Project Updates

Aug. 18, 2020

Crew members have installed reinforcing braces in the tunnels underneath the building's hallways and are now fastening and tightening the braces.

reinforcing braces installed in tunnel

checking the installation of bracing

tightening the fasteners

These tunnels underneath a couple of the hallways in the building will be reinforced over two weeks to resolve some sagging of the floors.

tunnel 1 under Poynter

tunnel 2 under Poynter

Photo 1: ceiling tiles have been installed in the nearly-complete phase 4 renovation at Poynter.

phase 4 hallway renovation

Photo 2: walls have been sealed up to cover the conduit for HVAC units in classrooms.

HVAC unit in classroom

Photo 3: the small, auxiliary gym has been freshly-pained.

small gym painting complete

Photos 1 and 2: ceiling tiles are being installed to cover the underlying pipes and conduit in the phase 4 hallway.

ceiling tile installation in Poynter hallway

crew member installs ceiling tile

Photo 1: the walls are installed and ready to be painted, as overhead work continues in the phase 4 section.

phase 4 hallway renovation

Photo 2: the classroom HVAC units are operational; on this cold, wintry day, the heat was running nicely.

classroom HVAC unit

Phase 4 renovations continue. Walls are being sheetrocked and insulating sheathing is being added to plumbing pipes.

phase 4 hallway renovation

crew member adds sheathing to pipe

Phase 4 renovations started at the end of October, with expected completion by Dec. 20, 2019, two months ahead of schedule.

phase 4 hallway renovation

classroom HVAC unit being installed

Phase 3 renovations have been completed.

completed phase 3 hallway

completed phase 3 locker area

Phase 3 renovations are nearing completion.

renovated phase 3 hallway

nearly-completed phase 3 classroom

Photos 1-4: renovations in the phase 3 section are underway.

classroom under renovation

hallway under renovation

renovations in hallway

ceiling work in hallway

Photos 1 and 2: students arrive for their first day of school in the renovated sections of the building and try out their new lockers.

renovated hallway

renovated hallway

Photo 3: the soffit (top left corner of photo) in the cafeteria was completely finished before the start of school.

finished soffit in cafeteria

Photos 1 and 2: a new secure entry doorway is being installed in the main office area.

new secure entry

inside of secure entry doorway

Photo 3: a soffit is being framed that will eventually hide the underlying pipework in the cafeteria area.

soffit framing

Photo 4: a phase 1 hallway is getting the finishing touches.

renovated hallway

Photo 5: phase 2 work continues.

hallway under renovation

Photos 1 and 2: overhead seismic and roofing work.

overhead seismic and roofing work

worker on exposed beams

Photo 3: a finished classroom with new HVAC unit to bring in air conditioning.

finished classroom with new HVAC unit

Photo 4: ceiling tiles are being installed to finish a phase 1 hallway.

ceiling tile installation

Photo 1: a phase 1 hallway is nearly complete.

renovated hallway

Photo 2: demolition work has exposed the underlying structure in a phase 2 hallway.

demolition work

Photo 3: crew members unload HVAC ducts to bring into the building.

workers unloading HVAC ducts

Photo 4: in the gym, the HVAC ductwork is being upgraded.

HVAC ductwork in gym

Photos 1 and 2: work on the roofs continues.

aerial view of roofing work

roofing work

Photos 3 and 4: phase 1 renovations are progressing along.

phase 1 renovation progress

phase 1 renovation progress

Photo 5: insulation has been removed and cleanup of demolition debris continues in the phase 2 sections of the building.

phase 2 demolition work

Photo 1: old roofing is removed to prepare for replacement of the decking and reroofing.

worker tears up old roofing

Photo 2: HVAC ductwork is being installed in the gym to bring in air conditionining.

overhead HVAC ductwork in gym

Photo 3: a crew member adds a tape finish to the drywall in the phase 1 wing.

tape-finishing drywall

Photo 4: phase 2 is underway as crew members demolish the underlying walls in preparation for seismic upgrades.

demolition of old walls

Photos 1 and 2: the wood floor is completely installed in the small gym and awaits final sanding and coating, while work in the main gym continues.

Wood floor installed in small gym

Wood floor removal in large gym

Photos 3 and 4: domestic water pipe is being replaced throughout the building.

Copper pipe replacements in ceiling

Copper pipe replacement in bathroom

Photo 5: electrical conduits and wiring are being installed in the ceiling.

Conduit installation in ceiling

Photo 1: New wood flooring is being installed in the small gym, replacing the flooring from the '60s that was original to the building.

Gym floor installation

Photo 2: Roofing work continues, which includes repairs, adding new insulation (white stacks) and reroofing.

Poynter roofing renovations

Photo 3: Inside the main building, walls and ceilings are exposed so that seismic and HVAC ductwork can be done.

Poynter renovations in hallways

Photo 4: Copper pipes are replacing the old domestic water piping.

Poynter pipe replacements

Portables are being installed on the north side of campus. These will house temporary classrooms, beginning in the fall through the end of construction, as interior classrooms in the building are being renovated with seismic, HVAC, roofing and other upgrades.

Installation of portables

View of portable building being installed

Interior of a portable classroom

Crews continue with the roofing upgrades above the small gym; work is about 50 percent complete in this area.

Reroofing of small gym

Crew member drills holes for roofing

Crews cut boards for small gym roof

First phase of renovations:

Contractors prepare for roof work
Photo 1: contractors prepare for roofing upgrades

Exposed ceiling
Photo 2: ceilings have been exposed to allow for seismic, electrical and HVAC work

small gym renovations
Photo 3: the small gym and workout room are getting new floors and seismic, electrical and HVAC upgrades

The library/media center is all packed up to prepare for seismic, roofing and HVAC upgrades (first photo) and work continues in the small gym area (second photo).

Poynter library renovations

Poynter small gym renovations

Poynter small gym floor replacement

The floor in the small gym is being replaced as part of the first phase of Poynter's renovations

Milestones

Oct. 28, 2019 - phase 4 renovations begin.

Sept. 3, 2019 - phase 3 renovations begin.

Aug 30, 2019 - phase 2 completed in time for start of school.