Project Updates

Dec. 23, 2021

Photos 1 and 2: the fire lane has been completed, including installation of a new gate and signage.

fire lane gate

fire lane signage

Photo 1: the new ADA-accessible restroom is painted and ready for fixtures to be installed.

ADA restroom under construction

Photos 2 and 3: the final seismic upgrades are installed in the gym ceiling.

crew member installs seismic upgrades

seismic bracing

Photos 1 and 2: seismic work is nearly complete in the gym and stage area.

seismic work in stage ceiling

seismic work in gym ceiling

Photos 3 and 4: in the basement, the finished seismic work included bracing between the lateral beams as well as shoring underneath.

seismic bracing in basement ceiling

supportive shoring in basement ceiling

Photo 5: new lighting fixtures complete the renovations in the basement.

new lighting fixtures in basement

Photo 6: walls in the new ADA restroom are taped and drywall mud applied to prepare for painting and installation of fixtures.

finishing walls of ADA restroom

Photos 1 and 2: skirting and ramps have been added to the portables; next are electrical and low-voltage hookups as well as carpeting installation.

portable 1 skirting

portable 2 skirting

Photos 3 and 4: after application of seismic bracing, plywood board is being installed to re-cover the ceilings.

seismic bracing in ceiling

boarded-up ceiling after seismic upgrades

Photos 1 and 2: bracing and reinforcements have been added to the roof the gyms, which will bring the building up to current "safe exit" seismic standards.

bracing on gym roof

closer look at seismic bracing on gym roof

Photos 3 and 4: sheetrock is being installed on finished areas.

sheetrocking reinforced ceiling

sheetrocking reinforced walls

Photos 1 and 2: seismic upgrades continue in the gyms.

seismic upgrades in gyms

crew member installs seismic bracing in gym roof

Photo 3: in the basement, temporary structural shoring is in place to provide extra support for the building while work continues.

temporary structural shoring in basement

Photo 1: seismic upgrades are underway in the gyms as bracing is installed on the roof trusses.

seismic upgrades in gyms

Photo 2: all four sections of the portables that were moved from North Plains Elementary are now in place on the Peter Boscow campus.

portable buildings

Two portables (four sections) were relocated from North Plains Elementary to the Peter Boscow campus

Photo 1: bracketing and rods such as these will be attached between roof and wall areas to provide additional seismic reinforcement.

brackets and rods used for seismic reinforcement

Photo 2: a crew member spotlights one of the areas for reinforcement in a mechanical room.

spotlighting seismic reinforcement area

Photo 3: installation of brackets and rods has already started in this classroom ceiling.

seismic brackets and rods installed in ceiling

Photo 1: strapping is being applied to ceiling beams in the basement areas for added seismic reinforcement.

ceiling strapping in basement area

crew members apply seismic strapping to ceilng

ceiling strapping in boxing club area

Photo 1: crew members demolish a ceiling in the basement area to prepare for seismic upgrades.

demolition work in basement area

Photo 2: a sewer pipe has been trenched in the basement that serves the new ADA restroom on the floor above.

new sewer pipe in basement

Photo 3: a new ADA restroom is being constructed on the main floor of the building, just off the entrance from the ADA ramp.

ADA restroom under construction

Photos 1-3: work on seismic reinforcements begins in the basement after removal of sheetrock and abatement to expose the ceiling studs.

Peter Boscow basement after abatement

crew members affix brackets to the ceiling studs

crew member works on seismic bracing

Photos 1-2: brackets and bracing have been added to seismically reinforce the ceiling of one of the upstairs classrooms.

upstairs classroom with ceiling reinforcement

closer view of reinforcing brackets and bracing

Photo 3: in the other upstairs classroom, reinforcements also are being added.

seismic reinforcement in upstairs classroom

Photos 1-3: seismic reinforcement upgrades have started early at the Peter Boscow building, home of Hillsboro Online Academy. In the unoccupied rooms upstairs, brackets and wood bracing are being added to the ceilings.

upstairs room at HOA being upgraded

crew member installs reinforcing brackets

reinforcing brackets up close

Photo 4: Downstairs, in the basement's boxing club area, wood is ready to be installed for the seismic work.

basement are to be upgraded

Peter Boscow roofing project
Roofing upgrades are being installed at the Peter Boscow building, home of Hillsboro Online Academy.

Milestones

March 2021: seismic upgrades begin.

July 2018 — roofing upgrades begin