 3 and 4: walls are being framed in the team room addition.

team room addition wall framing

team room construction

Photos 5 and 6: weight room framing is being installed.

weight room addition framing

weight room construction

Photo 7: welding of steel beams in media center addition.

welding steel beam

Photo 8: building of stairs to the second floor of the media center addition.

building stairs

Photo 9: a view of the second floor of the media center addition.

second floor construction in media center addition

Photos 1 and 2: now that the roof deck panels are in place on the media center addition, the second floor base panels are being installed.

welder working on the second floor of the media center addition

aerial view of media center construction

Photo 3: the cafeteria addition masonry work continues.

aerial view of cafeteria addition construction

Photos 1-4: the metal roof panels have been installed as crew members continue welding on the steel structure.

aerial view of construction of media center addition

crew members working on the structure rooftop

crew member welds rooftop steel

crew member welds steel on the first floor

Photo 5: work on the team room continues after the roof beams have been fireproofed

team room under construction

Photo 6: the weight room is being prepared for fireproofing.

weight room under construction

Photo 7-8: reinforced concrete masonry blocks are being installed on the perimeter and entry area of the cafeteria addition

concrete masonry block installation

crew installs concrete masonry blocks

Photos 1 and 2: concrete masonry has been set to outline the walls for the cafeteria addition.

aerial view of construction of cafeteria addition

concrete masonry outlines the cafeteria wall construction

Photos 3-5: crew members check connections and weld the steel beams for the media center addition.

crew member checking steel beams

crew members welding steel beams

aerial view of construction of media center addition

Photos 6-7: work continues on the roofing and sides of the weight room and team rooms.

aerial view of construction of weight room addition

aerial view of construction of team room addition

Photos 1-3: a crane lifts steel beams to frame the new media center addition.

aerial view of media center addition construction

aerial view of media center addition construction

aerial view of media center addition construction

Photos 4-5: construction continues on the weight and team rooms.

aerial view of weight room construction

aerial view of team room construction

Photo 6: the cafeteria addition is taking shape with the foundation laid.

aerial view of cafeteria addition construction

OUTSIDE

Steel beams are being arranged around the media center site in preparation for the framing of the structure.

aerial view of media center construction site

The frame has been installed for the weight room roof.

aerial view of weight room construction

Decking has been installed on the team room roof.

aerial view of team room roof decking

INSIDE

Completed renovations in the student services office, main office, band storage/concessions, and the student store.

student services office

main office

band storage/concessions area

student store

Photo 1: the foundation has been poured for the new weight room, and workers start preparing for structural framing.

aerial view of weight room construction

Photo 2: the foundation in the second section of the media center addition has been poured.

aerial view of media center construction

The second section of the media center/classroom addition has been framed in preparation for the next concrete pour.

aerial view of construction site for addition

An aerial view of the south side of campus at the start of the school year.

aerial view of the south campus

Paving, striping and landscaping have been completed for the new parking lot on the south side of campus. Note the canopy at the side of the building over the sidewalk - this will help shelter students as they wait for the bus. Light poles are still pending installation.

aerial view of south parking lot

Video: Project update by Glencoe senior Andrew Goodwin

Photo 1: "Mount Glencoe" is filled with concrete excavated from various areas of the site. It will be ground up and repurposed to form part of the base in the south parking lot.

Mound of excavated concrete, aka Mt. Glencoe

Photo 2: Crew members work on strapping the new ventilation ducts in the school office.

Crews strapping HVAC ducts

Photo 3: The main entryway is being excavated and graded to prepare for the new addition. The crane lifts gravel to the rooftop.

Main entryway excavation

Photo 4: The student store is undergoing renovations to expand counters and casework, add sinks, and build a new opening. This is just one of many career-technical education spaces that will be worked on.

Student store renovations

Photo 5: Work continues in the early childhood education classroom to replace underground pipe as well as overhead HVAC ducts.

Pipe repair/trenching and HVAC ductwork

Video: Project update by Glencoe senior Andrew Goodwin

Photo 1: Walls in the main office have been demolished.

Main office demolition work

Photo 2: canopies adjacent to the gym and theatre have been removed to prepare for construction of the new weight room.

Removing canopies to prepare for weight room construction

The main office has been cleared out, the HVAC system and wiring exposed, and walls have been marked for demolition.

Main office has been cleared

HVAC ductwork and wiring

The old football shed has been demolished. The new, north parking lot will eventually extend into that area.

Old football shed demolished
 

During October and early November, the parking lots were redesigned based on an evaluation from our traffic engineers and other feedback. The latest design can be viewed in the site plans section.

A neighborhood meeting was held at Glencoe to preview the proposed designs for additions and renovations to the campus, accommodating a growing enrollment of up to 400 more students. The goal is to start construction in May 2019 and conclude by the end of summer 2020. Seismic retrofits are included as part of the improvements. BLRB architects answered questions from the audience - consolidated into primary, common themes here:

  • Land use process - plans will be submitted to the City of Hillsboro shortly; the City is likely to schedule public hearings and an opportunity for public comment in the next few months
  • Relocation/staging of students and classrooms during construction - a plan will be in place; this may not always be "comfortable," but the priority will be on protecting students, yet allowing them to safely observe progress
  • Improving safety - unsecured entry will be reduced with the new main entrance and vestibule design as well as by enclosing and connecting the cafeteria addition to the main building
  • Glencoe Road traffic - staff knows this is an issue and has commissioned a traffic study to evaluate flows; potential solutions for improvement will likely require funding beyond the current bond budget
  • Fire lane access (between gym and field) - concerns were raised about cars driving through and parking, as well as needed access for theatre loading; since this lane cannot be blocked, signage or other operational solutions will need to address these concerns
  • Band trailer storage/parking and theatre storage - this is a known concern as storage will need to be relocated
  • Traffic flow and congestion - concerns were raised about ingress/egress, numbers/idling of buses, neighborhood parking, crosswalk access in lots; expansion/redesign of the parking lots is expected to help alleviate these concerns (with minimal impact to existing mature trees) as well as the just-approved District policy ECG to minimize bus idling
  • Digital/technology/electrical access - additions/renovations will be constructed to the latest, state-of-the-art standards, including wireless access points and Chromebook cart plug-ins (Chromebook carts were already delivered in early 2018 as part of the first bond-funded technology roll-out)
  • Murals - graphic design instructor already has been in touch to potentially incorporate student-led designs

View the presentation here. Read Olivia Singer's article for Pamplin Media Group/Hillsboro Tribune.