Skip To Main Content

2021-22 Renovations

May 2, 2022

Photos 1-3: the structural frames for the dismantled temporary gym building are stacked and ready to be removed from the campus.

aerial view of dismantled gym building

stacked roof frames

structural frames stacked for removal

Photos 1 and 2: on Thursday, April 28, the front and back panels of the temporary gym have been removed.

removed front panel of temporary gym

removed back panel of temporary gym

Photos 3-5: on Friday, April 29, crew members start removing the back side panels and framing from the building. Work will continue through the weekend.

aerial view of temporary gym with back side panels removed

aerial view of south side of temporary gym with the first side panels removed

east side of temporary gym with first side panels removed

Photo 1: a crew member sweeps up the rubberized pellets that underlaid the synthetic turf in the temporary gym.

sweeping up rubberized pellets in temporary gym

Photos 2 and 3: all the synthetic turf has been removed from the temporary gym, rolled up and ready to be transported to storage.

synthetic turf removed from temporary gym

synthetic turf rolled up on truck

Photo 4: the renovations contractor is wrapping up in the cafeteria.

nearly-finished cafeteria

Photos 5 and 6: work remains in the kitchen by the restoration contractor to continue remediating the damage done by flooding last December, including stainless steel work and replacement of appliances.

school kitchen remediation

remediation in school kitchen

Photo 1: school branding decals have been affixed to one of the beams in the gym as well as a gym wall.

school branding on beam

Photos 2 and 3: this is the first day that students are able to have PE in their newly-renovated gym.

first day of PE back in gym

students enjoy PE in gym

Photos 4 and 5: downstairs in the cafeteria, crew members add fixtures, including dimmable lights, in the freshly-painted space. Unfortunately, it won't be completely open to students until the fall.

adding fixtures to newly-painted cafeteria

continuing installation of cafeteria fixtures and finishes

Photo 1: the new windows on the gym have been installed.

new gym windows

Photo 2: newly-painted doors provide a fresh entrance into the gym.

painted gym doors

Photos 3 and 4: the gym is fully painted and nearly finished with the attachment of the climbing wall and wall pads, and installation of the scoreboard and basketball hoops.

view of gym interior to the north

view of gym interior to the south

Photo 5: the Groner Grizzly mascot decal will soon be attached to a gym wall. Other decals will be placed on the first beam on the roof.

mascot decal to be attached

Photos 6 and 7: below the gym, painters add the finishing coat of paint to the renovated cafeteria.

painting renovated cafeteria

nearly-finished cafeteria renovation

Photo 1: the hallway into the gym has been painted and wall panels installed.

hallway into gym

Photo 2: painting and fixture installation are essentially finished in the gym; installation of new windows is pending. Groner logos will be applied to the first beam and on one of the walls.

painted gym

Photo 3: now that heavy lifts are no longer needed in the gym, the scaffolding has been removed from the cafeteria below. New ceiling is being installed.

cafeteria with scaffolding removed

Photo 1: fixtures and finishes are being applied in the gym. Hanging from the center of the gym is the new projector.

crew members at work in the gym

Photo 2: crew members apply acoustic panels to the walls to help deaden noise.

crew members apply acoustic panels

Photo 3: light fixture bases are being installed as painting continues.

crew members install light fixture bases

Photo 4: a crew member installs the motorized projection screen.

crew member installs projection screen

Photo 5: scaffolding remains in the cafeteria area while heavy equipment is being used in the gym. Finishes have started to be applied.

scaffolding in unfinished cafeteria

Photos 1-3: crew members are wrapping up the painting in the gym.

finishing up gym painting

crew member sprays paint on gym wall

the painting crew in the gym

Photos 1-3: all three beams are now secured to the building. Scaffolding has been removed, insulation has been added to the ceiling (it did not exist before), and crew members apply finishing touches to the drywall.

three beams in gym ceiling

new insulation and drywall installed in gym

crew member finishes drywall seams

Photos 1-4: the third and final beam is installed in the gym. Scaffolding will start to be removed from the gym as well as the cafeteria beneath as work is completed. Expected completion is around spring break, after which the temporary gym will be removed and the existing gym can be used again.

third beam hangs by crane

third beam inserted into gym window

crew member helps move beam inside

long view of beam installation and scaffolding

Photos 1-3: scaffolding is being removed after the second beam is secured. Crew members cut wood to frame the windows that were cut into the gym wall.

two beams installed in gym

crew members cut wood for window framing

crew member installs wood for window framing

Photos 1-3: the second of three beams is installed through another cutout in the gym and placed in the middle of the building. This is one of two beams that has student, staff and community signatures. The third, and final, beam with remaining signatures is scheduled to be lifted on Feb. 19.

second beam craned to gym cutout

beam gets extra lift

placement of beams in gym

Photos 4-5: signatures can be seen on the beam.

view of beam to south

view of beam to north

Photo 5: as each beam is secured to the building, scaffolding is removed.

exposed floor after scaffolding is partially removed

The first of three beams has been installed and painted in the gym. Crew members are now securing the beam in its permanent location. The video below shows how the beam was lifted by crane to a cut-out window and winched through to its location.

first beam installed in gym

securing the beam

Photos 1-3: students, families, staff and community members had an opportunity to sign their names on two of the three beams before they are installed in the ceiling of the gym, setting up a legacy for the future.

beam signing 1

beam signing 2

beam signing 3

Photos 1-3: seismic work continues in anticipation of the first new beam installation on Dec. 11. Scaffolding supports the existing roof framework until all the new beams are installed.

seismic work on gym roof, southeast

sesmic work on gym roof, northeast

scaffolding supports on roof beams

Photos 1-3: in the school gym, demolition work has begun to expose beam and trusses in advance of new beam installations and remaining seismic work.

scaffolding in gym

exposed gym wall near roof

cross-bracing of roof

Photo 4: the new lift to the stage is fully assembled and operational.

assembled and operational lift to stage

Photos 1-3: the temporary gym is open! The happy noise of active children can be heard outside the gym. Inside, PE class involves a bit of running on the synthetic turf and, yes, throwing of some rubber chickens. It took a team of adults in service of the children—from project managers to County and TV Fire staff to contractors—to provide a safe, warm and dry space for PE in just a few months, especially with the winter months approaching, while the school gym is undergoing repairs.

exterior of temporary gym

PE students inside temporary gym

PE activities inside temporary gym

Photos 4 and 5: at the front of the school, the new entry vestibule provides added security for monitoring access into the school.

entry security hardware

entry vestibule

Photo 6: work continues on wiring the new ADA lift adjacent to the stage. In the background, scaffolding for gym repairs can be seen.

wiring for new lift

Photos 1 and 2: door hardware and ramps have been installed at the front of the temporary gym. Inside, heaters and fans keep the gym warm and cozy. The base is ready for turf installation as soon as the turf crew is available.

front of temporary gym

unfinished interior of temporary gym

Photo 3: the hallway to the gym has been painted and paneling installed on the walls.

finished gym hallway

Photo 4: the new lift will provide ADA accessibility to the stage. Plastic covering protects the lift from the painting currently underway.

new lift access to stage

Photos 4 and 5: the elevator is ready for final electrical and phone line connections, and finishing of the cafeteria level.

finished elevator, main floor

elevator, main floor

Photos 1 and 2: newly-installed drywall is finished up in the hallways near the gym and new elevator. This area is expected to continue to be closed off to students and staff while the gym repairs are in progress.

drywalled hallway near gym

finishing drywall near new elevator

Photo 3: in the temporary gym, fine gravel has been laid to even out the base for the turf. Heating units stand by to be connected to temporary power.

temporary gym construction

Photo 1: the exterior of the temporary gym is nearly complete with the addition of the end panels and doors.

exterior of temporary gym

Photo 2: inside, the floor base has been compacted and edged. Fine gravel will be added to the base, upon which synthetic turf will be installed once it can be delivered. Heating units also will be installed. The temporary gym is expected to be completed by the end of October.

interior view of temporary gym

Photo 3: crew members bring in drywall sheets to finish the hallway next to the existing gym.

bringing in drywall sheets

Photo 4: steel beams are being designed and manufactured to supplement and support the gym's roof trusses, currently supported by scaffolding.

scaffolding supporting roof truss

Photo 5: to the right of the stage, a new lift is being assembled to provide access for those with disabilities.

assembly of stage lift

Photo 6: a crew member adds finishing touches in the new elevator shaft.

finishing up in elevator shaft

Photo 1: the temporary gym is situated at the back of the school near the playground. Once the erection is complete, students will have a covered area for PE while the existing gym is undergoing structural repairs.

aerial view of temporary gym

Photo 2: the primary supports and exterior have been erected.

interior view of temporary gym under construction

Photo 3: crew members work on installing one of the roll-up doors.

installing roll-up door

Photos 1 and 2: scaffolding looks like a metal forest as it supports the gym roof while structural repairs are being made.

scaffolding supporting roof

exposed gym roof undergoing repairs

Photo 3: scaffolding has been completed in the lower-level cafeteria to help support the gym above.

scaffolding in cafeteria

Photo 4: doors have been installed on the main level as work continues to finish the elevator.

installed elevator doors

Photo 5: down below, the lift mechanism has been installed for the elevator.

installed elevator lift

Photo 1: once completed, the new secure entry vestibule will allow office staff to monitor and limit access into the building.

new entry vestibule

Photo 2-4: the finished hallways in the building are refreshed with new trim and paint after seismic and other upgrades.

main school hallway

lower-level hallway 1

lower-level hallway 2

Photos 5-6: work continues to finish the new elevator, including the shaft on the main and lower levels as well as the pit at the bottom.

upper elevator shaft construction

upper elevator pit construction

Photo 7: shoring has been added in the cafeteria to support repairs in the gym above it.

shoring in cafeteria

Photos 1 and 2: on Thursday, April 28, the front and back panels of the temporary gym have been removed.

removed front panel of temporary gym

removed back panel of temporary gym

Photos 3-5: on Friday, April 29, crew members start removing the back side panels and framing from the building. Work will continue through the weekend.

aerial view of temporary gym with back side panels removed

aerial view of south side of temporary gym with the first side panels removed

east side of temporary gym with first side panels removed

Photo 1: a crew member sweeps up the rubberized pellets that underlaid the synthetic turf in the temporary gym.

sweeping up rubberized pellets in temporary gym

Photos 2 and 3: all the synthetic turf has been removed from the temporary gym, rolled up and ready to be transported to storage.

synthetic turf removed from temporary gym

synthetic turf rolled up on truck

Photo 4: the renovations contractor is wrapping up in the cafeteria.

nearly-finished cafeteria

Photos 5 and 6: work remains in the kitchen by the restoration contractor to continue remediating the damage done by flooding last December, including stainless steel work and replacement of appliances.

school kitchen remediation

remediation in school kitchen

Photo 1: school branding decals have been affixed to one of the beams in the gym as well as a gym wall.

school branding on beam

Photos 2 and 3: this is the first day that students are able to have PE in their newly-renovated gym.

first day of PE back in gym

students enjoy PE in gym

Photos 4 and 5: downstairs in the cafeteria, crew members add fixtures, including dimmable lights, in the freshly-painted space. Unfortunately, it won't be completely open to students until the fall.

adding fixtures to newly-painted cafeteria

continuing installation of cafeteria fixtures and finishes

Photo 1: the new windows on the gym have been installed.

new gym windows

Photo 2: newly-painted doors provide a fresh entrance into the gym.

painted gym doors

Photos 3 and 4: the gym is fully painted and nearly finished with the attachment of the climbing wall and wall pads, and installation of the scoreboard and basketball hoops.

view of gym interior to the north

view of gym interior to the south

Photo 5: the Groner Grizzly mascot decal will soon be attached to a gym wall. Other decals will be placed on the first beam on the roof.

mascot decal to be attached

Photos 6 and 7: below the gym, painters add the finishing coat of paint to the renovated cafeteria.

painting renovated cafeteria

nearly-finished cafeteria renovation

Photo 1: the hallway into the gym has been painted and wall panels installed.

hallway into gym

Photo 2: painting and fixture installation are essentially finished in the gym; installation of new windows is pending. Groner logos will be applied to the first beam and on one of the walls.

painted gym

Photo 3: now that heavy lifts are no longer needed in the gym, the scaffolding has been removed from the cafeteria below. New ceiling is being installed.

cafeteria with scaffolding removed

Photo 1: fixtures and finishes are being applied in the gym. Hanging from the center of the gym is the new projector.

crew members at work in the gym

Photo 2: crew members apply acoustic panels to the walls to help deaden noise.

crew members apply acoustic panels

Photo 3: light fixture bases are being installed as painting continues.

crew members install light fixture bases

Photo 4: a crew member installs the motorized projection screen.

crew member installs projection screen

Photo 5: scaffolding remains in the cafeteria area while heavy equipment is being used in the gym. Finishes have started to be applied.

scaffolding in unfinished cafeteria

Photos 1-3: crew members are wrapping up the painting in the gym.

finishing up gym painting

crew member sprays paint on gym wall

the painting crew in the gym

Photos 1-3: all three beams are now secured to the building. Scaffolding has been removed, insulation has been added to the ceiling (it did not exist before), and crew members apply finishing touches to the drywall.

three beams in gym ceiling

new insulation and drywall installed in gym

crew member finishes drywall seams

Photos 1-4: the third and final beam is installed in the gym. Scaffolding will start to be removed from the gym as well as the cafeteria beneath as work is completed. Expected completion is around spring break, after which the temporary gym will be removed and the existing gym can be used again.

third beam hangs by crane

third beam inserted into gym window

crew member helps move beam inside

long view of beam installation and scaffolding

Photos 1-3: scaffolding is being removed after the second beam is secured. Crew members cut wood to frame the windows that were cut into the gym wall.

two beams installed in gym

crew members cut wood for window framing

crew member installs wood for window framing

Photos 1-3: the second of three beams is installed through another cutout in the gym and placed in the middle of the building. This is one of two beams that has student, staff and community signatures. The third, and final, beam with remaining signatures is scheduled to be lifted on Feb. 19.

second beam craned to gym cutout

beam gets extra lift

placement of beams in gym

Photos 4-5: signatures can be seen on the beam.

view of beam to south

view of beam to north

Photo 5: as each beam is secured to the building, scaffolding is removed.

exposed floor after scaffolding is partially removed

The first of three beams has been installed and painted in the gym. Crew members are now securing the beam in its permanent location. The video below shows how the beam was lifted by crane to a cut-out window and winched through to its location.

first beam installed in gym

securing the beam

Photos 1-3: students, families, staff and community members had an opportunity to sign their names on two of the three beams before they are installed in the ceiling of the gym, setting up a legacy for the future.

beam signing 1

beam signing 2

beam signing 3

Photos 1-3: seismic work continues in anticipation of the first new beam installation on Dec. 11. Scaffolding supports the existing roof framework until all the new beams are installed.

seismic work on gym roof, southeast

sesmic work on gym roof, northeast

scaffolding supports on roof beams

Photos 1-3: in the school gym, demolition work has begun to expose beam and trusses in advance of new beam installations and remaining seismic work.

scaffolding in gym

exposed gym wall near roof

cross-bracing of roof

Photo 4: the new lift to the stage is fully assembled and operational.

assembled and operational lift to stage

Photos 1-3: the temporary gym is open! The happy noise of active children can be heard outside the gym. Inside, PE class involves a bit of running on the synthetic turf and, yes, throwing of some rubber chickens. It took a team of adults in service of the children—from project managers to County and TV Fire staff to contractors—to provide a safe, warm and dry space for PE in just a few months, especially with the winter months approaching, while the school gym is undergoing repairs.

exterior of temporary gym

PE students inside temporary gym

PE activities inside temporary gym

Photos 4 and 5: at the front of the school, the new entry vestibule provides added security for monitoring access into the school.

entry security hardware

entry vestibule

Photo 6: work continues on wiring the new ADA lift adjacent to the stage. In the background, scaffolding for gym repairs can be seen.

wiring for new lift

Photos 1 and 2: door hardware and ramps have been installed at the front of the temporary gym. Inside, heaters and fans keep the gym warm and cozy. The base is ready for turf installation as soon as the turf crew is available.

front of temporary gym

unfinished interior of temporary gym

Photo 3: the hallway to the gym has been painted and paneling installed on the walls.

finished gym hallway

Photo 4: the new lift will provide ADA accessibility to the stage. Plastic covering protects the lift from the painting currently underway.

new lift access to stage

Photos 4 and 5: the elevator is ready for final electrical and phone line connections, and finishing of the cafeteria level.

finished elevator, main floor

elevator, main floor

Photos 1 and 2: newly-installed drywall is finished up in the hallways near the gym and new elevator. This area is expected to continue to be closed off to students and staff while the gym repairs are in progress.

drywalled hallway near gym

finishing drywall near new elevator

Photo 3: in the temporary gym, fine gravel has been laid to even out the base for the turf. Heating units stand by to be connected to temporary power.

temporary gym construction

Photo 1: the exterior of the temporary gym is nearly complete with the addition of the end panels and doors.

exterior of temporary gym

Photo 2: inside, the floor base has been compacted and edged. Fine gravel will be added to the base, upon which synthetic turf will be installed once it can be delivered. Heating units also will be installed. The temporary gym is expected to be completed by the end of October.

interior view of temporary gym

Photo 3: crew members bring in drywall sheets to finish the hallway next to the existing gym.

bringing in drywall sheets

Photo 4: steel beams are being designed and manufactured to supplement and support the gym's roof trusses, currently supported by scaffolding.

scaffolding supporting roof truss

Photo 5: to the right of the stage, a new lift is being assembled to provide access for those with disabilities.

assembly of stage lift

Photo 6: a crew member adds finishing touches in the new elevator shaft.

finishing up in elevator shaft

Photo 1: the temporary gym is situated at the back of the school near the playground. Once the erection is complete, students will have a covered area for PE while the existing gym is undergoing structural repairs.

aerial view of temporary gym

Photo 2: the primary supports and exterior have been erected.

interior view of temporary gym under construction

Photo 3: crew members work on installing one of the roll-up doors.

installing roll-up door

Photos 1 and 2: scaffolding looks like a metal forest as it supports the gym roof while structural repairs are being made.

scaffolding supporting roof

exposed gym roof undergoing repairs

Photo 3: scaffolding has been completed in the lower-level cafeteria to help support the gym above.

scaffolding in cafeteria

Photo 4: doors have been installed on the main level as work continues to finish the elevator.

installed elevator doors

Photo 5: down below, the lift mechanism has been installed for the elevator.

installed elevator lift

Photo 1: once completed, the new secure entry vestibule will allow office staff to monitor and limit access into the building.

new entry vestibule

Photo 2-4: the finished hallways in the building are refreshed with new trim and paint after seismic and other upgrades.

main school hallway

lower-level hallway 1

lower-level hallway 2

Photos 5-6: work continues to finish the new elevator, including the shaft on the main and lower levels as well as the pit at the bottom.

upper elevator shaft construction

upper elevator pit construction

Photo 7: shoring has been added in the cafeteria to support repairs in the gym above it.

shoring in cafeteria

Photos 1 and 2: crew members install paneling in the hallways and start removing floor protectors in the finished areas.

installing wall paneling

removing floor protectors in finished hallway

Photo 3: boards are re-installed in finished classrooms.

finished classroom

Photo 4: security cabling hangs from exposed ceilings, ready to be threaded through and connected.

security cabling installation

Photo 5: a crew member continues work at the bottom of the elevator shaft, which now has concrete walls erected.

crew member working in elevator shaft

Photo 6: concrete has been freshly poured to restore the floor above the shaft.

main floor restoration at elevator shaft

Photo 7: the entry vestibule is nearly finished.

nearly-finished entry vestibule

Photos 1 and 2: painting has begun in the hallways and in the classrooms.

painted hallway

painting started in classroom

Photos 3 and 4: walls on both sides of the new entry vestibule have been sheetrocked .

nearly-finished entry vestibule (looking inside)

nearly-finished entry vestibule (looking outside)

Photo 5: ADA access to the stage is being constructed.

ADA access construction

Photo6: work continues in the elevator shaft to frame and construct the concrete walls.

framing for elevator shaft walls

Photos 1 and 2: seismically-upgraded hallways have been sheetrocked, taped and drywall mud applied to prepare for painting.

sheetrocked walls in south hallway

sheetrocked walls in main hallway

Photo 3: crew members tape and mud sheetrocked walls in the classrooms after seismic upgrades.

drywall taping and mud applied to classroom wall

Photo 4: in the gym, the Groner blue is being painted around the stage area.

painting around stage area

Photo 5: walls are adjusted around the plumbing in restrooms.

adjusting walls around restroom plumbing

Photo 6: work continues in the entry vestibule area, including framing of the interior door.

entry vestibule construction

Photo 7: crew members build a frame for the sump pump in the elevator shaft; rebar will be added around it for an upcoming concrete pour.

elevator shaft construction for a sump pump box

Photo 8: roofing material is lifted to the top of the roof.

lifting up roofing material

Photos 1 and 2: seismic upgrades have been applied in the school hallways; sheetrocking is starting to be installed.

hallway walls before sheetrocking

hallway walls after sheetrocking

Photo 3: crew members are covering up walls in the classrooms.

covering up classroom wall

Photos 4 and 5: domestic water pipe is also being worked on throughout the building.

exposed piping in a restroom

crew member works on copper plumbing

Photo 6: rebar and framing are starting to be constructed in the elevator shaft for an upcoming concrete pour.

rebar and framing in elevator shaft

Photo 7: work continues to construct the secured entry vestibule, including installation of security cabling and electrical conduit.

entry vestibule construction

Photos 8 and 9: walls are starting to be covered up in the gym and on the stage.

covering gym seismic upgrades

covering stage wall

Photos 1 and 2: walls in the gym and stage area have been stripped to prepare for seismic upgrades there.

gym with stripped walls

stage area with stripped walls

Photo 3: a crew member works deep in the elevator shaft.

elevator shaft work

Photos 4 and 5: walls also have been stripped in the hallways and specific areas in the classrooms. Plastic sheeting encloses the classroom areas to prevent dust and debris from reaching into the rest of the classroom.

hallways with stripped walls

classroom with stripped wall enclosed in plastic

Photo 6: roofing work is nearly complete on the north section of the building.

nearly-completed roofing work

Photo 1: work begins on the roof to apply seismic upgrades and eventual reroofing.

roofing work

Photos 2 and 3: the elevator shaft continues to be constructed. Removal of the concrete floor in this section has exposed the basement area underneath.

working on elevator shaft

exposed basement area

Photo 4: shoring supports the roof over the gym area.

shoring supports in place

Photo 5: a new vestibule is being framed at the main entrance to the building. Additional security will help monitor access.

framing for entry vestibule

Photos 1 and 2: with the concrete floor removed, the level underneath is exposed and work can begin on the elevator shaft. .

elevator shaft under construction

exposed level under cut floor

Photo 3: walls in the school hallway are exposed in preparation for seismic upgrades.

exposed hallway walls

Photos 1 and 2: saw-cutting has started to break up part of the concrete floor above the lower level to create an elevator shaft for ADA access.

concrete saw-cutting operation

saw-cut pieces of stairway

Photo 3: an electrical panel and associated wiring will be removed on the lower level to make way for the elevator door.

removing electrical wiring

Photos 4 and 5: select walls are being exposed to allow access for seismic upgrade work.

crew members review work for walls

exposed classroom wall