Project Scope

Timeline for Orenco projects


Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Total costs: $1.1 million

COMPLETED

  • Entry Vestibule

The main entry into the school was remodeled in summer 2022 to incorporate enhanced security measures, including better monitoring of visitors, requiring check-in at the main office, and additional vestibule doors to secure entry into the rest of the building.

  • Security Fencing

Security fencing and gates were completed in May 2022 along the west side of the playground to help prevent children from running into the parking lot.

  • Flexible Furniture

Orenco classrooms received flexible furniture (FFE) in summer 2019. Research shows this type of furniture enhances the learning environment and increases student engagement.

  • DAS

A distributed antenna system (DAS) ensures that first responders can communicate between themselves throughout all areas of the building. This safety-related project incorporates cable and antennae that boost the radio signals on the first responders' operating frequencies. This project was completed in March 2019.

Project Managers

Cornerstone Management Group

  • Entry vestibule: John Abel / Luke Harkness
  • Fencing: Luke Harkness
  • FFE: Karyn Rainone

Architect

  • Entry vestibule: Process PDX

Contractors

  • Entry vestibule: Inline Construction
  • Fencing: Dick's Evergreen Fence and Deck
  • FFE
    • McDowell-Craig (desks)
    • School Specialty (seating)