2021 - Playground, Entry Vestibule, Covered Play
Sept. 8, 2021
Photos 1-2: the new playground is finished and ready for students on the first day of school.
Photos 1-2: crew members install the new playground equipment and the rubberized tiles that provide a cushioned surface.
Photos 1-2: the concrete has been poured for the playground base, with holes created for placing the equipment posts.
Photos 1-3: curbs have been poured around the playground perimeter and the base gravel compacted. The round forms will create holes in an upcoming concrete pour to guide placement of the playground equipment and swingset.
Photos 1 and 2: forms for the concrete curbs outline the playground area.
Photos 1 and 2: crew member start framing the playground curb for an upcoming concrete pour.
Photo 3: security hardware has been installed at the main entry to the school to monitor and secure access into the building.
Photos 1 and 2: excavation and grading of the new playground has started.
Photo 3: re-roofing of the covered play area canopy is complete.
Photos 1-2: crew members install the new playground equipment and the rubberized tiles that provide a cushioned surface.
Photos 1-2: the concrete has been poured for the playground base, with holes created for placing the equipment posts.
Photos 1-3: curbs have been poured around the playground perimeter and the base gravel compacted. The round forms will create holes in an upcoming concrete pour to guide placement of the playground equipment and swingset.
Photos 1 and 2: forms for the concrete curbs outline the playground area.
Photos 1 and 2: crew member start framing the playground curb for an upcoming concrete pour.
Photo 3: security hardware has been installed at the main entry to the school to monitor and secure access into the building.
Photos 1 and 2: excavation and grading of the new playground has started.
Photo 3: re-roofing of the covered play area canopy is complete.