Project Scope
Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $1.9 million
COMPLETED
- Flexible Furniture
In summer 2020, South Meadows received new flexible furniture (FFE) in the classrooms that stimulates engagement and learning.
- Security Cameras, DAS
Installation of security cameras enhances safety and security in the building. A distributed antenna system (DAS) ensures that first responders can communicate between themselves throughout all areas of the building. This safety-related project incorporates cable and antennae that boost the radio signals on the first responders' operating frequencies. Installation of these safety and security measures was completed in summer 2018.
NOTE: the electric generator upgrade originally planned was not undertaken due to the high cost of bids that greatly exceeded the available budget.
Project Managers
Cornerstone Management Group
- Renovations: John Abel / Luke Harkness
- In-building radio communication/DAS: Todd Johnson
Architects/Engineers
- Renovations: PAE Engineers / Process Engineering
- DAS: AWS Communications
Contractors
- Renovations: tbd (bid date Feb. 10, 2022)
- DAS: Reece
- FFE
- McDowell-Craig (desks)
- School Specialty (seating)