August 31, 2018

North Plains portables

With one each moved from Patterson and Reedville, the two portables stand on the west side of the campus.

July 25, 2018

ADA ramp at North Plains portables

The ADA ramp has been installed between the two portables. Stairs are on the other side.

July 17, 2018

Work on North Plains portables

Siding has been placed to enclose the foundation and the crew is starting the installation of the ADA ramp and stairs.

July 9, 2018

Portables were relocated from Reedville and Patterson Elementaries to North Plains. These portables provide additional classrooms for the school's growing enrollment, until the new, second elementary school is constructed in the North Plains area (expected summer 2021).

Milestones

July 9, 2018 - portables were relocated from Reedville and Patterson.