2019 - Parking Lot
Aug. 19, 2019
The dropoff areas and parking lot have been paved and striped.
Photo 1: the striping shows dropoff and through lanes for buses (nearest the school) and a separate exit to the west, and two lanes for parent vehicles (dropoff lane and through lane).
Photo 2: an additional parking lot to the right of the entrance provides spaces for staff and visitors.
Photo 1: as asphalt is poured into the paver, it is deposited and leveled to a specific depth; crew members ensure a smooth installation. The roller will compact the asphalt even more.
Photo 2: the dropoffs/parking lots prior to paving; the gravel and soil have been compacted to prepare for the paving.
Aerial views show how the dropoffs and parking lot areas are beginning to be outlined with concrete curbs.
Photos 1 and 2: aerial views of the grading and compaction of the bus and parent dropoff area and the new staff/visitor parking lot.
Photo 3: crew members prepare a hole to place the concrete base for a parking lot light pole.
Photos 1 and 2: The front sidewalk is being excavated.
Photo 3: Stormwater pipe will be installed in trenches below the parking lot.
Photos 1 and 2: excavation and grading of the dropoffs/parking lot for parents (1) and for buses and staff (2) are underway.
Photo 3: the reconstruction of Jacob's Field is nearly complete. The infield area has been graded and graveled; it is now awaiting the turf installation.
The southeast ball field is being excavated to prepare for construction of the new parking lot area. A replacement field is currently being built in the northeast corner of the campus.
Due to delays in the permitting process, the parent/bus dropoff project has been postponed to summer 2019. The relocation of Jacob's Field is also being rescheduled.
A backhoe and excavator have been mobilized and stand ready to begin the remodel of Jackson's parent/bus dropoff area, which is expected to be completed by the end of August.