2018 - Dropoffs, Modular
2018 Project Updates
Photo 1: The parent dropoff is located at the front of the school.
View the site map for more information and directions.
Photo 2: A separate bus dropoff has an entrance off of Darnielle at the west side of the school.
Photo 3: Teachers prepare the preschool classroom in the new modular building.
The dropoff areas are being paved.
Inside one of the three classrooms in the new modular building
Curbing and grading continue in the bus dropoff area.
Walkways are being constructed along the bus dropoff area.
The new modular building for McKinney is being placed and assembled. The three sections of the building will house spaces for three classrooms.
The foundation is ready for McKinney's new modular building.
As soon as the school year ended, our contractors began clearing the area around the portables and prepared for demolition and removal. The portables will be replaced with a new, three-classroom modular building behind the school.