Project Updates
Dec. 29, 2022
Photos 1-2: all of the new garage doors have been installed on the mechanical bays.
Photos 1-3: new garage doors have arrived and are being installed as part of the building improvements.
Photos 1 and 2: concrete has been sealed, and the new hydraulic lifts are covered while electrical connections are completed.
Photos 3 and 4: painting is being completed around the new sliding glass window and rolling window in the dispatchers' office.
Photos 1 and 2: the new hydraulic lifts are being installed in their pits.
Photo 3: the storage area for waste oil has been finished off with a cover and protective bollards.
Photo 4: the new skylights bring much-needed natural daylighting into the mechanics' bays.
Photo 5: glazing has been added to the dispatchers' office window.
Photos 1 and 2: materials are loaded onto the rooftop in preparation for roofing work.
Photo 3: the pits for the hydraulic lifts are ready for their upcoming installation.
Photos 1 and 2: skylights are being added to the roof of the mechanics' bays to bring in more natural daylighting.
Photo 3: as seen from below, the skylights have a screen that prevents anyone on the rooftop from falling through.
Photo 4: a crew member works on adjustments beneath a skylight.
Photo 5: the concrete floor in the mechanics' bay is dried and finished; the hydraulic lifts are expected to be installed next week.
Photo 6: a new window is being added to the dispatchers' office area to add daylighting.
Photos 1 and 2: concrete for the floor has been poured and is being smoothed by crew members.
Photos 1 and 2: rebar has been installed to prepare for an upcoming concrete slab pour for the floor.
Photo 3: conduit also has been laid in a trench for electrical connections between the hydraulic lifts and power source.
Photo 4: a crew member wires secured door access to the security system.
Photo 1: a crew member trims along the edges of the walls of the left-side concrete base for a hydraulic lift.
Photo 2: the right-side trench is ready for installation of a lift.
Photo 3: the tank for waste motor oil is being installed in an excavated trench.
Photo 1: concrete slabs have been poured in the trenches for the new lifts.
Photo 2: crew members touch up the concrete slab pour in the right-side trench.
Photo 3: additional boring and excavation for another trench is taking place outside the bay.
Photos 1 and 2: trenches have been dug in the mechanical bays for the new lifts.
Photo 3: rebar has been laid out to install in the trench framing to support the upcoming concrete pour.
Concrete has been removed from a mechanics' bay to prepare for digging and other work to install new lifts.
Building renovations are underway, starting with sawcutting of the concrete floors in the mechanics' bays to prepare for installation of new lifts and other equipment.